Materials management
22
DEFINITION Its a total concept involving an organizational Structure unifying into a single responsibility, the Systematic flow and control of material from Identification of the need through customer delivery
6/28/12
6/28/12
Planning function
Production and control Inventory and stores control Shipping/physical distribution Traffic
purchasing function
6/28/12
PLANNING FUNCTION
The planning part of the materials management deals with the following issues:
v
Translation of the sales projection into long term requirements of materials. On the basis of updated production plan, adjust the latest sales demand and the requirements of material accordingly. To arrange the facilities required for the materials management.
6/28/12
PRODUCTION CONTROL
This is done by: Determining requirements of materials and parts to be purchased and manufactured.
v
PURCHASING
Purchasing department procures the materials of desired quality in time to meet the production specifications at the lowest possible cost. The main activities of purchasing are: Selection of acceptable suppliers and issue of purchase order.
v
To look for new materials and suppliers that can contribute to company profile.
v
6/28/12
6/28/12
To store the materials properly according to the policy and ensure their quick identification.
v
To verify the materials physically at periodic intervals and to record discrepancies, if any, along with the reasons
v
6/28/12
SHIPPING/PHYSICAL DISTRIBUTION
It is concerned with the distribution of finished goods from the production department and to verify the quantity; To receive the finished goods from the production departments, to verify them and store them properly till they are distributed.
v
To pack and label the finished goods to make them ready for transport to customers.
v
To prepare shipping documents such as packing slip, bill of materials, railway receipts, lorry receipts etc. which are forwarded with shipments.
v
6/28/12
MATERIALS HANDLING It involves; vTo handle in-planned materials through trucking, pallets, containers, etc vTo maintain the material handling equipments and other incidental items like pallets, containers ,etc TRAFFIC It is concern with the incoming consignments of raw materials and outgoing shipments of finished goods. It includes : v To carry raw materials from the suppliers plant or railway goods office or such destinations. v To carry finished goods to customers, railway goods office branch, wholesalers or retailers. v To administer fright rates, routes, etc. If transport services are hired.
6/28/12
THANK YOU
6/28/12