Beruflich Dokumente
Kultur Dokumente
INDIA
PRESENTATION OUTLINE
Where do we stand Power sector Evolution Present Structure Strength & weakness Objective and transformation roadmap Electricity for all by 2012 Major challenges Reforms in the sector Vision of MoP
1947 - Total installed capacity of only 1362 MW. 1948 - Electricity Supply Act leads to formation of SEBs Priority in development through SEBs Development through Five Year Plans Emphasis on hydel power in the first two Plans Uneven distribution of natural resources; inter-state imbalances Early Seventies - Country faces unprecedented power crisis Capacity: 16,664 MW in 1974 1975 - NTPC and NHPC set up in Central Sector 1991 - Liberalization; Private participation permitted 1992 - Power Grid Corp. Formed to facilitate formation of National Grid 1998 - Regulation through formation of CERC/SERC 2003 - Electricity Act2003
Generating capacity has grown manifold from 1712 MW in 1950 to more than 1,40,000 MW by end of Jan 2008. Generation in the country has also increased from 5 billion units in 1950 to about 617 billion units by end of Jan 2008.
The growth in the transmission lines has been from 2708 ckm in 1950 to more than 265,000 ckm by Jan 2008.
The average PLF increased from 54% in 1990-91 to an impressive 77.6% in 2006-07. 65% households have access to Electricity ,balance to be covered by 2012.
1,24,310 112,058
1,41,079
66,000
1950
1960
1970
1980
1990
2004
2006
2008(jan)
(Jan., 2008)
35,208 MW (24.7%) 90,896 MW (64.6%) Coal Gas Oil 75,002 MW (53.3%) 14,692 MW (10.5%) 1,202 MW (0.9%) 4,120 MW (2.9%) 10,855 MW (7.7%)
Thermal
Nuclear Renewables
TOTAL
1,41,079 MW
587
GENERAION IN BUs
450
400
74 72 70
67.3 69
72.7
72.1 69.9
68 66 64 62 60 58
98-99 99-00 2000-01 2001-02 2002-03 2003-04 2006-07 64.6
11.7
12.3
13.9
Per Capita consumption (kWh / Year) (appx.) Brazil : 2070 China : 1200 Thailand: 2000 Malaysia: 3000 USA : 9000
UNDER THE VIITH SCHEDULE OF THE INDIAN CONSTITUTION, THE POWER SECTOR IS ON THE CONCURRENT LIST, MEANING THAT BOTH PARLIAMENT AND STATE ASSEMBLIES HAVE POWER TO LEGISLATE. IN THE EVENT OF CONFLICT, CENTRAL ACTS PREVAILS.
Centre
Legislativ e function
Executive Function
Execution
Regulatory Function
States
State Assemblies
State Govts.
SERCs
Central, State and Private utilities have a complementary role for optimal development of power sector in India.
Central
Under MOP: NTPC, NHPC, NEEPCO,DVC,BBMB Other Ministries: NLC, NPC SEBs/State Gencos NJPC, THDC, NHDC IPPs, Licensees (CESC, BSES, AEC) CTU-Power Grid
Generation
State Joint
Private
Central State
Transmission Transmission
State
Distribution Distribution
Private
STRENGTHS
Abundant coal reserves (enough to last at least 200 years) Vast hydro-electric potential (150,000 MW out of which only 18 per cent has so far been tapped) A large pool of highly skilled technical personnel Emergence of strong and globally comparable central utilities (NTPC, Powergrid) Political consensus on reforms Potentially one of the largest power markets in the world
Weaknesses
Declining trend of Capacity addition and persisting shortages Poor financial health of State Power Utilities Under utilization of existing capacity due to transmission constraints. Inadequate distribution network Irrational Tariff Poor state of Rural Electrification / Nonelectrified households Increasing Cost of Power
Estimates indicate the need for an additional 100 GW to provide Power for All by 2012
As per the 16th EPS, by the year 2012, Indias peak demand would be 157,107 MW with energy requirement of 975 BU. Peak requirement in MW
Energy requirement in BU
Mar.'07(act)
Mar.'12 (est.)
* Installed capacity to increase to 212,000 MW by year 2012 to meet the peak demand of 1,57,107 MW.
MULTIPRONGED STRATEGY
Total
58644 16553 3380
Total
39865
27952
10760
78577
In addition, 13,500 MW through Non- conventional sources and 12,000 MW through captive power plants.
TIDAL POWER
SOLAR
9,000
20 MW/SQ. KM (40,000 MW) 20,000
NIL
2.64
NIL
140049 MW
Assuming 30:70 ratio, 60 Billion as equity and 140 Billion debt needed in next 8-9 years
Current
Required by 2012
18.0 11.5 13.0 7.8 8.8 12.2 11.2 7.1 11.7 7.3 12.2 8.3 13.9 9.3
7.3
33% '50
41% '60
46%
40% '80
29% '90
25% 2003
26% 2004
25 2008
'70 Hydro
Thermal + Others
HYDRO POTENTIAL IN THE COUNTRY IS OF THE ORDER OF 150 GW. ONLY 18% HAS BEEN TAPPED SO FAR. OPTIMAL MIX IS 40 : 60 FOR HYDRO : THERMAL TO ENSURE MAXIMUM UTILIZATION OF INSTALLED CAPACITY AND TO REDUCE PEAKING
SHORTAGES.
Country
% of Potential Utilised
58 41 31 18 17.5
Enabling Legislative Framework Generation (other than hydro) freed from licensing Transmission & Distribution: Licensed but unlimited entry Transmission is isolated from Generation, Distribution and Trading Open Access: T&D licensees to act as common carriers
It facilitates investment by creating competitive environment and reforming distribution segment of power industry. Entry Barriers removed/reduced Delicensed generation. freedom to captive generation including group captive.
Contd
(CONTD)
Open access to consumers above 1 MW within five years commencing Multiple licenses in distribution. No requirement of licence for generation and distribution in notified rural areas. The new law envisages deregulation of tariff fixation in certain cases: Tariff determined through competitive bidding is not to be regulated. Where open access has been allowed to a consumer, he can reach an agreement with his supplier for purchase of electricity and the tariff for such transaction would not be regulated.
ENCOURAGING RESULTS
(CONTD)
Trading activity has picked up. 11 licencees are in the fray. Increasing trading volumes for which sellers are receiving payments. Applications for transmission licensees by a private company. Applications for distribution license by private players in Delhi, Mumbai and at other places. Capital cost of new projects and tariff lower than anticipated.--- effective regulation and competition Cost per MW still around Rs. 4 crore in new coalfired thermal power stations. Weighted average tariff of NTPC projects is Rs. 1.62 per kWh.
Contd..
RECENT DEVELOPMENTS
3 Ultra Mega Power Projects of 4,000MW each awarded through tariff based competitive bidding. Approval for setting up first power exchange in India accorded by CERC. Rural Electrification : Rajiv Gandhi Gramin Vidyutikaran Yojana (RGGVY) is a major national effort to universalize access to electricity.
TECHNOLOGY UPGRADATION
Supercritical technology is one essential component of the Ultra Mega Power Projects Next stage will be ultra supercritical technology subject to its cost effectiveness
India is also working on an IGCC pilot plant based on Indian coal which has high ash content.
6. Rationalization of tariff
UNAFFORDABLE
AFFORDABLE
2 4 6 8 10 12
Energy Bills account for 10% of total income for Indian Consumers vis--vis 0.25% for US Consumer and 5% for China
THANK YOU