Presentation outline
Overview of HT LT supply system HT-LT supply system Commissioning process: Bus Bars Current Transformers Voltage Transformers Circuit Breakers Integrated checks Conclusion

May 24, 2012

PMI Revision 00

Overview of HT/LT Supply System


G
UAT-A
16.5 KV 6.6 KV GT Stn. SWGR-SA UNIT SWGR--A UST A BFP ESP TRF-A X USS-A Air Compr Trf Blr MCC
May 24, 2012

Station TRF-1

UAT-B

6.6 KV

SB

UNIT SWGR--B

Stn Serv Trf-A

ID Fan X X USS-B Turb MCC

UST-B

ESP TRF-B 415 V Unit EMG SWGR X X

DMP Serv Trf S/Serv. Trf.-B

SWYD Serv Trf-1

From DG SWGR

PMI Revision 00

Components Of HT LT system
Switching devices : Switches, Fuses, Isolators, Earthing switch Circuit breakers / contactors Control Circuit : service / test /isolated position, Tripping & closing circuit Spring charging, anti pumping, Supply monitoring, indications, Measurement : Ammeter, voltmeter, energy meter Protection : Relays, CT, PT,
May 24, 2012

Cables , Bus ducts etc

PMI Revision 00

(HT & LT) Supply system Commissioning


BUSBAR Power & Control Buses Physical Inspection Continuity Insulation Resistance Contact Resistance (mV Drop Test) HV Test

May 24, 2012

PMI Revision 00

(HT & LT) Supply system Commissioning


CURRENT TRANSFORMER Physical Inspection Winding Resistance Insulation Resistance Polarity Test Ratio Test Magnetization Test

May 24, 2012

PMI Revision 00

(HT & LT) Supply system Commissioning


VOLTAGE TRANSFORMER Physical Inspection Winding Resistance Insulation Resistance Polarity Test Ratio Test

May 24, 2012

PMI Revision 00

(HT & LT) Supply system Commissioning


CIRCUIT BREAKERS Physical Inspection and earthing Mechanical Operation Insulation Resistance Vacuum Test Contact Resistance Timing

May 24, 2012

PMI Revision 00

(HT & LT) Supply system Commissioning


Protective Relays Secondary Injection Primary Injection Relay Setting Control Wiring Checking Indications Operation in Switchgear & Remote Counter

May 24, 2012

PMI Revision 00

(HT & LT) Supply system Commissioning


Integrated checking: Interlocks as per logic Annunciation and event logging in DAS Interface with other departments e. g. C&I Commissioning documentation