Beruflich Dokumente
Kultur Dokumente
PROJECT MANAGER S JOB Plan the project Manage it- To the schedule - Within budget. Estimate the cost Establish the budget
Identify and acquire necessary resources. -People --Equipment -- Machineries etc, etc.
continue
Able to determined the cost By how much ( labour, material, Etc. Plus how long ( schedule ) But often lack of accuracy.
Unable to figure out What it will take on the cost before have done it.
Project construction
1. Capital Cost
Land acquisition Planning and feasilities studies. Architecture and engineering design. Constuction + material + equipment + labour. Field supervision. Insurance, bon , tax during construction. Client general office. Equipment and furnishing. Inspection and testing
- Operating staff - Labour and material for maintenance and repair. - Insurance / tax . - Utilities.
+ Contigencies
Refer to the note
CONSTRUCTION INDUSTRY
- Cost estimate involve the following entity s role
Owner / Client
Designer
Constructors / contractors
Suppliers
Field manager
PROJECT CONSTRUCTION
NOTE:
Allowance for contigencies / unexpected cost: 1.Change in design development. 2. Adjustment of schedule. 3. Other requirements from government agencies / local Authority.
COST ESTIMATION TOOLS AND TECHNIQUES 3 basic tools and techniques for cost estimates 1. Anologous or top down
- Use the actual cost of a previous, similar project as a basis for the new estimate.
2. Definitive or Bottom up - Estimate individual work items and sum them to get total estimate . In other word based on complete detail of quantity, specification and condition . 3. Parametric or top down estimate
OTHERS...... Appropriation estimate -Prepared from best available information to establish a budget submitted for funding approval. ( i.e an appropriation ) Also known as budget estimate. Rough Order of Magnitude estimate -An approx estimate made without detail info
BEST PRACTICE TO MANAGE THE PROJECT AT SITE- COST CONTROL
Project manager
ESTIMATING METHOD
The following are some of the rough estimating method that can be selected to anticipate a project cost before it being constructed ( there is already design but contract information has not been prepared ) :1. Cubic Content Method 2. Floor Area Method 3. Unit Valuation Method 4. Appropriate qualities method 5. Bill of Quantities Method
1. Frequently used to calculate building cost. 2. Unit according to the building cubic meter ( m 3 ) 3. The length and width of the building should be taken from the external building surface.
4. Comparison being made with building of the similar design, function, characteristic etc.
5. This method provide limited application.
1. Good and almost accurate. 2. A few items will be group as one collective unit. 3. Work, material will be removed roughly from the drawing for calculation purposes.
The following section of the tender document that required pricing : 1. Preliminaries work - indirect cost that is taken into consideration at the early stage. Eg insurance, performance bond. 2. Measured works. BQ / Breakdown cost of each item. 3. Total prime cost and temporary allocation cost for special work eg. electricity., air condition, lift carried out by nominated sub contractor or named supplier.
The price of the building / landscape material include pricing for 1. L abor. 2. Materials. 3. Usage of machineries and equipment. 4. Profit.
4. Wastage ( Damage material or surplus material estimated 10 % - 15 % of building / landscape material will result in wastage )
-Rough profit consist of -A ) Net cost -B ) Overhead cost - staff / director salary - office rental - furniture - electricity, water and telephone bill - transport allowance - Road tax - supervisor, agent etc
BUILT PRICE FOR MACHINERIES / EQUIPMENTS -Prior to the purchasing or rental of machineries, its good to consider the following :1. Able to generate bigger profit or not. 2. Machineries / equipments to be rented / purchase is able to be handled by labour or not 3. Does it can benefit on other project to be carried out later.
Continue ...BUILT
Capital cost include -Original price of the machineries / equipment. -Machineries / equipment interest ( 5 % - 10 % ) -Life span of the machineries / plants. -Repairing cost ( 1/10 of the original price ) -Transportation cost ( 1 /20 of the original price ) -Operating cost include -Warranty of the machineries / equipments -Machineries loading capacity -Using of the combustible material and others related -Labour / workers wages
THANK YOU