LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT


Our Northern Gateway to Mindanao

PROJECT STATUS AND UPDATES AS OF 30 APRIL 2012

PROJECT STATUS AND PICTURES

CIVIL WORKS (As of 30 April 2012)


Original Contract Amount Revised Contract Amount Contractor Scope of Works : :

PhP 4,991,771,319.67 PhP 5,484,657,799.78 Hanjin Heavy Industries & Const. Co., Ltd. (HHIC)

: :

Runway 2100 m x 45 m Taxiways 23 m x 260 m (A & B) Main Apron 130 m x 355 m (5 Aircraft Parking Bays) Passenger Terminal Bldg. 7184 sq.m. Operation and Control Tower Bldg., Power House Bldg., Cargo Terminal Bldg., CFR (CAT-1) Bldg., Maintenance Bldg., Cold Water Receiving Station Administration Bldg., Waste Water Treatment Plant, Other Airport Support Facilities : 18 January 2008

Start Date Target Date of Completion

17 January 2012 (original) Delay is due to the interfacing

of civil works & ANSSF

Status

Actual Physical Accomplishment is 95.45% ,


Slippage (-) 4.55%

PROJECT STATUS AND PICTURES

CIVIL WORKS

CONSTRUCTION AT RUNWAY AREA

(Ongoing Activities at Airside Area)

Accomplishment as of 30 April 2012 Actual (Over-All)

91.93%

Description ICAO Code 4E

2,100 m x 45 m Single Runway

Length Completed: 2,100 m (W @ 45 m) out of 2,100 m

PCCP Construction, 101,303 sq.m. out of the 103,088 sq.m. (98.26%)

CIVIL WORKS

PROJECT STATUS AND PICTURES

(Ongoing Activities at Airside Area)


PASSENGER TERMINAL APRON

Accomplishment as of 30 April 2012 Actual

94.61%
Description

Max. No. of Parking Bays Area

5 46,207 sq.m. (355 m x 130 m)

PCCP Construction 46,207 sq.m. out of the 46,207 sq.m. (100.00%)

CIVIL WORKS

PROJECT STATUS AND PICTURES

(Ongoing Activities at Airside Area)


TAXIWAY A CONSTRUCTION

Accomplishment as of 30 April 2012 Actual

82.22%
Description 2 Perpendicular

No.

Dimension (23 m x 260 m)

CIVIL WORKS

PROJECT STATUS AND PICTURES

Sodding

(Ongoing Activities at Airside Area)

72.71% Complete

PROJECT STATUS AND PICTURES

CIVIL WORKS

(Ongoing Activities at Airside Area) AIRSIDE PERIMETER FENCING WORKS

100% Complete

CIVIL WORKS (Ongoing Activities at Landside Area)

PROJECT STATUS AND PICTURES

PASSENGER TERMINAL BUILDING


Accomplishment as of 30 April 2012 Actual

95.00%
Description 1.6 Million 5,303

Design Annual Passenger Design Day Passenger

PROJECT STATUS AND PICTURES


CIVIL WORKS (Ongoing Activities at Landside Area)

PASSENGER TERMINAL BUILDING

Installed (2) Passenger Boarding Bridges (PBB)

CIVIL WORKS (Ongoing Activities at Landside Area)

PROJECT STATUS AND PICTURES

PTB Roads and Car Parking Area 99.71% Complete

CIVIL WORKS (Ongoing Activities at Landside Area)

PROJECT STATUS AND PICTURES

OPERATION AND CONTROL TOWER BUILDING

Accomplishment as of 30 April 2012


Actual

92.81%

PROJECT STATUS AND PICTURES

CIVIL WORKS

(Ongoing Activities at Landside Area)


CARGO TERMINAL BUILDING

Accomplishment as of 30 April 2012 Actual

90.54%
Description 736 m2

Floor Area

CIVIL WORKS

PROJECT STATUS AND PICTURES

(Ongoing Activities at Landside Area)


CRASH FIRE AND RESCUE BUILDING Accomplishment as of 30 April 2012 Actual

90.78%
Description 599 m2

Floor Area

PROJECT STATUS AND PICTURES

CIVIL WORKS

(Ongoing Activities at Landside Area)

Accomplishment as of 30 April 2012 Actual

86.92%
Description 519 m2

Floor Area

POWER HOUSE BUILDING

PROJECT STATUS AND PICTURES

CIVIL WORKS

(Ongoing Activities at Landside Area)


ADMINISTRATION BUILDING

Accomplishment as of 30 April 2012 Actual Floor Area

90.16%
Description 730 m2

CIVIL WORKS

PROJECT STATUS AND PICTURES

MAINTENANCE BUILDING Accomplishment as of 30 April 2012 Actual

(Ongoing Activities at Landside Area)

92.31%
Description 739 m2

Floor Area

PROJECT STATUS AND PICTURES

CIVIL WORKS

30 April 2012 Actual

(Ongoing Activities at Landside Area) COLD WATER RECEIVING STATION

94.85%
Description 317 m2 227.50 m3 227.50 m3

Floor Area Fire Water Supply Cold Water Supply

PROJECT STATUS AND PICTURES

CIVIL WORKS

(Ongoing Activities at Access Road ROAD SIGNS

PROJECT STATUS AND PICTURES CONCRETING OF ROAD CROSSINGS AT AIRPORT ACCESS ROAD
(As of 05 May 2012)

CROSSING - DIAMOND VILLAGE LEFT SIDE (going to the RIGHT SIDE (going to the
airport) airport)

BEFO RE

AFT ER

PROJECT STATUS AND PICTURES CONCRETING OF ROAD CROSSINGS AT AIRPORT ACCESS ROAD
(As of 05 May 2012)

CROSSING BARANGAY GASI LEFT SIDE (going to the RIGHT SIDE (going to the
airport) airport)

BEFO RE

AFT ER

PROJECT STATUS AND PICTURES

AIR NAVIGATION SYSTEM AND SUPPORT FACILITIES


Estimated Project Cost Source of Funds 2.69 M Scope of Works (LLZ), Equipment (DME) : : US $ 16.07 Million (PhP 755.24 Million)

: EDCF-Republic of Korea - US $ 13.38 M Government of the Philippines - US $ Navigation Aids Facilities -Instrument Landing System (ILS) composed of Localizer Glide Path Equipment (GP), and Distance Measuring -DVOR/DME -Air Meteorological Observation System (AMOS) -VHF and HF System for Air Traffic Communication -Testing of Equipment, Special Tools, and Spare Part Supply -Commissioning Flight Test and Operational Test Run Aeronautical Ground Lighting System -Underground Conduits and Cables -Airfield Lighting System -Electrical Equipment composed of High and Low Voltage -Special Tools and Spare Part Supply -Commissioning Flight Test and Operational Test Run

Electrical Equipment with Cables

PROJECT OVER-ALL PHYSICAL AND FINANCIAL PROGRESS (As of 30 April 2012)

LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT


Our Northern Gateway to Mindanao

Contact Us: LADP Project Management Office