Beruflich Dokumente
Kultur Dokumente
Other types of base On occasion: tiles are laid on asphalt. Examples include, its use for exterior verandahs, and asphalt employed as 'tanking' in basements. Factors to consider; it may retard the drying out of bedding laid on top; variations in the surface level, and tendency for plastic flow to occur in warm conditions. Other surfaces on which a tile fixer may be asked to lay tiles include existing tiled floors, terrazzo, granolithic and natural stone, and metal surfaces; these types of bases are only infrequently encountered, but the procedure to be adopted is the same as described for wall tiles.
Floor Screeds
There are four types of screed for dense concrete.
12 25 mm
1. Monolithic construction This is a case where a screed is laid in-situ on a concrete base before it has set (within 3 hours of placing) thus obtaining a complete bond. A screed thickness of 12 mm is considered adequate and layers thicker than 25 mm should be avoided.
40 mm
2. Separate construction In this case the screed is laid after the base has set and hardened. A minimum thickness of 40 mm is considered sufficient provided the base has been adequately prepared to receive the screed.
Not to scale
Fig 2 Separate Construction Screed placed more than 3 hours after base.
3. Unbounded construction Where a damp-proof membrane is used or the concrete is contaminated with oil or grease, or if it is weak concrete; the minimum thickness for the screed should be 50 mm or if the floor contains heating cables at least 65 mm. 4. Floating Screed A screed laid on a compressible layer of thermal or soundinsulating material should be at least 65 mm thick. The floating screed is usually on 20-50 mm mesh wire netting resting on polythene sheeting over the layer of insulating material. If the screed is to contain heating cables then it should be at least 75 mm thick. Mix proportion for screeding up to 40 mm thick should be 1;3/4 cement and sand. For thicker screeding fine concrete should be used 1;1;3 (cement; fine aggregate : course aggregate). If there is difficulty in finishing the concrete it can be topped up with a layer of cement and sand about 5-10 mm thick placed before the concrete has set. Other Materials used for screeds These include synthetic anhydrite, lightweight aggregate concrete, and screeds, modified by the inclusion of polyacetate, synthetic rubber, etc. Where tiles are to be laid on such screeds then the suppliers of the screed material should be consulted, and it should be established whether or not there is likely to be any incompatibility with the proposed method of laying.
50 mm min.
60 mm min.
1. 2. 3. 4. 5. 6. 7.
Check water level is working correctly. Note that the level of water in both tubes should be the same. If not correct, there is an air-lock in the tubes. Hold end of tube under the water tap and force water through the tube to remove the air-lock. Mark off position of the datum. With assistance, use the water level with the stoppers in. Hold one end of tube to the mark whilst assistant holds the other end in the approximate position where level mark is required. 8. Remove stoppers and assistant adjusts the height of his tube until the height of water is level with the datum mark 9. Assistant marks the level of the water in his tube. 10. Repeat process to all corners of the room. 11. Snap lines to these marks by using the chalk line.
Lay Wood Screeds Beded in Cement and Sand Levelled in from Datum
1. 2. 3. 4. 5. 6. 7. 8. 9.
Wood battens 20 mm x 50 mm to thickness of the screeding and cut to fit the length of the room. Form bays about 1200 mm wide. Ascertain the height of the floor screed from the bottom of the door lining, allowing for the thickness of a tile and bed if tiles are to be laid later. Make a pinch or gauge rod from say, a piece of batten 20 mm 50 mm, and mark on it the height of the floor level to the datum line. (see illustration over page). Brush cement slurry over the sub-floor where the rules are to be laid. Place cement and sand in a layer 75 mm wide next to side of rules. Rules are now placed on the top of the compo and bedded down into the material. The pinch rod is now used to gauge the height of the top of the rule from the level datum line. Use straight edged rule and level to level and straighten pinch rod in from this point.
10. Adjust the rules and consolidate the material at the sides of the rule by using he gauging trowel.
2.
Screed rules These can now be put in place, see slide 8 and bedded in as previously described. Use gauging trowel to consolidate material at sides of rules.
Datum Line Method 1. Check datum line is continuous at the angles; not one above the other. 2. Check lines are straight. 3. Take timber gauge rod, place upright against one wall and mark one rod height of datum line from floor. 4. Using rod in a like manner, check level of sub-floor and mark off high or low points. Level and Straight Edge 1. Check level of floor from the door opening using a long straight edge rule, 3 m to 4 m long and spirit level. (see diagram) Mark off high or low points.
3. Use the pinch rod and check the setting out of the tiles so that the joint coincides with the expansion joint. Allow for the extra width in the joint.