Production Schedule: Filming

Date
7/2/12

Activity
Filming

Location
Design technology department Technicians room
Media room E21

Personnel
Crew: Lucy (Camera operator) and Beth (Director) + actor

Equipment
Camera, Tripod, Microphone.

Contingency Plan
Reschedule filming to the 24/1/12 as we only have one filming location.
Work on poster

9/2/1221/2/12

Editing

Crew: Lucy and Beth

iMovie, Final Cut Express

23/2/12

Filming

Design technology department Technicians room Media room E21

Crew: Lucy (Camera Operator) and Beth (Director) + actor

Camera, Tripod, Dolly, Microphone

Reschedule filming to the 24/1/12 as we only have one filming location. Work on poster

24/2/1213/3/12

Editing

Crew: Lucy, Helena and Beth

iMovie, Final Cut Express

13/3/12

Filming

Design technology department Technicians room Media room E21 Design technology department Technicians room Media room E21 Media room E21 Media room E21

Crew: Lucy (Director) and Beth (Camera Operator) + actor

Camera, Dolly, Tripod, Microphone

Reschedule filming to the 24/1/12 as we only have one filming location. Work on poster

15/3/1227/3/12 27/3/12

Editing

Crew: Lucy and Beth

iMovie, Final Cut Express Camera, Dolly, Tripod, Microphone iMovie, Final Cut Express, Live Type GarageBand LiveType

FilmingRe-filming if needed. Editing Composin g music Create titles for film

Crew: Lucy and Beth + actor

Reschedule filming to the 24/1/12 as we only have one filming location. Start on music Edit Radio Trailer

29/3/12 29/3/12 29/3/12

Crew: Lucy and Beth Crew: Lucy and Beth Crew: Lucy and Beth

Production Schedule: Poster

Date
24/1/12

Activity
Taking pictures for the poster Develop first ideas for the poster Experiment with font/colour/size Edit primary image. Create production logo

Location
Media Studio E20 Media room E21 Media room E21 Media room E21 Media room E21 Media room E21 Media room E21

Personnel
Lucy and Beth

Equipment
Still camera

Contingency Plan
Work on pre-production

26/1/12

Lucy

Adobe Photoshop

Work on pre-production

31/1/12

Lucy and Beth

Adobe Photoshop

Work on pre-production

7/2/12

Lucy and Beth

Adobe Photoshop

Edit film

23/2/12

Add effects- tints/shadows

Lucy

Adobe Photoshop

Edit film

28/2/12

Decide text and layer it and create production credits Finalise layout

Lucy

Adobe Photoshop

Create music

15/2/12

Lucy and Beth

Adobe Photoshop

Create Credits

Production Schedule: Radio Trailer

Date
27/3/12

Activity
Recording for the radio trailer

Location
Sound room E20

Personnel
Crew: Lucy and Beth + 2 actors

Equipment
Camera, Dolly, Tripod, Microphone

Contingency Plan
Work on editing film

29/3/12

Recording and editing of radio trailer.

Sound room E20

Crew: Lucy and Beth + 2 actor

Camera, computer, firewire and harddrive

Work on editing film and make sure poster is all finalised