Sie sind auf Seite 1von 179

TABEL BERAT BESI TULANGAN PER METER ( POLOS )

Diameter Volume Berat Besi Diameter Volume Berat Besi


Tulangan Besi Tul. Tulangan Tulangan Besi Tul. Tulangan
( mm ) Per meter Per meter ( mm ) Per meter Per meter
Real ( m3 ) ( Kg ) Real ( m3 ) ( Kg )

3.00 0.0007 0.0554 14.80 0.0172 1.3483


3.20 0.0008 0.0630 15.00 0.0177 1.3850
3.40 0.0009 0.0712 15.20 0.0181 1.4222
3.60 0.0010 0.0798 15.40 0.0186 1.4599
3.80 0.0011 0.0889 15.60 0.0191 1.4980
4.00 0.0013 0.0985 15.80 0.0196 1.5367
4.20 0.0014 0.1086 16.00 0.0201 1.5758
4.40 0.0015 0.1192 16.20 0.0206 1.6155
4.60 0.0017 0.1303 16.40 0.0211 1.6556
4.80 0.0018 0.1418 16.60 0.0216 1.6962
5.00 0.0020 0.1539 16.80 0.0222 1.7373
5.20 0.0021 0.1664 17.00 0.0227 1.7790
5.40 0.0023 0.1795 17.20 0.0232 1.8211
5.60 0.0025 0.1930 17.40 0.0238 1.8637
5.80 0.0026 0.2071 17.60 0.0243 1.9067
6.00 0.0028 0.2216 17.80 0.0249 1.9503
6.20 0.0030 0.2366 18.00 0.0254 1.9944
6.40 0.0032 0.2521 18.20 0.0260 2.0390
6.60 0.0034 0.2681 18.40 0.0266 2.0840
6.80 0.0036 0.2846 18.60 0.0272 2.1296
7.00 0.0038 0.3016 18.80 0.0277 2.1756
7.20 0.0041 0.3191 19.00 0.0283 2.2222
7.40 0.0043 0.3371 19.20 0.0289 2.2692
7.60 0.0045 0.3555 19.40 0.0295 2.3167
7.80 0.0048 0.3745 19.60 0.0302 2.3647
8.00 0.0050 0.3940 19.80 0.0308 2.4132
8.20 0.0053 0.4139 20.00 0.0314 2.4622
8.40 0.0055 0.4343 20.20 0.0320 2.5117
8.60 0.0058 0.4553 20.40 0.0327 2.5617
8.80 0.0061 0.4767 20.60 0.0333 2.6122
9.00 0.0064 0.4986 20.80 0.0340 2.6631
9.20 0.0066 0.5210 21.00 0.0346 2.7146
9.40 0.0069 0.5439 21.20 0.0353 2.7666
9.60 0.0072 0.5673 21.40 0.0359 2.8190
9.80 0.0075 0.5912 21.60 0.0366 2.8719
10.00 0.0079 0.6156 21.80 0.0373 2.9254
10.20 0.0082 0.6404 22.00 0.0380 2.9793
10.40 0.0085 0.6658 22.20 0.0387 3.0337
10.60 0.0088 0.6916 22.40 0.0394 3.0886
10.80 0.0092 0.7180 22.60 0.0401 3.1440
11.00 0.0095 0.7448 22.80 0.0408 3.1999
11.20 0.0098 0.7722 23.00 0.0415 3.2563
11.40 0.0102 0.8000 23.20 0.0423 3.3132
11.60 0.0106 0.8283 23.40 0.0430 3.3705
11.80 0.0109 0.8571 23.60 0.0437 3.4284
12.00 0.0113 0.8864 23.80 0.0445 3.4868
12.20 0.0117 0.9162 24.00 0.0452 3.5456
12.40 0.0121 0.9465 24.20 0.0460 3.6049
12.60 0.0125 0.9773 24.40 0.0467 3.6648
12.80 0.0129 1.0085 24.60 0.0475 3.7251
13.00 0.0133 1.0403 24.80 0.0483 3.7859
13.20 0.0137 1.0725 25.00 0.0491 3.8472
13.40 0.0141 1.1053 25.20 0.0499 3.9090
13.60 0.0145 1.1385 25.40 0.0506 3.9713
13.80 0.0149 1.1723 25.60 0.0514 4.0341
14.00 0.0154 1.2065 25.80 0.0523 4.0974
14.20 0.0158 1.2412 26.00 0.0531 4.1612
14.40 0.0163 1.2764 26.20 0.0539 4.2254
14.60 0.0167 1.3121 26.40 0.0547 4.2902
Diameter Volume Berat Besi
Tulangan Besi Tul. Tulangan
( mm ) Per meter Per meter
Real ( m3 ) ( Kg )

26.60 0.0555 4.3554


26.80 0.0564 4.4212
27.00 0.0572 4.4874
27.20 0.0581 4.5541
27.40 0.0589 4.6213
27.60 0.0598 4.6891
27.80 0.0607 4.7573
28.00 0.0615 4.8260
28.20 0.0624 4.8951
28.40 0.0633 4.9648
28.60 0.0642 5.0350
28.80 0.0651 5.1057
29.00 0.0660 5.1768
29.20 0.0669 5.2485
29.40 0.0679 5.3206
29.60 0.0688 5.3933
29.80 0.0697 5.4664
30.00 0.0706 5.5400
30.20 0.0716 5.6141
30.40 0.0725 5.6887
30.60 0.0735 5.7638
30.80 0.0745 5.8394
31.00 0.0754 5.9155
31.20 0.0764 5.9921
31.40 0.0774 6.0691
31.60 0.0784 6.1467
31.80 0.0794 6.2247
32.00 0.0804 6.3033
32.20 0.0814 6.3823
32.40 0.0824 6.4619
32.60 0.0834 6.5419
32.80 0.0845 6.6224
33.00 0.0855 6.7034
33.20 0.0865 6.7849
33.40 0.0876 6.8669
33.60 0.0886 6.9494
33.80 0.0897 7.0324
34.00 0.0907 7.1158
34.20 0.0918 7.1998
34.40 0.0929 7.2842
34.60 0.0940 7.3692
34.80 0.0951 7.4546
35.00 0.0962 7.5406
35.20 0.0973 7.6270
35.40 0.0984 7.7139
35.60 0.0995 7.8013
35.80 0.1006 7.8892
36.00 0.1017 7.9776
36.20 0.1029 8.0665
36.40 0.1040 8.1559
36.60 0.1052 8.2457
36.80 0.1063 8.3361
37.00 0.1075 8.4270
37.20 0.1086 8.5183
37.40 0.1098 8.6101
37.60 0.1110 8.7025
37.80 0.1122 8.7953
38.00 0.1134 8.8886
38.20 0.1146 8.9824
LAMPIRAN I : KEPUTUSAN BUPATI PONOROGO
NOMOR : 188.45/ /405.14/2014
TANGGAL :

STANDAR SATUAN HARGA POKOK KEGIATAN BIDANG SARANA DAN PRASARANA FISIK
KABUPATEN PONOROGO TAHUN ANGGARAN 2014

HARGA SATUAN
No. JENIS BAHAN BANGUNAN SAT
TERENDAH TERTINGGI
1 2 3 4 5
I PENUTUP ATAP & PLAFON
1 Asbes datar tebal 4mm (60x180) lbr 53,600.00 56,100.00
2 Asbes datar tebal 5mm (60x180) lbr 67,600.00 70,700.00
3 Asbes datar tebal 6mm (40x180) lbr 79,700.00 83,300.00
4 Asbes gelombang besar tebal 5 mm (2.50 x 1.02 m) 25.05 kg lbr 93,500.00 97,700.00
5 Asbes gelombang besar tebal 5 mm (2.25 x 1.02 m) 22.55 kg lbr 85,800.00 89,700.00
6 Asbes gelombang besar tebal 5 mm (2.00 x 1.02 m) 20.05 kg lbr 79,200.00 82,800.00
7 Asbes gelombang besar tebal 5 mm (1.80 x 1.02 m) 18.04 kg lbr 69,300.00 72,400.00
8 Asbes gelombang kecil tebal 4 mm (3.00 x 1,05 m) 24 kg lbr 86,300.00 90,200.00
9 Asbes gelombang kecil tebal 4 mm (2.70 x 1,05 m) 21.5 kg lbr 78,600.00 82,200.00
10 Asbes gelombang kecil tebal 4 mm (2.40 x 1,05 m) 19 kg lbr 69,800.00 73,000.00
11 Asbes gelombang kecil tebal 4 mm (2.10 x 1,05 m) 17 kg lbr 57,700.00 60,300.00
12 Asbes gelombang kecil tebal 4 mm (1.50 x 1,05 m) 12 kg lbr 38,500.00 40,200.00
13 Asbes gelombang besar tebal 6 mm (3.00 x 1,08 m) lbr 105,300.00 110,600.00
14 Asbes gelombang besar tebal 6 mm (2.70 x 1,08 m) lbr 96,100.00 100,900.00
15 Asbes gelombang besar tebal 6 mm (2.40 x 1,08 m) lbr 82,700.00 86,800.00
16 Asbes gelombang besar tebal 6 mm (2.10 x 1,08 m) lbr 69,900.00 73,400.00
17 Asbes gelombang besar tebal 6 mm (1.80 x 1,08 m) lbr 58,200.00 61,100.00
18 Asbes wuwung stel gelombang 0,92 mm lbr 21,500.00 22,500.00
19 Asbes wuwung stel gelombang 1,05 mm lbr 28,600.00 29,900.00
20 Asbes wuwung stel gelombang 1,08 mm lbr 31,300.00 32,700.00
21 Atap allumunium gelombang tebal 0,55 m² 98,200.00 106,700.00
22 Plat Asbes tebal 3,5 mm lbr 24,200.00 25,300.00
23 Plat Asbes tebal 4 mm lbr 30,800.00 32,200.00
24 Plat Asbes tebal 5 mm lbr 34,800.00 36,400.00
25 Plat Asbes tebal 6 mm lbr 37,100.00 38,800.00
26 Genteng flam pres jawa / lokal bj 1,700.00 2,000.00
27 Genteng Karang Pilang / wisma bj 3,200.00 3,600.00
28 Genteng wuwung jawa / lokal bj 6,600.00 6,900.00
29 Genteng wuwung karang pilang / wisma bj 9,000.00 9,400.00
30 Genteng Palentong bj 2,000.00 2,100.00
31 Genteng palentong super bh 3,300.00 3,400.00
32 Genteng nok palentong bj 6,700.00 7,000.00
33 Genteng bubung kodok glazzur bh 21,000.00 23,100.00
34 Genteng bubung kodok bj 6,500.00 7,100.00
35 Genteng Beton bj 3,800.00 4,000.00
36 Genteng aspal lbr 18,300.00 19,200.00
37 Genteng metal lbr 96,800.00 101,200.00
38 Genteng sirap lbr 1,900.00 2,000.00
39 Nok genteng Beton bj 11,500.00 12,000.00
40 Nok genteng Aspal bj 32,200.00 33,700.00
41 Nok paten 0,92 m bj 33,000.00 31,000.00
42 Nok paten 1,05' m bj 37,500.00 39,200.00
43 Nok paten 1,08' m bj 42,200.00 44,100.00
44 Nok stel rata 0.92 m bj 27,600.00 28,800.00
45 Nok stel rata 1.05 m bj 36,000.00 39,600.00
46 Nok stel gelombang bj 34,500.00 36,100.00
47 Nok standar 40 cm 18, swg 22 m² 36,300.00 37,900.00
48 Genteng dercrabond lbr 93,500.00 97,700.00
49 Sisalation/allumunium foil m² 20,300.00 21,200.00
50 Genteng Kodok bj 2,700.00 2,800.00
51 Seng gelombang 3" X 6" bjls 28 lbr 58,500.00 64,350.00
52 Seng Plat 3' x 6' Bjls 28 lbr 47,800.00 50,000.00

Page 3
53 Seng Datar lbr 36,500.00 38,100.00
54 Teakwood tebal 4 mm (1.22x2.44) lbr 124,700.00 130,400.00
55 Teakwood tebal 4 mm (1.10x2.10) lbr 110,000.00 115,000.00
56 Plywood tebal 4 mm (1.22x2.44) lbr 95,000.00 104,500.00
57 Plywood tebal 9 mm (1.22x2.44) lbr 137,200.00 150,900.00
58 Plywood tebal 4 mm (0.40x0.80) lbr 66,000.00 69,000.00
59 Plywood tebal 6 mm (0.40x0.80) lbr 71,000.00 74,200.00
60 Triplek tebal 4 mm (1,20 x 2.40) lbr 55,600.00 58,200.00
61 Triplek tebal 4 mm (0,90 x 2.00) lbr 48,900.00 51,100.00
62 Triplek tebal 4 mm (1.22 x 2.44) lbr 60,500.00 63,200.00
63 Triplek tebal 4 mm (1.10 x 2.10) lbr 47,500.00 49,700.00
64 Formite/ penjaga jarak bekisting/ spacer bh 6,000.00 6,300.00
65 Formika lbr 82,500.00 86,200.00
66 Plastik Aerator bh 15,000.00 15,500.00
67 Sunscreen alluminium m² 385,000.00 402,500.00
68 Rolling door alluminium m² 423,500.00 442,700.00
69 Pintu aluminium m' 302,500.00 316,200.00
70 Akustik ukuran (30x30) cm lbr 19,200.00 20,100.00
71 Akustik ukuran (30x60) cm lbr 38,500.00 40,200.00
72 Akustik ukuran (60x120) cm lbr 46,700.00 48,800.00
73 Gypsum board m³ 63,800.00 66,700.00
74 Profil Alluminium "T" m 22,000.00 23,000.00
75 Aluminium strip m 42,000.00 43,900.00
76 Roof light fibreglass 3,7 kg/m2 lbr 75,300.00 78,700.00
77 Tepung Gypsum kg 3,900.00 4,100.00
78 Ramset bh 550.00 600.00
79 Atap Polycarbonate lbr 2,585,000.00 2,702,500.00
80 Alumunium Composite Panel Grade A (Ex Eropa & Jepang)+Rangka m² 863,500.00 902,700.00
81 Alumunium Composite Panel Grade B ( Ex Indonesia & China)+Rangka m² 530,200.00 554,300.00
82 Calcium/Cement Cladding Panel 8mm + Rangka m² 198,000.00 207,000.00
83 Calcium/Cement Cladding Panel 10mm + Rangka m² 223,800.00 234,000.00
84 Calcium/Cement Cladding Panel 12mm + Rangka m² 253,000.00 264,500.00
85 Eternit Biasa 100 X100 m² 14,500.00 15,100.00
86 Eternit Gresik m² 16,500.00 17,200.00
87 Fiberglass lebar 92 cm X 180 m² 47,800.00 50,000.00
88 Genteng Bubung Glazur Ending bh 30,200.00 31,600.00
89 Genteng Bubung Keramik Glazur bh 26,900.00 28,100.00
90 Genteng Glazur Ending (Left/Right) bh 19,500.00 20,400.00
91 Genteng Kaca bh 8,800.00 9,200.00
92 Genteng Keramik Glazur Espanica (Single Interlock) bh 8,800.00 9,200.00
93 Genteng Keramik Glazur Millenio (Double Interlock) bh 10,100.00 10,500.00
94 Genteng wuwung galvalum x 115.000 = 2m' bh 58,500.00 61,200.00
95 Kalsiboard lbr 53,500.00 55,000.00
96 Seng (2 x 1,05) lbr 57,700.00 60,300.00
97 Seng Datar BJLS 30 (0,60 x 1,00) m' 30,800.00 32,200.00
98 Seng Gelombang Kecil ukuran 0,8 x 2,4 lbr 56,600.00 59,200.00
99 Seng Gelombang bwg 32 lbr 58,300.00 60,900.00
100 Seng Gelombang BJLS 30 (0,8 x 3.00) lbr 93,500.00 97,700.00
101 Seng Gelombang BJLS 30 (0,8 x 1,50) lbr 77,000.00 80,500.00
102 Seng Plat Datar BJLS 30 (0,45 x 1,00) lbr 49,500.00 51,700.00
103 Triplek 2.7 mm 1.20 x 2.40 m lbr 55,000.00 57,500.00
104 Triplek 2.7 mm 0.90 x 2.00 m lbr 49,500.00 51,700.00
105 Triplek 9 mm (120 x 240) lbr 102,800.00 107,500.00
106 Woodplank 8 x 20 x 400 m² 64,900.00 67,800.00
107 Woodplank 9 x 30 x 400 m² 89,600.00 93,700.00

II BAHAN MENGGUNAKAN KAYU


1 Dolken kayu O 8-10/400 cm btg 22,000.00 25,000.00
2 Kayu jati balok 8/12, 6/12 m³ 15,800,000.00 16,560,000.00
3 Kayu jati usuk 5/7, 4/6, 3/5 m³ 13,000,000.00 13,900,000.00
4 Kayu jati papan 2/20 x 2 m m³ 18,000,000.00 19,800,000.00
5 Kayu jati reng 2/3, 3/5 m³ 10,000,000.00 11,000,000.00
6 Kayu kamper (balok) m³ 8,000,000.00 8,500,000.00
7 Kayu kamper (papan) m³ 9,000,000.00 9,500,000.00

Page 4
8 Kayu kamper (usuk) m³ 7,000,000.00 7,500,000.00
9 Kayu kamper (reng) m³ 6,500,000.00 7,000,000.00
10 Kayu meranti (balok) m³ 5,000,000.00 5,500,000.00
11 Kayu meranti (papan) m³ 6,000,000.00 6,200,000.00
12 Kayu meranti (usuk) m³ 4,000,000.00 4,300,000.00
13 Kayu meranti (begesting) m³ 3,575,000.00 3,737,500.00
14 Kayu kruing (balok) m³ 5,500,000.00 5,750,000.00
15 Kayu kruing (papan) m³ 6,250,000.00 6,500,000.00
16 Kayu kruing (usuk) m³ 5,150,000.00 5,500,000.00
17 Kayu Borneo (balok) m³ 7,750,000.00 8,525,000.00
18 Kayu Borneo (papan) m³ 8,500,000.00 9,350,000.00
19 Kayu Borneo (usuk) m³ 7,000,000.00 7,500,000.00
20 Kayu 5/7 (meranti) m³ 4,000,000.00 4,300,000.00
21 Kayu cetakan m³ 200,000.00 220,000.00
22 List Kayu 2/4 m' 5,000.00 5,200.00
23 List Kayu Profil m' 8,500.00 8,900.00
24 Perancah Kayu m³ 5,000,000.00 5,175,000.00
25 Kayu terentang m³ 3,300,000.00 3,500,000.00
26 Tali ijuk kg 20,900.00 21,800.00
27 Ijuk kg 6,500.00 7,150.00
28 Kaso 5/7 m³ 4,000,000.00 4,300,000.00
29 Kayu papan tebal 9 mm m² 135,000.00 148,500.00
30 Bambu Ø 6 - 10/600 cm btg 13,700.00 14,300.00
31 Bilik Bambu m' 9,300.00 9,700.00
32 Minyak bekisting liter 4,700.00 4,900.00
33 Kayu bakar m3 350,000.00 385,000.00
34 Gedeng guling m² 35,000.00 38,500.00
35 Bambu ori btg 15,000.00 15,700.00
36 Kayu Gelam (dia 10-12 cm) - 4 m btg 13,200.00 13,800.00

III BAHAN MENGGUNAKAN BATU/PASIR & SEMEN


1 Batu Bata merah kelas 1 88.88 bh 1.5 kg bh 750.00 800.00
2 Batu bata merah kelas 2 bh 700.00 750.00
3 Bata berongga ekspose bh 2,000.00 2,150.00
4 Batu kali pecah 15/20 m³ 148,500.00 155,200.00
5 Batu pecah 5/7 m³ 154,000.00 161,000.00
6 Batu pecah 2/3 m³ 192,500.00 201,200.00
7 Batu pecah 1/2 m³ 203,500.00 212,000.00
8 Batu pecah 3/5 m³ 185,300.00 193,700.00
9 Batu gunung pecah 15/20 m³ 148,500.00 155,200.00
10 Batu Tempel m² 126,500.00 132,200.00
11 Bata pelapis klinker 5x5x24 cm bh 2,700.00 2,800.00
12 Batu kerikil beton m³ 185,300.00 193,700.00
13 Pasir cor/beton m³ 200,000.00 210,000.00
14 Pasir Pasang (lokal) m³ 132,000.00 138,000.00
15 Pasir urug m³ 70,000.00 75,000.00
16 Pasir Silika kg 38,500.00 40,000.00
17 Klingker bj 2,700.00 2,800.00
18 Semen berwarna yiyitan kg 11,000.00 12,000.00
19 Semen PC (Portland Cement)/Semen Gresik ( 50 Kg) kg 1,400.00 1,500.00
20 Semen Tiga Roda (50 Kg) kg 1,300.00 1,400.00
21 Semen Putih kg 2,300.00 2,700.00
22 Semen Merah m³ 105,000.00 115,500.00
23 Kapur Pasang (10 kg) kg 7,200.00 7,500.00
24 Tanah Urug m³ 90,000.00 98,000.00
25 Tanah sirtu m³ 68,000.00 71,500.00
26 Tanah katel m³ 55,000.00 57,500.00
27 Batu apung kg 9,900.00 10,300.00
28 Kapur Padam m³ 280,000.00 305,000.00
29 Kapur sirih kg 3,500.00 3,700.00
30 Air liter 80.00 100.00
31 Strorox - 100 kg 27,500.00 28,700.00
32 Waterstop lebar 150 mm m' 8,300.00 8,700.00
33 Waterstop lebar 200 mm m' 12,300.00 12,900.00

Page 5
34 Waterstop lebar 230 mm - 320 mm m' 41,300.00 43,200.00
35 Batu Granit kg 3,800.00 4,000.00
36 Batu Teraso kg 5,500.00 5,700.00
37 Semen nat kg 12,500.00 13,500.00
38 Abu Batu m3 110,000.00 115,000.00
39 Bata Ringan AAC m2 8.33 bh 5 kg m3 902,000.00 943,000.00
40 Bata Ringan CLC m2 8.33 bh 6 kg m3 852,500.00 891,200.00
41 Batako 20 x 40 cm bh 4,000.00 4,300.00
42 Glass Block bh 19,800.00 20,700.00
43 Batu Rain / Muka bh 700.00 750.00
44 Batu Alor Pipih m² 95,000.00 100,000.00
45 Batu Ampyang m² 55,000.00 60,000.00
46 Batu Andhesit 20/30 < m² 130,000.00 140,000.00
47 Batu Andhesit 20/30 > m² 140,000.00 150,000.00
48 Batu Belah 6/10 cm m² 135,000.00 145,000.00
49 Batu Candi 20/30 < m² 110,000.00 120,000.00
50 Batu Candi 20/30 > m² 120,000.00 130,000.00
51 Batu Lempeng Acak m² 70,000.00 80,000.00
52 Batu Lempeng 20/30 < m² 105,000.00 115,000.00
53 Batu Lempeng Potong 20/30 < m² 95,000.00 105,000.00
54 Batu Marmo m² 87,500.00 91,500.00
55 Batu Palimanan m² 150,000.00 175,000.00
56 Batu Paras m² 60,000.00 65,000.00
57 Batu Pecah ½-1 m³ 203,500.00 212,700.00
58 Batu Pecah 4-6 m³ 170,000.00 180,000.00
59 Batu Susun Sirih m² 173,500.00 190,000.00
62 Krikil Sungai disaring m³ 126,500.00 132,200.00
63 Krikil Sungai tak disaring m³ 110,000.00 115,000.00
64 Krikil Sungai - Royalti m³ 165,000.00 172,500.00
65 Sirtu Royalti m³ 70,000.00 75,000.00
66 Timbunan Pilihan m³ 65,000.00 70,000.00

IV BAHAN MENGGUNAKAN BESI/LOGAM


1 Besi begel/ baut kg 15,000.00 16,500.00
2 Besi beton polos kg 10,300.00 10,800.00
3 Besi beton ulir kg 10,500.00 11,000.00
4 Besi pipa galvanis medium 1 1/2, 6m ljr 288,700.00 303,000.00
5 Besi pipa galvanis medium 1, 6m ljr 240,000.00 251,000.00
6 Besi pipa galvanis medium 1/2, 6m ljr 115,000.00 120,000.00
7 Besi pipa galvanis medium 2 1/2, 6m ljr 515,100.00 540,300.00
8 Besi pipa galvanis medium 2, 6m ljr 484,500.00 508,200.00
9 Besi pipa galvanis medium 3, 6m ljr 555,900.00 583,100.00
10 Besi pipa galvanis medium 4, 6m ljr 790,500.00 829,200.00
11 Besi plat 4 x 8 tebal 2 mm, 46,7 kg kg 10,800.00 11,300.00
12 Besi Plat bordes 4" x 8" tebal 3mm 75 kg kg 17,000.00 17,800.00
13 Besi profil WF <= 200 mm kg 13,200.00 13,800.00
14 Besi profil WF <= 200 mm s/d 400 mm kg 13,200.00 13,800.00
15 Besi profil WF <= 200 mm s/d 500 mm kg 13,200.00 13,800.00
16 Besi strip tebal 5 mm kg 15,000.00 16,500.00
17 Besi scuare tube kg 6,000.00 6,300.00
18 Kawat ikat beton kg 15,000.00 17,000.00
19 Kawat nyamuk kasa alumunium m² 49,500.00 51,700.00
20 Kawat harmonika m 35,500.00 39,000.00
21 Kawat las listrik kg 36,500.00 40,000.00
22 Kawat Ø 4 mm kg 17,000.00 18,500.00
23 Jendela nako 13 daun psg 154,000.00 160,000.00
24 Besi angkur Ø 8 mm kg 17,500.00 19,200.00
25 Pagar kawat jaring kg 18,700.00 19,500.00
26 Pintu gulung besi m² 363,000.00 379,500.00
27 Pintu lipat bh 410,000.00 425,500.00
28 Skrup Fixer bh 900.00 1,000.00
29 Rel pintu dorong bh 75,000.00 82,500.00
30 Jaring kawat baja dilas m² 45,000.00 49,500.00
31 Rolling door alluminium m² 423,500.00 442,700.00

Page 6
32 Jendela nako (rangka + kaca 5 mm) m' 57,200.00 59,000.00
33 Kawat duri m' 13,000.00 14,000.00
34 Kunci lemari bh 10,800.00 11,300.00
35 Allumunium B kg 47,000.00 51,000.00
36 Allumunium C kg 47,000.00 51,000.00
37 Pengelasan cm 2,200.00 2,500.00
38 Pagar BRC 120 x 240 biasa unit 313,500.00 325,000.00
39 Pintu Dorong BRC/PMG ukuran 120 x 300 cm unit 2,057,000.00 2,150,500.00
40 Tiang pagar BRC/PMG 2" tinggi 150 cm btg 95,000.00 104,500.00
41 Alumunium 40.100.10 m' 72,500.00 75,000.00
42 Alumunium 40.100.12 m' 82,000.00 87,500.00
43 Alumunium 40.60.10 m' 60,000.00 65,000.00
44 Baja Konstruksi kg 16,500.00 18,000.00
45 Baja Profil kg 16,500.00 18,000.00
46 Besi U No. 8 kg 16,000.00 17,500.00
47 Elektroda kg 19,800.00 20,700.00
48 Elektroda Baja kg 27,500.00 28,700.00
49 Elektroda Stainless kg 22,000.00 23,000.00
50 Kawat Ayakan 2.5 mm m² 17,500.00 18,000.00
51 Kawat Ayakan 5 mm m² 15,500.00 17,000.00
52 Kawat Ayakan 10 mm m² 15,500.00 17,000.00
53 Kabel Sling Baja dia 1/2" m' 50,000.00 70,000.00
54 Kabel Sling Baja dia 1" m' 150,000.00 170,000.00
55 Kabel Sling Baja dia 1 1/4" m' 175,000.00 200,000.00
56 Kabel Sling Baja dia 1 1/2" m' 200,000.00 240,000.00
57 Kabel Sling Baja dia 2" m' 240,000.00 260,000.00
58 Karet kusen alumunium m' 3,800.00 4,000.00
59 Kawat Baja (bindrat) kg 15,000.00 17,000.00
60 Kawat Baja Hitam 10 mm kg 14,000.00 15,000.00
61 Kawat Nyamuk Kasa plastik m' 12,100.00 12,600.00
62 Pintu Fiberglass/PVC (low grade) bh 260,000.00 215,000.00
63 Pintu Fiberglass/PVC Kombinasi Kaca ( High Grade ) bh 780,000.00 858,000.00
64 Pintu Harmonika m² 935,000.00 1,055,000.00
65 Pintu Harmonika Folding Gate m² 825,000.00 907,500.00
66 Pintu Pagar Besi komplit dengan mainan m² 580,000.00 695,000.00
67 Pintu Rolling door m² 635,000.00 650,000.00
68 Pintu Swing ganda BRC/PMG uk. 1.2. X 3.00 m2 unit 3,000,000.00 3,250,000.00
69 Pipa Besi 2 1/2" medium m' 81,000.00 90,000.00
70 Pipa Besi Putih (stenlis) 1" medium m' 70,000.00 75,000.00
71 Pipa Besi Putih (stenlis) 1,5" medium m' 80,000.00 85,000.00
72 Plat Rambu bh 16,500.00 18,000.00
73 Plat Strip uk. 2" x 5" kg 15,000.00 17,000.00
74 Kawat Bronjong dia 3 dan 4 mm - (2 x 1 x 0.5) m kg 375,000.00 400,000.00
75 Plat Besi Cor kg 18,000.00 18,000.00
76 Roda gigi M.10 psg 6,500,000.00 7,000,000.00
77 Seal Karet m' 100,000.00 100,000.00
78 Spie bh 5,000.00 5,000.00
79 Splite Pen/Pengunci bh 50,000.00 50,000.00
80 Besi Siku kg 11,000.00 11,500.00
81 Angker Bolt 19 mm bh 25,000.00 25,000.00
82 Besi Bulat st. 42 kg 17,000.00 17,000.00
83 Besi Bulat st. 60 kg 18,000.00 18,000.00
84 Besi Cor kg 18,000.00 18,000.00
85 Besi Kanal kg 11,000.00 11,500.00
86 Dop (Bronze) kg 125,000.00 125,000.00
87 Dop (Besi Cor) kg 18,000.00 18,000.00
88 Drucklager kecil/besar bh 700,000.00 750,000.00
89 Mur Baut 1/2", 5/8", 7/8" kg 18,000.00 19,500.00
90 Na F + Ring bh 100,000.00 100,000.00
91 Nipple bh 2,000.00 2,000.00
92 Plat Bronze kg 125,000.00 125,000.00

V BAHAN UNTUK LANTAI


1 Tegel PC Abu-abu 20 x 20 cm bh 1,100.00 1,200.00

Page 7
2 Tegel PC Abu-abu 30 x 30 cm bh 2,900.00 3,100.00
3 Tegel PC Abu-abu 40 x 40 cm bh 5,500.00 5,700.00
4 Porselen (11x11) cm bh 700.00 750.00
5 Porselen (10x20) cm bh 1,100.00 1,200.00
6 Porselen (20x20) cm bh 1,900.00 2,000.00
7 Ubin Warna 20x20 cm bh 2,700.00 2,800.00
8 Ubin Warna 30x30 cm bh 3,300.00 3,400.00
9 Ubin Warna 40x40 cm bh 4,900.00 5,100.00
10 Tegel Keramik 10 x 20 cm bh 1,100.00 1,200.00
11 Tegel Keramik 20 x 20 cm bh 1,900.00 2,000.00
12 Tegel keramik 30 x 30 cm bh 4,000.00 4,400.00
13 Tegel Keramik 33 x 33 cm bh 4,900.00 5,100.00
14 Tegel keramik 10 x 30 cm bh 1,650.00 1,850.00
15 Keramik artistik (10x20) cm bh 1,100.00 1,200.00
16 Keramik artistik (5x20) cm bh 550.00 600.00
17 Tegel teraso 20 x 20 cm bh 1,600.00 1,700.00
18 Tegel teraso 30 x 30 cm bh 4,600.00 4,800.00
19 Tegel teraso 40 x 40 cm bh 8,800.00 9,200.00
20 Tegel wafel 20 x 20 bh 1,200.00 13,000.00
21 Ubin granit 30 X 30 Cm bh 22,500.00 23,500.00
22 Ubin granit 40 X 40 Cm bh 45,600.00 47,700.00
23 Plint keramik (10x20) cm bh 2,200.00 2,300.00
24 Plint keramik (10x10) cm bh 1,100.00 1,200.00
25 Plint keramik (5x20) cm bh 2,200.00 2,300.00
26 Plint ubin PC warna (10x20) cm bh 2,700.00 2,800.00
27 Plint ubin PC warna (10x30) cm bh 3,000.00 3,100.00
28 Plint ubin PC warna (10x40) cm bh 3,500.00 3,700.00
29 Plint ubin teraso (10x30) cm bh 3,300.00 3,400.00
30 Plint ubin teraso (10x40) cm bh 3,800.00 4,000.00
31 Plint ubin granit (10x40) cm bh 7,500.00 8,250.00
32 Plint ubin granit (10x30) cm bh 4,000.00 4,500.00
33 Plint ubin teralux kerang (10x40) cm bh 6,500.00 7,150.00
34 Plint ubin teralux kerang (10x30) cm bh 10,000.00 11,000.00
35 Plint ubin teralux marmer (10x60) cm bh 25,000.00 27,500.00
36 Plint ubin teralux marmer (10x40) cm bh 17,500.00 19,000.00
37 Plint ubin teralux marmer (10x30) cm bh 13,700.00 15,000.00
38 Tegel Keramik dinding (20 x 25) cm bh 2,300.00 2,500.00
39 Ubin Keramik artistik (10 x 20) cm bh 1,100.00 1,200.00
40 Ubin Keramik artistik (10 x 10) cm bh 550.00 600.00
41 Ubin Keramik artistik (5 x 20) cm bh 550.00 600.00
42 Ubin teralux kerang 30 x 30 Cm bh 13,500.00 15,000.00
43 Ubin teralux kerang 40 x 40 Cm bh 20,000.00 21,500.00
44 Internal cove artistik (5x5x20) cm bh 6,700.00 7,200.00
45 Bahan teraso cor m³ 450,000.00 485,000.00
46 Panel beton pracetak lbr 253,000.00 264,500.00
47 Kolom beton pracetak btg 363,000.00 379,500.00
48 Hollowblock (HB.20) bh 14,300.00 14,900.00
49 Hollowblock (HB.15) bh 11,000.00 11,500.00
50 Hollowblock (HB.10) bh 8,800.00 9,200.00
51 Terawang (Roster) bh 9,900.00 10,300.00
52 Gymfloor m² 125,000.00 137,500.00
53 Floor hardener kg 30,800.00 32,200.00
54 Mosaik (30 X 30) Cm bh 4,900.00 5,100.00
55 Marmer (100 X 100) Cm bh 250,000.00 275,000.00
56 Karpet m² 25,000.00 28,700.00
57 Parquet m² 320,000.00 350,000.00
58 Gymfloor (lantai kayu) bh 50,000.00 53,000.00
59 Batu tempel hitam m² 151,200.00 158,100.00
60 Vinyl (30x30) cm KL I bh 34,600.00 36,200.00
61 Lem Vinyl kg 18,000.00 18,900.00
62 Wall Paper lebar 50 cm m 53,000.00 58,000.00
63 Vinyl karet (30x30) cm bh 45,000.00 48,800.00
64 Granit 60x60 (merk granito) m² 192,500.00 201,200.00
65 Parquet HDF m² 278,000.00 300,000.00

Page 8
66 Plint parquet HDF m 57,500.00 62,500.00
67 Keramik 39 x 39 rectified m² 82,000.00 87,000.00
68 Keramik 50 x 50 rectified m² 105,000.00 115,000.00
69 Kuku Macan keramik bh 800.00 850.00
70 Paving stone (ex pabrikan K300) persegi abu-abu tebal 6 cm m² 68,000.00 73,000.00
71 Paving stone (ex pabrikan K400) persegi abu-abu tebal 6 cm m² 87,500.00 92,500.00
72 Paving stone (ex pabrikan K300) persegi warna tebal 6 cm m² 78,000.00 83,000.00
73 Paving stone (ex pabrikan K400) persegi warna tebal 6 cm m² 97,500.00 102,500.00
74 Paving stone (ex pabrikan K300) persegi abu-abu tebal 8 cm m² 78,000.00 83,000.00
75 Paving stone (ex pabrikan K400) persegi abu-abu tebal 8 cm m² 98,500.00 103,500.00
76 Paving stone (ex pabrikan K300) persegi warna tebal 8 cm m² 88,000.00 93,000.00
77 Paving stone (ex pabrikan K400) persegi warna tebal 8 cm m² 107,500.00 112,500.00
78 Paving stone (lokal-manual) persegi abu-abu tebal 6 cm halus m² 28,000.00 33,000.00
79 Paving stone (lokal-mesin press) persegi abu-abu tebal 6 cm kasar m² 48,000.00 53,000.00
80 Paving stone (lokal-manual)persegi abu-abu tebal 8 cm halus m² 32,500.00 37,500.00
81 Paving stone (lokal-mesin press) persegi abu-abu tebal 8 cm kasar m² 52,500.00 57,500.00
82 Plint Cove Keramik 10 x 20 m' 75,000.00 85,000.00
83 Plint Cove Granite 10 x 20 m' 120,000.00 130,000.00
84 Tegel Trotoar m² 11,000.00 12,500.00
85 Under Layer Foam Sheet m² 12,500.00 14,000.00

VI BAHAN UNTUK PENGECATAN


1 Cat besi Emco kg 47,800.00 50,000.00
2 Cat kayu Emco kg 45,000.00 48,500.00
3 Cat meni (besi/kayu) cap Pedang kg 28,000.00 31,000.00
4 Cat residu ltr 12,800.00 14,000.00
5 Meni A kg 18,500.00 20,000.00
6 Meni B kg 15,000.00 16,500.00
7 Cat tembok Vinilek, Aviapaint (sejenis) kg 27,500.00 30,000.00
8 Cerlak kg 30,000.00 33,000.00
9 Politur ltr 26,600.00 29,000.00
10 Politur jadi ltr 39,000.00 42,800.00
11 Vernis ltr 35,000.00 38,500.00
12 Dempul kg 19,300.00 20,200.00
13 Minyak cat/ afduner ltr 22,000.00 23,500.00
14 Teer kg 18,000.00 20,000.00
15 Kertas gosok/ Ampelas lbr 3,200.00 3,500.00
16 Plamur tembok kg 19,800.00 20,700.00
17 Plamur kayu kg 19,800.00 20,700.00
18 Plamur Besi kg 27,000.00 295,000.00
19 Spiritus ltr 11,200.00 13,000.00
20 Lem kayu kg 27,200.00 29,900.00
21 Thinner B / minyak cat ltr 11,500.00 12,000.00
22 Soda api kg 18,700.00 19,500.00
23 Sabun kg 13,700.00 14,300.00
24 Teak Oil ltr 60,000.00 65,000.00
25 Kuas bh 11,200.00 11,700.00
26 Kalkarium kg 17,000.00 18,700.00
27 Alang-alang ikat 5,500.00 5,700.00
28 Alkali Primer Coat / Wallsealer Anti Alkali (Eksterior) ltr 40,000.00 45,000.00
29 Blass Bit kg 27,500.00 28,700.00
30 Cat Bron kg 42,000.00 45,000.00
31 Cat Exterior Weathercoat/weatherproof kg 57,500.00 63,250.00
32 Cat Interior ex Mowilex, Dulux, Jotun - setara ltr 49,000.00 53,900.00
33 Cat Marka kg 49,500.00 51,700.00
34 Cat Tembok Decolit (sejenis) kg 15,500.00 18,000.00
35 Metilen / Lem wallpaper kg 27,500.00 28,700.00
36 Thinner A ltr 19,500.00 23,500.00
37 Wallpaper ex lokal / china lbr 115,000.00 120,000.00
38 Wallpaper ex Japan / Eropa / USA lbr 250,000.00 287,500.00
39 Wallsealer non anti alkali (Interior) ltr 24,000.00 29,000.00
40 Waterproofing Membrane m² 120,000.00 125,000.00
41 Waterproofing Primer ltr 20,000.00 25,000.00
42 Waterproofing Screed kg 26,000.00 31,000.00

Page 9
VII BAHAN PENGGANTUNG DAN PENGUNCI
1 Engsel H stl 9,600.00 10,000.00
2 Engsel Kuningan arch asli stl 25,300.00 26,400.00
3 Engsel jendela bh 18,850.00 21,000.00
4 Engsel angin bh 18,000.00 19,800.00
5 Engsel pintu bh 16,500.00 17,200.00
6 Espanyolet stl 30,000.00 33,000.00
7 Grendel bj 10,500.00 11,000.00
8 Grendel biasa (besar) bh 15,300.00 16,200.00
9 Grendel biasa (kecil) bh 9,100.00 9,500.00
10 Grendel tanam bh 42,500.00 45,000.00
11 Kunci tanam antik bh 157,500.00 165,000.00
12 Kunci tanam (808) bj 10,000.00 11,300.00
13 Kunci tanam besar kuda terbang 2 x putar bj 59,400.00 62,100.00
14 Kunci tanam kamar mandi bh 29,700.00 31,000.00
15 Kunci silinder bh 82,500.00 90,000.00
16 Spring knip bh 26,100.00 27,300.00
17 Door closer bh 203,500.00 212,700.00
18 Door stop bh 25,000.00 27,500.00
19 Door holder bh 70,000.00 73,200.00
20 Kunci selot bh 57,000.00 62,000.00
21 Hak angin bj 27,500.00 30,200.00
22 Hak angin 4 mm (lurus) bj 15,000.00 17,200.00
23 Kait angin bh 12,600.00 13,200.00
24 Pegangan pintu bh 165,000.00 181,000.00
25 Pintu aluminium m 302,500.00 316,200.00
26 Kunci tanam biasa bh 47,500.00 52,000.00
27 Grendel Kuningan / crom (kecil) bh 18,000.00 20,000.00
28 Hak Angin (sikutan) bh 10,000.00 11,000.00
29 Hak Angin lurus (bisa disetel maju/mundur) stel 15,000.00 16,500.00
30 Handle Engkol Stainless stel 75,000.00 85,000.00
31 Handle Tarik Stainless stel 97,500.00 102,000.00
32 Kunci Tanam Grade A, ex Solid, Dekkson, Logo - setara stel 125,000.00 137,500.00
33 Kunci Tanam Grade B, Muller, Cavell, setara stel 87,500.00 95,000.00
34 Rambucis bh 45,000.00 50,000.00

VIII BAHAN UNTUK KM/WC/URINOIR


1 Pipa / slang spiral saluran kran set 45,000.00 48,000.00
2 Closet duduk putih porselin komplit bh 1,850,000.00 2,000,000.00
3 Closet jongkok porselin warna putih bh 203,500.00 212,000.00
4 Closet jongkok teraso bh 88,000.00 92,000.00
5 Bak teraso bh 85,000.00 93,500.00
6 Bak cuci stainless steel bh 250,000.00 275,000.00
7 Bak cuci teraso bh 150,000.00 166,000.00
8 Seal tape bh 3,500.00 4,000.00
9 Wastafel bh 522,500.00 546,200.00
10 Kran air bh 23,600.00 24,700.00
11 Sumur peresap unit 3,000,000.00 3,300,000.00
12 Water drain + Assesories set 85,000.00 95,000.00
13 Urinoir bh 2,000,000.00 2,200,000.00
14 Floor drain bh 25,000.00 30,000.00
15 Bakdip bh 26,400.00 27,600.00
16 Bak fibreglass bh 225,000.00 250,000.00
17 Air Ltr 80.00 100.00
18 Rol TBA bh 9,200.00 10,000.00
19 Selang Biasa m' 5,000.00 6,000.00
20 Sifon Wasser set 60,000.00 65,000.00
21 Tandon Air Fiberglass Kapasitas 100 L bh 275,000.00 287,500.00
22 Tandon Air Fiberglass Kapasitas 200 L / 250 bh 522,500.00 546,200.00

IX BAHAN JENIS KACA


1 Kaca polos tb. 3 mm m² 75,000.00 80,000.00
2 Kaca polos tb. 5 mm m² 93,500.00 97,700.00

Page 10
3 Kaca polos tb. 8 mm m² 220,000.00 243,000.00
4 Kaca rayban tb. 5mm m² 121,000.00 126,500.00
5 Krepyak kaca nako + kerangka lbr 45,000.00 49,500.00
6 Venetions blinds dan vertical blinds (tirai) m2 278,300.00 290,900.00
7 Profil kaca m 8,200.00 8,600.00
8 Sealant tube 28,000.00 30,800.00
9 Kaca buram m² 150,000.00 170,000.00
10 Kaca cermin 5 mm m² 137,500.00 143,700.00
11 Kaca cermin 6 mm m² 157,800.00 165,000.00
12 Kaca cermin 8 mm m² 214,500.00 224,200.00
13 Kaca wireglass m² 605,000.00 632,500.00
14 Kaca patri m² 1,100,000.00 1,150,000.00

X BAHAN BETON CETAKAN


1 Buis beton diameter 15 cm 100 cm bh 25,000.00 28,000.00
2 Buis beton diameter 20 cm 100 cm bh 32,600.00 35,800.00
3 Buis beton diameter 30 cm 100 cm bh 50,000.00 55,000.00
4 Buis beton diameter 40 cm 100 cm bh 60,000.00 65,000.00
5 Buis beton diameter 50 cm 100 cm bh 148,500.00 155,200.00
6 Buis beton diameter 60 cm 100 cm bh 192,500.00 201,200.00
7 Buis beton diameter 80 cm 100 cm bh 165,000.00 172,500.00
8 Buis beton diameter 100 cm 100 cm bh 198,000.00 207,000.00
9 Buis beton U 15 cm bh 14,800.00 15,500.00
10 Buis beton U 20 cm bh 20,000.00 25,000.00
11 Buis beton U 30 cm bh 25,000.00 30,000.00
12 Buis beton U 40 cm bh 33,000.00 34,500.00
13 Buis beton U 50 cm bh 55,000.00 57,500.00
14 Buis Beton U 80 cm pcs 71,500.00 74,700.00

XI BAHAN PLASTIK PIPA PVC


1 Keni PVC 1/2" bh 1,600.00 1,700.00
2 Keni PVC 3/4" bh 2,200.00 2,300.00
3 Keni PVC 2" bh 6,600.00 6,900.00
4 Keni PVC 3" bh 10,400.00 10,900.00
5 Keni PVC 4" bh 33,000.00 34,500.00
6 Keni PVC 5" bh 38,000.00 41,700.00
7 Klem PVC bh 3,000.00 3,200.00
8 Pipa paralon 5/8" panjang 4.00 mt (Maspion) ljr 5,500.00 6,000.00
9 Pipa PVC 1/2" panjang 4.00 mt (Maspion) ljr 23,000.00 25,000.00
10 Pipa PVC 3/4" panjang 4.00 mt (Maspion) ljr 28,000.00 30,000.00
11 Pipa PVC 2" panjang 4.00 mt (Maspion) ljr 63,800.00 68,500.00
12 Pipa PVC 3" panjang 4.00 mt (Maspion) ljr 120,000.00 132,000.00
13 Pipa PVC 4" panjang 4.00 mt (Maspion) ljr 182,500.00 200,000.00
14 Pipa PVC 1/2" type AW panjang 6.00 mt ljr 21,000.00 22,500.00
15 Pipa PVC 3/4" type AW panjang 6.00 mt ljr 27,500.00 30,000.00
16 Pipa PVC 1" type AW panjang 6.00 mt ljr 38,500.00 40,000.00
17 Pipa PVC 1½" type AW panjang 6.00 mt ljr 61,700.00 64,500.00
18 Pipa PVC 2" type AW panjang 6.00 mt ljr 76,500.00 80,000.00
19 Pipa PVC 2½" type AW panjang 6.00 mt ljr 115,200.00 120,500.00
20 Pipa PVC 3" type AW panjang 6.00 mt ljr 155,400.00 162,400.00
21 Pipa PVC 4" type AW panjang 6.00 mt ljr 257,700.00 269,400.00
22 Pipa PVC 5" type AW panjang 6.00 mt ljr 320,000.00 352,000.00
23 Bend 22.5' dia 2" PVC (All Flange) bh 169,700.00 186,500.00
24 Bend 22.5' dia 3" PVC (All Flange) bh 171,600.00 188,700.00
25 Bend 22.5' dia 4" PVC (All Flange) bh 229,700.00 252,500.00
26 Bend 45' dia 2" PVC (All Flange) bh 172,800.00 190,000.00
27 Bend 45' dia 3" PVC (All Flange) bh 199,700.00 219,500.00
28 Bend 45' dia 4" PVC (All Flange) bh 251,625.00 276,700.00
29 Bend 90' dia 2" PVC (All Flange) bh 176,800.00 194,400.00
30 Bend 90' dia 3" PVC (All Flange) bh 268,875.00 295,700.00
31 Bend 90' dia 4" PVC (All Flange) bh 293,300.00 322,500.00
32 Bend 45' dia 2" GI bh 50,000.00 55,000.00
33 Bend 45' dia 3" GI bh 78,500.00 86,000.00
34 Bend 45' dia 4" GI bh 114,000.00 125,000.00

Page 11
35 Bend 90' dia 2" GI bh 57,000.00 62,500.00
36 Bend 90' dia 3" GI bh 85,500.00 94,000.00
37 Bend 90' dia 4" GI bh 128,500.00 141,000.00
38 Dop 2" PVC bh 8,900.00 9,700.00
39 Dop 3" PVC bh 16,900.00 18,500.00
40 Dop 4" PVC bh 28,200.00 31,000.00
41 Flange drat dia 2" GI bh 71,500.00 78,500.00
42 Flange drat dia 3" GI bh 107,250.00 117,500.00
43 Flange drat dia 4" GI bh 143,000.00 157,000.00
44 Flange las dia 2" GI bh 40,400.00 44,000.00
45 Flange las dia 3" GI bh 50,200.00 55,000.00
46 Flange las dia 4" GI bh 60,500.00 66,500.00
47 Flange socket dia 2" PVC bh 83,100.00 91,400.00
48 Flange socket dia 3" PVC bh 110,000.00 121,000.00
49 Flange socket dia 4" PVC bh 147,700.00 162,400.00
50 Gate valve 2" bh 351,900.00 387,000.00
51 Gate valve 3" bh 622,700.00 684,500.00
52 Gate valve 4" bh 799,000.00 879,900.00
53 Giboltjoint 2" PVC bh 75,000.00 82,500.00
54 Giboltjoint 3" PVC bh 110,200.00 121,200.00
55 Giboltjoint 4" PVC bh 186,500.00 205,000.00
56 Giboltjoint 2" GI bh 75,800.00 83,300.00
57 Giboltjoint 3" GI bh 111,300.00 122,400.00
58 Giboltjoint 4" GI bh 177,300.00 195,000.00
59 Pipa PVC 1/2" 6.00 m' S-12.5 ljr 13,700.00 15,300.00
60 Pipa PVC 1 " 6.00 m' S-12.5 ljr 32,600.00 36,500.00
61 Pipa PVC 1 1/2" 6.00 m' S-12.5 ljr 76,700.00 84,400.00
62 Pipa PVC 2" 6.00 m' S-12.5 ljr 112,600.00 123,900.00
63 Pipa PVC 2 1/2" 6.00 m' S-12.5 ljr 161,000.00 176,700.00
64 Pipa PVC 3" 6.00 m' S-12.5 ljr 232,800.00 250,000.00
65 Pipa PVC 4" 6.00 m' S-12.5 ljr 728,900.00 758,900.00
66 Pipa PVC 1" AW ex Wavin ljr 30,000.00 33,000.00
67 Pipa PVC 2" AW ex Wavin ljr 63,500.00 69,500.00
68 Pipa PVC 3" type AW - 4 m ljr 120,000.00 132,000.00
69 Pipa PVC 4" type AW - 4 m ljr 198,000.00 217,800.00
70 Reducer dia 2" x 1 1/2" PVC bh 10,800.00 11,500.00
71 Reducer dia 3" x 2" PVC bh 31,900.00 35,000.00
72 Reducer dia 4" x 3" PVC bh 55,600.00 61,000.00
73 Stop Kran 1/2" bh 30,000.00 33,000.00
74 Stop Kran 3/4" bh 41,400.00 45,500.00
75 Stop Kran 1" bh 51,700.00 56,500.00
76 Stop Kran 1 1/4" bh 110,500.00 121,500.00
77 Stop Kran 1 1/2" bh 162,300.00 178,500.00
78 Stop Kran 2" bh 158,700.00 174,500.00
79 Stop Kran 2 1/2" bh 327,000.00 359,700.00
80 Stop Kran 3" bh 675,200.00 742,700.00
81 Stop Kran 4" bh 875,400.00 962,500.00
82 Tee' dia 2" x 2" (All Flange) bh 212,400.00 218,400.00
83 Tee' dia 3" x 2" (All Flange) bh 295,450.00 313,700.00
84 Tee' dia 3" x 3" (All Flange) bh 333,950.00 355,900.00
85 Tee' dia 4" x 2" (All Flange) bh 323,400.00 338,325.00
86 Tee' dia 4" x 3" (All Flange) bh 379,850.00 403,300.00
87 Tee' dia 4" x 4" (All Flange) bh 413,450.00 430,900.00
88 Tee' dia 2" x 2" PVC (All Sock) bh 47,300.00 52,000.00
89 Tee' dia 3" x 2" PVC (All Sock) bh 80,300.00 88,300.00
90 Tee' dia 3" x 3" PVC (All Sock) bh 95,700.00 105,200.00
91 Tee' dia 4" x 3" PVC (All Sock) bh 149,200.00 164,000.00
92 Tee' dia 4" x 4" PVC (All Sock) bh 158,000.00 173,800.00
93 Trek mur bh 31,500.00 34,650.00
94 Water mur 1/2" bh 12,300.00 13,500.00
95 Water mur 3/4" bh 15,100.00 16,500.00
96 Water mur 1" bh 18,300.00 20,000.00
97 Water mur 1 1/4" bh 25,800.00 28,300.00
98 Water mur 1 1/2" bh 34,500.00 37,500.00

Page 12
99 Water mur 2" bh 49,500.00 54,000.00
100 Water mur 2.5" bh 86,200.00 94,800.00
101 Water mur 3" bh 135,700.00 149,200.00
102 Water mur 4" bh 258,500.00 284,300.00

XII BAHAN JENIS PAKU


1 Paku asbes bh 550.00 600.00
2 Paku reng kg 14,500.00 15,100.00
3 Paku triplek kg 20,000.00 21,000.00
4 Paku usuk kg 14,500.00 15,100.00
5 Paku Kalsiboard kg 22,000.00 23,000.00
6 Paku Payung kg 20,000.00 21,000.00
7 Paku Sekrup dos 8,200.00 8,500.00
8 Paku Keling 3/4", 5/8", 7/8" kg 22,000.00 23,000.00

XIII BAHAN PERALATAN LISTRIK


1 Stop kontak (Broco) bh 15,000.00 17,000.00
2 Sakelar (Broco) bh 13,700.00 15,000.00
3 Sakelar / hendel bh 24,000.00 25,000.00
4 Zekering lengkap bh 44,000.00 46,000.00
5 Zekering SPA 60 Amp. bh 14,000.00 15,500.00
6 Panel box bh 200,000.00 220,000.00
7 Lampu pijar 25,40,75 / 220 V bh 24,500.00 25,600.00
8 Lampu TL 20 W / 220 V komplit balast, kaca (Philips) bh 60,000.00 65,000.00
9 Lampu TL 40 W / 220 V komplit balast, kaca (Philips) bh 85,000.00 90,000.00
10 Capasitor sox 20 mf/ 250 v bh 14,500.00 15,500.00
11 Capasitor sox 90 W 10 mf/ 250 v bh 18,500.00 20,000.00
12 Fiting plafon bh 10,500.00 11,500.00
13 Isolator bh 1,600.00 1,700.00
14 Las doof bh 1,600.00 1,700.00
15 Stater lampu TL bh 3,300.00 3,400.00
16 T doos PVC bh 1,600.00 1,700.00
KABEL
1 Kabel NYA 1 x 2.5 mm m' 2,500.00 3,000.00
2 Kabel NYA 1000 Volt 1 x 1.5 mm2 m' 1,500.00 1,700.00
3 Kabel NYA 1000 Volt 1 x 2.5 mm2 m' 2,500.00 3,000.00
4 Kabel NYA 1000 Volt 1 x 2 mm2 m' 5,000.00 5,500.00
5 Kabel NYFGBY 4 x 10 mm m' 80,000.00 87,500.00
6 Kabel NYFGBY 4 x 16 mm m' 110,000.00 120,000.00
7 Kabel NYFGBY 4 x 4 mm m' 47,500.00 52,000.00
8 Kabel NYFGBY 4 x 6 mm m' 60,000.00 65,000.00
9 Kabel NYFGBY/ NYRGBY 4 x 4 mm m' 47,000.00 60,000.00
10 Kabel NYFGBY/ NYRGBY 4 x 6 mm m' 59,000.00 65,000.00
11 Kabel NYFY/ NYM 4 x 2.5 mm m' 13,500.00 15,000.00
12 Kabel NYM 2 x 1.5 mm m' 6,500.00 7,500.00
13 Kabel NYM 2 x 2.5 mm m' 8,500.00 9,500.00
16 Kabel NYM 3 x 1.5 mm m' 8,000.00 11,000.00
14 Kabel NYM 500 Volt 2 x 4.0 mm m' 11,500.00 12,500.00
15 Kabel NYM 500 Volt 2 x 6.0 mm m' 15,500.00 17,000.00
16 Kabel NYY 2 x 1,5 mm m' 6,800.00 7,500.00
17 Kabel NYY 2 x 2.5 mm m' 12,000.00 13,500.00
18 Kabel NYY 4 x 10 mm m' 50,000.00 55,000.00
19 Kabel NYY 4 x 16 mm m' 98,000.00 108,000.00
20 Kabel NYY 4 x 2.5 mm m' 17,500.00 18,000.00
21 Kabel NYY 4 X 4 MM m' 20,000.00 25,000.00
22 SR 2 X 10 MM m' 4,000.00 7,500.00
23 SR 2 X 16 MM m' 6,500.00 10,000.00
24 NYAF 1 X 1 MM m' 2,500.00 5,000.00
25 Kabel Perakitan NYAF 1x 10 m' 18,000.00 20,000.00
26 Kabel skoen m' 10,000.00 11,000.00
27 Kabel twisted 2 x 10 mm m' 3,500.00 4,500.00
28 Kabel twisted 4 x 16 mm m' 35,000.00 45,000.00

XIV SEWA ALAT

Page 13
1 Sewa Theodolit hari
2 Sewa Waterpass hari 250,000.00 275,000.00
3 Sewa Pompa Air 5 KW hari 200,000.00 220,000.00
4 Sewa Pompa Air 10 KW hari 450,000.00 495,000.00
5 Sewa Pompa Air 20 KW hari 850,000.00 935,000.00

XV BAHAN BBM
1 Bensin liter 7,000.00 7,500.00
2 Premium Industri liter 10,000.00 10,500.00
3 Solar liter 7,000.00 7,500.00
4 Solar Industri liter 11,500.00 12,000.00
5 Minyak Tanah liter 9,300.00 9,700.00
6 Aspal AC (AC 60 - 70) curah kg 9000 kg 10,000.00 10,500.00
7 Aspal Emulsi kg 13,500.00 14,500.00
8 Butonic Aspal (Aspal beton) ton 7,500.00 8,000.00
9 Aspal drum kg 11,500.00 11,800.00
10 Minyak Aspal ltr 7,500.00 8,000.00
11 Minyak Diesel/Solar ltr 7,000.00 7,500.00
12 Minyak Pelumas ltr 27,500.00 28,700.00
13 Minyak Rem ltr 27,500.00 28,700.00
14 Oli Mesin ltr 32,500.00 35,000.00
15 Aspal kemas kg 10,500.00 11,200.00

XVI POMPA AIR


1 Pompa Tangan 258,500.00 270,200.00
2 Pompa Tangan Fuji 275,000.00 287,500.00
3 Pompa Listrik : Panasonik
Kapasitas : L/dt 200 W 550,000.00 575,000.00
Kapasitas : L/dt 125 W 385,000.00 402,500.00
4 Mesin Pompa Air 5.5 PK (Honda) unit 3,000,000.00 3,300,000.00
5 Mesin Pompa Air 8.5 PK (Yanmar) unit 9,500,000.00 10,500,000.00
6 Mesin Pompa Air 8.5 PK (Kubota) unit 9,500,000.00 10,500,000.00
7 Mesin Tangki Sprayer unit 1,400,000.00 1,500,000.00

XVII PERALATAN
1 Alat Bantu set 60,000.00 65,000.00
2 Alat potong rumput Tanaka 1,6 Hp/ 7200 Rpm unit 5,000,000.00 5,500,000.00
3 Bak Sampah bh 40,000.00 44,000.00
4 Ban Gerobak Luar bh 52,000.00 65,000.00
5 Ban Gerobak Dalam bh 17,500.00 20,000.00
6 Benang rol 2,000.00 2,500.00
7 Cangkul (lengkap) bh 75,000.00 78,000.00
8 Cetok bh 15,000.00 25,000.00
9 Chipping m³ 48,000.00 52,800.00
10 Cikrak Bambu bh 6,000.00 8,000.00
11 Cikrak Seng bh 10,000.00 12,500.00
12 Cintung bh 20,000.00 22,000.00
13 Drum Pemasak Aspal bh 20,000.00 25,000.00
14 Ember bh 7,500.00 9,000.00
15 Ganco bh 37,500.00 40,000.00
16 Garuk Besar bh 27,500.00 35,000.00
17 Garuk Kecil bh 22,500.00 24,750.00
18 Gedek Bambu Petung bh 40,000.00 42,500.00
19 Gembok Besar bh 60,000.00 65,000.00
20 Gembok Kecil bh 40,000.00 43,500.00
21 Gergaji besi sedang (Cainsow) unit 7,100,000.00 7,450,000.00
22 Gergaji besi besar (Cainsow) unit 11,000,000.00 11,550,000.00
23 Gunting tanaman bh 50,000.00 27,000.00
24 Hand sprayer swan 14 Lt bh 400,000.00 450,000.00
25 Jas Hujan bh 55,000.00 60,000.00
26 Karung Goni bh 7,500.00 8,000.00
27 Karung Plastik lbr 2,500.00 3,000.00
28 Kasut Kayu bh 10,000.00 12,000.00
29 Kayu Pemikul dan Tali stel 25,000.00 30,000.00

Page 14
30 Klaker Roda bh 10,000.00 11,000.00
31 Kunci pemotong baja bh 70,000.00 75,000.00
32 Kontainer unit 40,000,000.00 45,000,000.00
33 Kotak Adukan bh 80,000.00 90,000.00
34 Kranjang Bambu bh 15,000.00 16,500.00
35 Linggis bh 100,000.00 105,000.00
36 Meteran - 30 s/d 50 m bh 100,000.00 105,000.00
37 Palu Besar bh 35,000.00 50,000.00
38 Palu Kecil bh 20,000.00 21,000.00
39 Rambu Pengaman bh 300,000.00 310,000.00
40 Gerobag Artco stel 385,000.00 400,000.00
41 Sabit bh 35,000.00 37,000.00
42 Sand bag (kantong pasir) lbr 2,500.00 3,000.00
43 Sapu Lidi bh 3,000.00 3,500.00
44 Senter bh 30,000.00 35,000.00
45 Sepatu Lapangan psg 55,000.00 60,000.00
46 Sikat baja bh 6,500.00 7,000.00
47 Skop Kecil bh 35,000.00 45,000.00
48 Tali Rapia m' 500.00 125.00
49 Tang Pemotong bh 17,500.00 20,000.00
50 Tong Sampah Komplit (Besar) bh 200,000.00 220,000.00
51 Tong Sampah Komplit (Kecil) bh 150,000.00 165,000.00
52 Tong Sampah Komplit (Sedang) bh 50,000.00 75,000.00
53 Tusuk Bambu dos 7,000.00 7,500.00
PERALATAN Pertamanan/Sampah
A Mesin Potong Rumput
1 Busi bh 12,000.00 13,000.00
2 CDI bh 161,200.00 177,500.00
3 Olor gas bh 154,500.00 170,000.00
4 Olor potong rumput bh 322,000.00 354,000.00
5 Pack silinder bh 232,000.00 255,000.00
6 Peso potong rumput bh 26,000.00 28,000.00
7 Pier seker set 110,700.00 122,000.00
8 Stang seker bh 193,200.00 212,500.00
9 Tangki bensin bh 193,200.00 212,500.00
B Mesin Pembasmi Hama
1 Busi bh 12,000.00 13,000.00
2 Herbisida ltr 103,000.00 154,500.00
3 Insectisida ltr 257,500.00 309,000.00
4 Pier seker set 111,500.00 122,500.00
5 Selang keluar dan sprayer set 618,000.00 679,800.00

XVIII JENIS SPARE PART KENDARAAN


A BOOLDOZER HITACHI DX 75
1 Filter udara bh 1,050,000.00 1,155,000.00
2 Filter solar bh 735,200.00 808,700.00
3 Filtr hyd tranmi bh 1,890,000.00 2,079,000.00
4 Hydroulik hose oil lines bh 5,950,000.00 6,545,000.00
5 Seat rolek dan shaf bh 7,700,000.00 8,470,000.00
6 Drive sprocket bh 43,312,000.00 47,643,000.00
7 Hidoulik hose components bh 6,105,000.00 6,715,500.00
8 Track cain /link/rante bh 36,960,000.00 40,656,000.00
9 Shoe groser bh 250,000.00 275,000.00
10 Gear psg 14,500,000.00 15,950,000.00
11 Gear bh 17,500,000.00 19,250,000.00
12 Pinion gear psg 9,100,000.00 10,010,000.00
13 Oring psg 138,500.00 152,000.00
14 Seal kit set - 4,250,000.00 4,675,000.00
15 Bearing set psg 12,197,000.00 13,416,000.00
16 Carry roller - 13,312,000.00 14,643,000.00
B PICK UP ISUZU
1 Filter udara bh 112,000.00 123,000.00
2 Filter solar bh 56,000.00 61,500.00
3 Filter olie mesin bh 7,000.00 7,500.00

Page 15
4 Kampas rem belakang set 252,000.00 277,000.00
5 Kampas rem muka set 252,000.00 277,000.00
6 Karet kleyer rem belakang bh 14,000.00 15,000.00
7 Karet kleyer rem muka bh 14,000.00 15,000.00
8 Kleyer kopling bh 700,000.00 770,000.00
9 Kampas kopling bh 700,000.00 770,000.00
10 Klaker dinamo amper bh 49,000.00 53,500.00
11 Klaker dinamo stater bh 49,000.00 53,500.00
12 Bostel amper bh 28,000.00 30,500.00
13 Bostel stater bh 56,000.00 61,500.00
14 Timeng bel bh 616,000.00 677,500.00
15 Lampu depan 2x bh 140,000.00 154,000.00
16 Lampu Belakang bh 115,000.00 126,500.00
17 Kaca spion bh 56,000.00 61,500.00
18 Kipas kaca bh 42,000.00 46,000.00
19 Baut Roda bh 23,000.00 25,000.00
20 Karet bos pir bh 56,000.00 61,500.00
21 Olie sheel garden bh 112,000.00 123,000.00
22 Kaca depan besar psg 700,000.00 770,000.00
23 Kampas hanrem psg 84,000.00 92,000.00
C PICK UP SUZUKI
1 Filter udara bh 70,000.00 77,000.00
2 Filter bensin bh 56,000.00 61,500.00
3 Filter olie mesin bh 56,000.00 61,500.00
4 Kampas rem belakang set 112,000.00 123,000.00
5 Kampas rem muka set 112,000.00 123,000.00
6 Karet kleyer rem belakang bh 14,000.00 15,000.00
7 Olor spidometer bh 112,000.00 123,000.00
8 Cat-catan + kenteng ls 4,200,000.00 4,620,000.00
9 Kampas kopling bh 420,000.00 462,000.00
10 Klaker roda belakang bh 98,000.00 107,500.00
11 Klaker roda muka bh 56,000.00 61,500.00
12 Timeng bel bh 252,000.00 277,000.00
13 Klaker dinamo amper bh 49,000.00 53,500.00
14 Klaker dinamo stater bh 42,000.00 46,000.00
15 Bostel dinamo amper bh 28,000.00 30,500.00
16 Olie sheel roda belakang bh 56,000.00 61,500.00
17 Olie sheel roda muka bh 56,000.00 61,500.00
18 Lampu 2x bh 196,000.00 215,500.00
19 Klep keluar bh 70,000.00 77,000.00
20 Klep Masuk bh 70,000.00 77,000.00
21 Bel/ klakson bh 84,000.00 92,000.00
22 Accu 12 V N 40Z bh 490,000.00 539,000.00
23 Pir sekker set 700,000.00 770,000.00
24 Kipas kaca bh 42,000.00 46,000.00
25 Baut roda bh 20,500.00 22,500.00
26 Pakset set 560,000.00 616,000.00
27 Kresjuen bh 126,000.00 138,500.00
28 Terot bh 126,000.00 138,500.00
29 Kaca spion bh 56,000.00 61,500.00
30 Olie sheel preseneleng bh 63,000.00 69,000.00
31 Matahari bh 525,000.00 577,500.00
32 Reel kaca pintu bh 56,000.00 61,500.00
33 Karet pir bh 14,000.00 15,000.00
34 Jok bh 840,000.00 924,000.00
35 Knalpot bh 364,000.00 400,000.00
D DUMP TRUCK DAIHATSU
1 Filter udara bh 84,000.00 92,000.00
2 Filter solar bh 56,000.00 61,500.00
3 Filter olie mesin bh 70,000.00 77,000.00
4 Kampas rem belakang bh 224,000.00 246,000.00
5 Kampas rem muka bh 210,000.00 231,000.00
6 Karet Kleyer rem belakang set 14,000.00 15,000.00
7 Karet Kleyer Roda Belakang bh 23,800.00 26,000.00

Page 16
8 Karet Kleyer Roda Depan bh 23,800.00 26,000.00
9 Karet Kleyer Rem Atas bh 308,000.00 338,500.00
10 Karet Kleyer Kopling set 77,000.00 84,500.00
11 Karet gantungan juen bh 56,000.00 61,500.00
12 Bureng rem muka set 105,000.00 115,500.00
13 Klaker roda belakang bh 210,000.00 231,000.00
14 Klaker roda muka bh 182,000.00 200,000.00
15 Olie sheel roda belakang bh 126,000.00 138,500.00
16 Olie sheel roda muka bh 98,000.00 107,500.00
17 Klaker Ring bh 107,800.00 118,500.00
18 Ring Per bh 8,400.00 9,000.00
19 Kres juen bh 231,000.00 254,000.00
20 Lampu Belakang bh 115,500.00 127,000.00
21 Lampu Depan bh 138,500.00 152,000.00
22 Olor hendel dump bh 210,000.00 231,000.00
23 Swit Rem bh 54,000.00 59,000.00
24 Accu 12 V N. 100 bh 994,000.00 1,093,000.00
25 Kipas kaca KK bh 56,000.00 61,500.00
26 Baut Roda Belakang bh 138,500.00 152,000.00
27 Selang Radiator set 53,500.00 58,500.00
28 Peleg Roda bh 385,000.00 423,500.00
29 Pier Babok bh 231,000.00 254,000.00
30 Bineng Rem Depan bh 231,000.00 254,000.00
31 Karet gantungan juen bh 77,000.00 84,500.00
32 Klaker gandul bh 210,000.00 231,000.00
33 Peleser renteng bh 70,000.00 77,000.00
34 Kapas kopling bh 630,000.00 693,000.00
35 Spion lengkap bh 84,000.00 92,000.00
36 Olie sheel gardan bh 112,000.00 123,000.00
37 Kres juen handel bh 112,000.00 123,000.00
38 Lampu kota KK bh 168,000.00 184,500.00
39 Kipas pendingin R bh 175,000.00 192,500.00
40 Skok beker muka bh 210,000.00 231,000.00
41 Skok beker belakang set 210,000.00 231,000.00
42 Karet pir belakang set 14,000.00 15,000.00
43 Karet duduk mesin set 84,000.00 92,000.00
44 Karet duduk balok bh 7,000.00 7,700.00
45 Olor spidometer bh 112,000.00 123,000.00
46 Jok set 632,000.00 695,000.00
47 Filter Olie Transimisi bh 462,000.00 508,000.00
48 Karet kipas kaca bh 53,500.00 58,500.00
49 Pompa Bos Pimp bh 115,000.00 126,500.00
50 Karet Pier bh 11,700.00 13,000.00
51 Karet Tahu - Tahunan bh 11,700.00 13,000.00
52 Olie Shell Hidrolis Dump bh 92,400.00 101,500.00
53 Olie Shell Presnelleng set 138,500.00 152,000.00
54 Aspen Depan bh 70,000.00 77,000.00
55 Boss Pen bh 56,000.00 61,500.00
56 Olor Hidrolis bh 385,000.00 423,500.00
57 Knalpot bh 385,000.00 423,500.00
58 Peleg Roda bh 385,000.00 423,500.00
59 Baut Roda Belakang bh 115,000.00 126,500.00
60 Baut Roda Depan bh 100,000.00 110,000.00
61 Lampu Muka 2 X bh 154,000.00 169,000.00
62 Lampu Belakang bh 385,000.00 423,500.00
63 Kres Juen bh 224,000.00 246,000.00
64 Kaca Spion bh 154,000.00 169,000.00
65 Kampas Hand Rem bh 231,000.00 254,000.00
66 Baut Planting bh 46,000.00 50,500.00
67 Gigi Satelit bh 268,500.00 295,300.00
68 Piston/ Seker bh 1,038,000.00 1,141,500.00
69 Pack Shell bh 192,500.00 211,700.00
70 Skok Depan /Engkel bh 192,500.00 211,700.00
71 Skok Belakang /Engkel set 192,500.00 211,700.00

Page 17
72 Matahari set 924,000.00 1,016,500.00
73 Reli Lampu bh 46,000.00 50,500.00
74 Sweet Rem bh 61,500.00 67,500.00
75 Beugel Pier bh 61,500.00 67,500.00
76 Beugel Bak bh 77,000.00 84,500.00
77 Swet Mesin bh 53,500.00 58,800.00
78 Swet Reting bh 53,500.00 58,800.00
79 Drunk Layer Kopling bh 246,000.00 270,500.00
80 Kleyer Kopling bh 92,400.00 101,500.00
81 Baut Roda L.R set 215,500.00 237,000.00
82 Sunduk Pier bh 24,500.00 27,000.00
E DUMP TRUCK ISUZU
1 Filter udara bh 84,000.00 92,000.00
2 Filter solar bh 56,000.00 61,500.00
3 Filter olie mesin bh 70,000.00 77,000.00
4 Kampas rem belakang set 210,000.00 231,000.00
5 Kampas rem depan set 210,000.00 231,000.00
6 Kampas kopling bh 490,000.00 539,000.00
7 Karet kleyer rem belakang bh 14,000.00 15,000.00
8 Karet kleyer rem muka bh 14,000.00 15,000.00
9 Kleyer Kopling bh 115,300.00 126,500.00
10 Kampas kopling bh 847,000.00 931,500.00
11 Klaker roda belakang bh 196,000.00 215,500.00
12 Klaker roda muka bh 175,000.00 192,500.00
13 Olie sheel roda belakang bh 84,000.00 92,000.00
14 Olie sheel roda muka bh 56,000.00 61,500.00
15 Olie sheel roda gardan bh 56,000.00 61,500.00
16 Olie sheel presneleng bh 42,000.00 46,000.00
17 Skok beker muka set 210,000.00 231,000.00
18 Skok beker belakang set 210,000.00 231,000.00
19 Kres juen bh 168,000.00 184,500.00
20 Karet gantungan bh 56,000.00 61,500.00
21 Kaca spion komplit bh 84,000.00 92,000.00
22 Motor penggerak kipas set 280,000.00 308,000.00
23 Kipas kaca KK set 56,000.00 61,500.00
24 Timeng besi bh 616,000.00 677,500.00
25 Water pom bh 420,000.00 462,000.00
26 Lampu muka 2x bh 98,000.00 107,500.00
27 Lampu belakang bh 70,000.00 77,000.00
28 Terot LR set 280,000.00 308,000.00
29 Paleg roda bh 490,000.00 539,000.00
30 Baut roda belakang bh 56,000.00 61,500.00
31 Baut roda muka bh 35,000.00 38,500.00
32 Karet Pir bh 7,000.00 7,700.00
33 Karet tahu-tahunan bh 4,200.00 4,500.00
34 Begel Bak set 28,000.00 30,500.00
35 Begel Pir bh 35,000.00 38,500.00
36 Sindik pir bh 21,000.00 23,000.00
37 Matahari bh 700,000.00 770,000.00
38 Pir belakang no. 1 bh 280,000.00 308,000.00
39 Karet duduk mesin bh 98,000.00 107,500.00
40 Aspen bh 35,000.00 38,500.00
41 Bos asper bh 35,000.00 38,500.00
42 Olie sheel mesin bh 168,000.00 184,500.00
43 Karet duduk balok bh 7,000.00 7,700.00
44 Olie Sheel Handel Improl bh 77,000.00 84,500.00
45 Selang Hidrolis 2 m bh 654,500.00 720,000.00
46 Olor Hidrolis bh 92,400.00 101,500.00
47 Baut Pluting bh 46,200.00 50,500.00
48 Pleyer Renteng bh 54,000.00 59,000.00
49 Klaker roda belakang bh 385,000.00 423,500.00
50 Klaker Roda Depan bh 346,000.00 380,500.00
51 Sweet Rem bh 61,500.00 67,500.00
52 Walter Pump bh 577,500.00 635,000.00

Page 18
53 Swet Stater bh 269,000.00 295,500.00
54 Selang Radiator bh 44,500.00 48,500.00
55 Pum Bos Pom bh 115,000.00 126,500.00
56 Knalpot bh 385,000.00 423,500.00
57 Filter Transmisi Hidrolis bh 462,000.00 508,000.00
58 Olie Shell Handel Presnelleng bh 138,500.00 152,000.00
59 Blower Resin bh 924,000.00 1,016,000.00

XIX SUKU CADANG


A SUKU CADANG MGB1 - MGT2
1 RODA BELAKANG
1 Cyl Roller Bearing NUP 2313 ( 122.01.0000.27 ) bh 6,350,000.00 6,667,500.00
2 Cyl Roller Bearing NU 2313 ( 122.01.0000.28 ) bh 2,600,000.00 2,730,000.00
3 Cyl Roller Bearing N 216 ( 122.01.0000.29 ) bh 1,500,000.00 1,575,000.00
4 Cyl Roller Bearing NUP 2216 ( 122.01.0000.30 ) bh 3,250,000.00 3,412,500.00
5 Rubber Buffer ( 122.01.0000.47 ) bh 450,000.00 472,500.00
6 Ring Gear ( 122.01.0000.08 ) bh 12,500,000.00 13,125,000.00
2 KERANGKA
1 Tempat Duduk (122.00.0000.25) bh 450,000.00 472,500.00
3 MEKANIS PENGGERAK
1 V Belt (122.03.0000.15) bh 225,000.00 236,200.00
2 Rubber Buffer ( 122.03.0100.26 ) bh 525,000.00 551,200.00
3 Roda Rantai Z 17 (122.03.0100.07) bh 1,750,000.00 1,837,500.00
4 Needle Bearing NA 6910 ( 122.03.0100.18 ) bh 850,000.00 892,500.00
5 Cyl Roller Bearing NUP2208 ( 122.03.0100.19 ) bh 1,100,000.00 1,155,000.00
6 Poros Pinion (122.03.0100.04) bh 2,600,000.00 2,730,000.00
7 Roda Rantai (122.03.0100.05) bh 2,500,000.00 2,625,000.00
8 Cyl Roller Bearing NUP 2211 ( 122.03.0100.20 ) bh 1,500,000.00 1,575,000.00
9 Cyl Roller Bearing NUP 1016 ( 122.03.0100.21 ) bh 2,100,000.00 2,205,000.00
10 Pasak (122.03.0100.27) bh 125,000.00 131,200.00
4 MOTOR PENGGERAK ( FIL 511 )
1 Metal Jalan Std ( 5/0141-06 ) psg 1,000,000.00 1,050,000.00
2 Metal Duduk Std ( 83/0141-01 ) psg 1,239,700.00 1,310,700.00
3 Ring Piston Std ( 4/0141-07 ) set 900,000.00 945,000.00
4 Packing Set ( FIL 511 ) set 1,750,000.00 1,837,500.00
5 Piston Assy Std ( 1/0141-07 ) set 2,750,000.00 2,887,500.00
6 Fuel Filter ( 4/0141-20 ) bh 275,800.00 289,600.00
7 Oil Filter ( 4/0141-15 ) bh 300,000.00 315,000.00
8 Nozzle ( 4/0141-19 ) bh 875,000.00 918,700.00
9 Cylinder Liner ( 1/0141-04 ) bh 2,200,000.00 2,310,000.00
10 Valve Inlet ( 28/0141-08 ) bh 500,000.00 525,000.00
11 Valve Outlet ( 26/0141-08 ) bh 500,000.00 525,000.00
5 MEKANISME PENGGERAK GETARAN
1 ( Hanya untuk MGB1 )
2 Ball Bearing 6307 ( 122.05.0000.18 ) bh 124,800.00 131,100.00
3 Ball Bearing 6006 ( 122.05.0000.19 ) bh 90,000.00 94,500.00
4 V Belt (122.05.0000.30) bh 225,000.00 236,200.00
5 V Belt (122.05.0000.31) bh 200,000.00 210,000.00
6 MEKANISME KEMUDI
1 a. Roda Cacing ( 122.06.0700.09 ) bh 1,500,000.00 1,575,000.00
2 b. Roda Cacing ( 122.06.0700.10 ) bh 2,250,000.00 2,362,500.00
3 c. Ball Bearing 6210 ( 122.06.0700.16 ) bh 145,000.00 152,200.00
4 d. Taper Roller Bearing 32207 ( 122.06.0700.17 ) bh 145,000.00 152,200.00
7 PENEGANG SABUK
1 Ball Bearing 6006 ( 122.07.0000.06 ) bh 75,000.00 78,700.00
8 GARPU RODA MUKA
1 Selubung bh 275,000.00 288,700.00
2 Tapered Roller Bearing 32212 ( 122.12.0000.18 ) bh 425,000.00 446,200.00
3 Tapered Roller Bearing 32214 ( 122.12.0000.19 ) bh 450,000.00 472,500.00
9 RODA MUKA
1 Pena Pasak (122.13.3000.00) bh 225,000.00 236,200.00
2 Poros Roda Muka (122.13.3000.05) bh 2,750,000.00 2,887,500.00
3 Balok antara (122.134.3000.11) bh 225,000.00 236,200.00
4 Cyl Roller Bearing NU 1012 ( 122.13.0000.25 ) bh 2,250,000.00 2,362,500.00

Page 19
5 Cyl Roller Bearing NUP 209 ( 122.13.0000.26 ) bh 850,000.00 892,500.00
10 REDUKTOR
1 Oil Seal ( 40x62x12 ) bh 60,000.00 63,000.00
2 Oil Seal ( 40x55x10 ) bh 60,000.00 63,000.00
3 Oil Seal ( 46x62x12 ) bh 69,000.00 72,400.00
4 Ball Bearing 6306 N bh 105,000.00 110,200.00
5 Ball Bearing 6306 bh 95,000.00 99,700.00
6 Needle Bearing K32/27 bh 81,000.00 85,000.00
7 Needle Bearing K32/17 bh 65,000.00 68,200.00
8 Cyl Roller Bearing NJ 307 bh 425,000.00 446,200.00
9 Ball Bearing 6206 bh 75,000.00 78,700.00
10 Ball Bearing 6206 N bh 85,000.00 89,200.00
11 Ball Bearing 6308 bh 200,000.00 210,000.00
12 Needle Bearing B230 bh 260,000.00 273,000.00
13 Saringan Udara bh 120,000.00 126,000.00
14 Roda Gigi ( 177.16.02.A ) bh 750,000.00 787,500.00
15 Penggeser ( 157.57 ) bh 101,200.00 106,300.00
16 Penggeser ( 157.45 ) bh 101,200.00 106,300.00
17 Cincin Antara ( 177.51.1.A ) bh 101,200.00 106,300.00
18 Cincing Antara ( 177.51.A ) bh 101,200.00 106,300.00
19 Poros RG Pembalik ( 177.22.A ) bh 750,000.00 787,500.00
20 Oil Dipstick ( 177.40.A ) bh 90,000.00 94,500.00
21 Kabel rem bh 115,000.00 120,700.00
22 Pasak ( 03.177.37.01 ) bh 85,000.00 89,200.00

B SUKU CADANG MG6 - MV6P


1 KELOMPOK GEAR BOX
1 Mur ( 012.102.D.0000.27/06.00.106 ) bh 83,000.00 87,100.00
2 Cincin Pengunci ( 012.102.D.0000.28/06.00.107 ) bh 47,500.00 49,800.00
3 Pasak ( 012.102.D.0000.29/06.00.110 ) bh 84,000.00 88,200.00
4 Baut Spesial ( 012.102.D.0000.47/06.00.135 ) bh 46,000.00 48,300.00
5 Mur Mahkota ( 012.102.D.0000.48/06.00.136 ) bh 18,500.00 19,400.00
6 Cincin Antara ( 012.102.D.0000.61/06.00.154 ) bh 52,800.00 55,400.00
7 Dudukan Pegas ( 012.103.D.0000.28/06.00.59 ) bh 18,500.00 19,400.00
8 Skrup Penyetel ( 012.103.D.0000.26/06.00.57 ) bh 40,500.00 42,500.00
9 Baut Penutup ( 012.103.D.0000.25/06.00.56 ) bh 40,500.00 42,500.00
10 Pelat Penahan ( 012.103.D.0000.13/06.00.30 ) bh 101,500.00 106,500.00
11 Baut Garpu ( 012.103.D.0000.11/06.00.27 ) bh 37,000.00 38,800.00
12 Baut Garpu ( 012.103.D.0000.12/06.00.29 ) bh 37,000.00 38,800.00
13 Cincin Antara ( 012.102.D.000067/06.00.163 ) bh 162,000.00 170,100.00
14 Mur Pengunci ( 012.102.D.0000.19/06.00.87 ) bh 172,100.00 180,700.00
15 Mur ( 012.102.D.0000.41/06.00.129 ) bh 142,000.00 149,100.00
16 Bola Sendi ( 012.103.D.0000.19/06.00.46 ) bh 142,700.00 149,800.00
17 Support ( 012.103.D.0000.01/06.00.12 ) bh 580,000.00 609,000.00
18 Support ( 012.103.D.0000.14/06.00.20 ) bh 810,000.00 850,500.00
19 Poros penghubung RG ( 012.102.D.25/06.00.94 bh 3,175,000.00 3,333,700.00
20 Bearing ( 22215 C ) bh 1,104,000.00 1,159,200.00
21 Bearing ( 21306 C ) bh 754,500.00 792,200.00
22 Bearing ( 21307 C ) bh 773,000.00 811,600.00
23 Bearing ( 30215 ) bh 405,000.00 425,200.00
24 Bearing ( 32210 ) bh 202,500.00 212,600.00
25 Bearing ( 30213 ) bh 350,000.00 367,500.00
26 Bearing ( 6210 ) bh 138,000.00 144,900.00
27 Needle Bearing ( Dia 3,5 x 30 ) bh 17,500.00 18,300.00
28 Oil Seal ( 50x65x10 ) bh 52,000.00 54,600.00
29 Oil Seal ( 50x65x10 ) bh 52,000.00 54,600.00
30 Snap Ring Outer ( 50x2 ) bh 25,500.00 26,700.00
31 Snap Ring Outer ( 75 x 2,5 ) bh 30,500.00 32,000.00
32 Snap Ring ( 42x1.75 ) bh 24,100.00 25,300.00
33 Pegas Tekan ( 012.103.D.0000.27/06.00.58 ) bh 77,200.00 81,100.00
34 Pegas tekan konus ( 012.103.D.0000.23/06.00.50 ) bh 126,500.00 132,800.00
35 Ball ( Dia 16 ) bh 10,000.00 10,500.00
36 Ball ( Dia 12 ) bh 10,000.00 10,500.00
2 KELOMPOK RODA BELAKANG

Page 20
1 Pena ( 010.010.3.0000.21/09.00.32 ) bh 52,000.00 54,600.00
2 Bus Roda Belakang ( 012.010.D.0000.18/13.00.18 ) bh 414,000.00 434,700.00
3 Cincin Penahan ( 012.010.D.0000.11/13.00.11 ) bh 129,000.00 135,400.00
4 Pelat Penahan ( 012.010.D.0000.09/13.00.09 ) bh 252,000.00 264,600.00
5 Ring Gear ( 012.010.C.0000.04/09.40.00 ) bh 15,525,000.00 16,301,200.00
6 Poros Roda Belakang ( 012.010.D.0000.12/13.00.12.A ) bh 8,625,000.00 9,056,200.00
3 KELOMPOK RODA MUKA
1 Cincin Penahan ( 012.050.D.0000.07/01.13.10 ) bh 133,000.00 139,600.00
4 KELOMPOK KEMUDI
1 Poros Cacing ( 012.060.D.0000.09/30.00.19 ) bh 2,587,500.00 2,716,800.00
2 Gigi Tembereng ( 012.061.D.0000.08/30.00.13 ) bh 1,437,500.00 1,509,300.00
3 Pasak ( 012.060.D.0000.26/02.00.23 ) bh 92,000.00 96,600.00
4 Lengan garpu ( 012.071.D.0000.01/30.00.09 ) bh 86,500.00 90,800.00
5 Sambungan ( 012.071.D.0000.02/30.00.10 ) bh 176,000.00 184,800.00
6 Bus ( 012.071.D.0000.03/30.00.23 ) bh 129,000.00 135,400.00
7 Bus ( 012.071.D.0000.08/30.00.30 ) bh 1,585,000.00 1,664,300.00
8 Pasak ( 012.071.D.0000.39/30.00.31 ) bh 84,000.00 88,200.00
9 Pasak ( 012.071.D.0000.12/30.00.47 ) bh 84,000.00 88,200.00
10 Bearing ( 32207 DIN 720 ) bh 184,000.00 193,200.00
5 KELOMPOK ENGINE IMR 033 / 1
1 Fuel filter elemen ( 034.07.550 ) bh 196,100.00 205,900.00
2 Oil filter elemen ( 034.05.940 0 ) bh 260,000.00 273,000.00
3 Diapragma/membran bh 193,500.00 203,100.00
4 Nozzle ( W 5502 ) bh 412,000.00 432,600.00
5 Disc coupling ( 1247 ) bh 208,000.00 218,400.00
6 Plunger ( W 5136 ) bh 342,000.00 359,100.00
7 Ring piston std ( 034.02.330 ) bh 580,000.00 609,000.00
8 Piston+pin+circlip std ( 034.02.200 ) bh 995,000.00 1,044,700.00
9 Metal jalan std ( 034.02.103 ) bh 898,500.00 943,400.00
10 Metal duduk std ( 034.01.280 ) bh 2,500,000.00 2,625,000.00
11 Crank shaft ( 033.02.103 ) bh 12,100,000.00 12,705,000.00
12 Gasket cyl head ( 033.03.044 ) bh 276,000.00 289,800.00
13 Gasket set ( 033/1 ) bh 2,400,000.00 2,520,000.00
14 Valve inlet ( 034.03.013 ) bh 294,000.00 308,700.00
15 Valve outlet ( 034.03.014 ) bh 294,000.00 308,700.00
16 Hose bengkok ( 036.06.042 ) bh 126,000.00 132,300.00
17 Seal crank shaft ( 034.01.164 ) bh 83,500.00 87,600.00
18 Seal front cover ( G2.51x70x10 ) bh 171,500.00 180,100.00
19 Liner std ( 034.01.002 ) bh 698,500.00 733,400.00
20 Timing chain ( 034.04.044 ) set 795,000.00 834,700.00
21 Water pump ( 034.06.600 ) set 2,340,500.00 2,457,500.00
22 Shaft rocker assy ( 033.03.020 ) set 4,500,000.00 4,725,000.00
23 Valve spring inner ( 034.03.016 ) bh 91,100.00 95,600.00
24 Valve spring outer ( 034.03.017 ) bh 131,600.00 138,200.00

XX MATERIAL JARINGAN DISTRIBUSI LISTRIK


1 Accessories Conductor Adjustable Dead End Assembly TC 3x70 + 50 mm2 set 128,500.00 128,500.00
2 Accessories Conductor Bundle Protection Assembly TC 3x70 + 50 mm2 set 80,500.00 80,500.00
3 Accessories Conductor Fixed Dead End Assembly TC 3x70 + 50 mm2 set 102,500.00 102,500.00
4 Accessories Conductor Large Angel Assembly TC 3x70 + 50 mm2 set 110,500.00 110,500.00
5 Accessories Conductor Small Angle Assembly TC 3x70 + 50 mm2 set 105,500.00 105,500.00
6 Accessories Conductor Suspension Assembly TC 3x70 + 50 mm2 set 79,500.00 79,500.00
7 Alumuniun Binding Ware 3 mm m' 6,000.00 6,000.00
8 Alumuniun Tape - m' 9,500.00 9,500.00
9 Arm Tie Type 750-3/4" bh 50,000.00 50,000.00
10 Arm Tie Type 900-3/4" bh 103,500.00 103,500.00
11 Ball Clevis - unit 72,500.00 72,500.00
12 BC Drat 50 mm2 unit 75,500.00 75,500.00
13 Beton Blok 40x40x10 bh 99,000.00 99,000.00
14 Bolt & Nut M 16x50 mm bh 10,500.00 10,500.00
15 Bolt & Nut M.16 x 70 mm bh 11,500.00 11,500.00
16 Bolt & Nut M 16x350 mm bh 39,000.00 39,000.00
17 Bolt & Nut M 16x400 mm bh 44,000.00 44,000.00
18 Compression Joint AAAC,ACSR 50 sqmm unit 62,000.00 62,000.00

Page 21
19 Compression Joint AAAC,ACSR 70 sqmm unit 85,000.00 85,000.00
20 Compression Joint AAAC,ACSR 95 sqmm unit 115,000.00 115,000.00
21 Compression Joint AAAC,ACSR 150 sqmm unit 135,000.00 135,000.00
22 Conductor TC 3x70 + 50 mm2 m' 49,500.00 49,500.00
23 Conductor AAAC 70 mm m' 13,000.00 13,000.00
24 Conductor AAAC 150 mm m' 27,000.00 27,000.00
25 Conductor AAACS 150 mm m' 35,500.00 35,500.00
26 Conductor AAAC OC 150 mm m' 44,000.00 44,000.00
27 Cross Arm Clevis - set 45,500.00 45,500.00
28 Cross Arm UNP 100x40x4-2000mm bh 355,000.00 355,000.00
29 Cross Arm UNP 100x50x4-3000mm bh 450,000.00 450,000.00
30 Cross Arm UNP 100x50x5-2000mm bh 395,000.00 395,000.00
31 Cross Arm UNP 100x50x5-2500mm bh 455,000.00 455,000.00
32 Cross Arm UNP 100x50x5-3000mm bh 460,000.00 460,000.00
33 Double Arm Band 6" set 125,000.00 125,000.00
34 Double Arm Band 8" set 150,000.00 150,000.00
35 Fuse Cut Out Keramik 20 kV - 10 kA bh 1,300,000.00 1,300,000.00
36 Fuse Cut Out Polymer 20 kV - 10 kA bh 1,485,000.00 1,485,000.00
37 Galv. Steel Stranded Wire 35mm m' 14,000.00 14,000.00
38 Galv. Steel Stranded Wire 70mm m' 22,000.00 22,000.00
39 Ground Rod 1/2" x 1500 mm bh 126,000.00 126,000.00
40 Ground Rod 1/2" x 2500 mm bh 185,000.00 185,000.00
41 Ground Rod 5/8" x 1500 mm bh 149,500.00 149,500.00
42 Ground Rod 5/8" x 2500 mm bh 237,500.00 237,500.00
43 Ground Rod 5/8" x 3000 mm bh 285,000.00 285,000.00
44 Ground Rod 5/8" x 6000 mm bh 570,000.00 570,000.00
45 Ground Rod 3/4" x 2500 mm bh 315,000.00 315,000.00
46 Guy Wire Rod 5/8" (15mm) x 1800 mm bh 110,000.00 110,000.00
47 Guy Wire Rod 5/8" 5/8" (15mm) x 2500 mm bh 170,000.00 170,000.00
48 Guy Wire Timble TR/TM- bh 6,000.00 6,000.00
49 Insolator Tarik 20 kV unit 395,000.00 395,000.00
50 Insolator Tumpu Line post insulator 20 kV unit 295,000.00 295,000.00
51 Insolator Tumpu Pin post insulator 20 kV unit 285,500.00 285,500.00
52 Joint Connector Bimetal Al/Cu 50-50 mm2 bh 79,500.00 79,500.00
53 Joint Connector Bimetal Al/Cu 50-70 mm2 bh 85,500.00 85,500.00
54 Joint Connector Bimetal Al/Cu 70-70 mm2 bh 87,500.00 87,500.00
55 Joint Connector Bimetal Al/Cu 70-150 mm2 bh 95,000.00 95,000.00
56 Joint Sleeve Non Tension Al 50-50 mm2 bh 26,500.00 26,500.00
57 Joint Sleeve Non Tension Al 70-70 mm2 bh 33,000.00 33,000.00
58 Joint Sleeve Non Tension Al 150-150 mm2 bh 71,000.00 71,000.00
59 Joint Sleeve Non Tension Cu 50-50 mm2 bh 60,000.00 60,000.00
60 Joint Sleeve Non Tension Cu 70-70 mm2 bh 67,000.00 67,000.00
61 Joint Sleeve Non Tension Cu 150-150 mm2 bh 139,000.00 139,000.00
62 Joint Sleeve Tension Al 70 mm2 bh 85,000.00 85,000.00
63 Joint Sleeve Tension Al 150 mm2 bh 145,000.00 145,000.00
64 Ligthing Arrester Keramik 20 kV - 10 kA bh 1,261,000.00 1,261,000.00
65 Ligthing Arrester Polymer 20 kV - 10 kA bh 1,449,000.00 1,449,000.00
66 Line Tap Connector Al 150 mm type G bh 61,000.00 61,000.00
67 Link 25 x 25 bh 4,500.00 4,500.00
68 LV. Panel 2 Group (9 Houlder) - unit 15,470,000.00 15,470,000.00
69 NYA 35 sqmm - m' 49,000.00 49,000.00
70 Pararel Groove Clamp AL/AL 25-70 mm2 unit 26,000.00 26,000.00
71 Pararel Groove Clamp AL/AL 70-150 mm2 unit 51,000.00 51,000.00
72 Pararel Groove Clamp AL/AL 150-240 mm2 unit 63,000.00 63,000.00
73 Pipa Air 2" - 6000 mm (t; 2,35mm) bh 60,000.00 60,000.00
74 Pipa Air 3" - 6000 mm (t; 2,5mm) bh 91,000.00 91,000.00
75 Pipa pelindung 3/4"-2000 mm (t;1,4mm) bh 62,000.00 62,000.00
76 Preformed Grip 70mm bh 58,000.00 58,000.00
77 Sepatu Kabel/Cable Lug. Al 50 mm2 (mata baut 1) bh 25,000.00 25,000.00
78 Sepatu Kabel/Cable Lug. Al 50 mm2 (mata baut 2) bh 49,000.00 49,000.00
79 Sepatu Kabel/Cable Lug. Al 70 mm2 (mata baut 1) bh 27,500.00 27,500.00
80 Sepatu Kabel/Cable Lug. Al 70 mm2 (mata baut 2) bh 51,000.00 51,000.00
81 Sepatu Kabel/Cable Lug. Al 150 mm2 (mata baut 1) bh 65,000.00 65,000.00
82 Sepatu Kabel/Cable Lug. Al 150 mm2 (mata baut 2) bh 86,000.00 86,000.00

Page 22
83 Sepatu Kabel/Cable Lug. Al/Cu 50 mm2 (mata baut 1) bh 75,000.00 75,000.00
84 Sepatu Kabel/Cable Lug. Al/Cu 50 mm2 (mata baut 2) bh 95,000.00 95,000.00
85 Sepatu Kabel/Cable Lug. Al/Cu 70 mm2 (mata baut 1) bh 77,500.00 77,500.00
86 Sepatu Kabel/Cable Lug. Al/Cu 70 mm2 (mata baut 2) bh 117,500.00 117,500.00
87 Sepatu Kabel/Cable Lug. Al/Cu 150 mm2 (mata baut 1) bh 128,500.00 128,500.00
88 Sepatu Kabel/Cable Lug. Al/Cu 150 mm2 (mata baut 2) bh 237,500.00 237,500.00
89 Sepatu Kabel/Cable Lug. Cu 50 mm2 (mata baut 1) bh 55,000.00 55,000.00
90 Sepatu Kabel/Cable Lug. Cu 50 mm2 (mata baut 2) bh 121,500.00 121,500.00
91 Sepatu Kabel/Cable Lug. Cu 70 mm2 (mata baut 1) bh 65,000.00 65,000.00
92 Sepatu Kabel/Cable Lug. Cu 70 mm2 (mata baut 2) bh 175,500.00 175,500.00
93 Sepatu Kabel/Cable Lug. Cu 150 mm2 (mata baut 1) bh 125,000.00 125,000.00
94 Sepatu Kabel/Cable Lug. Cu 150 mm2 (mata baut 2) bh 295,000.00 295,000.00
95 SLO GTT 50 s/d 2000 kVA kVA 40,000.00 40,000.00
96 SLO SUTM 0 s/d 7.5 KMS m' 14,000.00 14,000.00
97 SLO SUTR 0 s/d 7.5 KMS m' 13,000.00 13,000.00
98 Square washer - bh 4,000.00 4,000.00
99 Stainless Steel Strip 0,7 x 20 mm/mtr 25 - 70 mm2 unit 18,500.00 18,500.00
100 Stoping Buckle - unit 4,500.00 4,500.00
101 Strain Clamp AAAC, ACSR 25-70 sqmm unit 55,000.00 55,000.00
102 Strain Clamp AAAC, ACSR 70-150 sqmm unit 65,000.00 65,000.00
103 Strain Clamp AAAC, ACSR 70-240 sqmm unit 86,000.00 86,000.00
104 Strain Clamp AAAC, ACSR 150-240 sqmm unit 132,000.00 132,000.00
105 Strain Rod Insulator - bh 336,000.00 336,000.00
106 Strut Arm TM (t; 4 mm) bh 72,000.00 72,000.00
107 Strut Arm TR (t; 4 mm) bh 56,000.00 56,000.00
108 Strut Tie 2000-pipe 2" bh 189,000.00 189,000.00
109 Tiang Beton 7m - 100 daN unit 1,741,500.00 1,741,500.00
110 Tiang Beton 7m - 100 daN + E unit 1,820,000.00 1,820,000.00
111 Tiang Beton 9m - 100 daN unit 2,195,000.00 2,195,000.00
112 Tiang Beton 9m - 100 daN + E unit 2,295,000.00 2,295,000.00
113 Tiang Beton 9m - 200 daN unit 2,418,000.00 2,418,000.00
114 Tiang Beton 9m - 200 daN + E unit 2,580,500.00 2,580,500.00
115 Tiang Beton 11m - 200 daN unit 3,718,000.00 3,718,000.00
116 Tiang Beton 11m - 200 daN + E unit 3,868,500.00 3,868,500.00
117 Tiang Beton 11m - 350 daN unit 4,320,500.00 4,320,500.00
118 Tiang Beton 11m - 350 daN + E unit 4,526,000.00 4,526,000.00
119 Tiang Beton 12m - 200 daN unit 4,138,500.00 4,138,500.00
120 Tiang Beton 12m - 200 daN + E unit 4,328,500.00 4,328,500.00
121 Tiang Beton 12m - 350 daN unit 4,451,000.00 4,451,000.00
122 Tiang Beton 12m - 350 daN + E unit 5,160,500.00 5,160,500.00
123 Tiang Beton 13m - 350 daN unit 5,521,000.00 5,521,000.00
124 Tiang Beton 13m - 350 daN + E unit 5,775,500.00 5,775,500.00
125 Tiang Beton 14m - 350 daN unit 6,725,500.00 6,725,500.00
126 Tiang Beton 14m - 350 daN + E unit 6,890,500.00 6,890,500.00
127 Trafo Distribusi 20 kV 3 PH 100 kVA bh 65,410,000.00 65,410,000.00
128 Trafo Distribusi 20 kV 3 PH 160 kVA bh 84,754,000.00 84,754,000.00
129 Turn Buckle TM 3/4" bh 105,000.00 105,000.00
130 Turn Buckle TR (5/8") bh 82,000.00 82,000.00
131 U Bolt & Steel Plat - set 74,000.00 74,000.00
132 Verlenk Stuck Pipa 3" - 3 mt - Medium set 410,000.00 410,000.00
133 Verlenk Stuck Pipa 4" - 3 mt - Medium set 495,000.00 495,000.00
134 Wire Clip TR/TM- bh 6,000.00 6,000.00

XXI BAHAN PERALATAN LISTRIK JALAN


A MERCURY HPLN (PAKAI BALAST BHL)
1 HPLN 50 W Philips - E 27 bh 37,000.00 40,000.00
2 HPLN 125 W Philips - E 27 bh 53,000.00 58,000.00
3 HPLN 250 W Philips - E 40 bh 67,000.00 73,000.00
4 HPLN 400 W Philips - E 40 bh 126,000.00 138,000.00
5 HQL 125 W Osram - E 27 bh 74,000.00 81,000.00
6 HQL 250 W Osram - E 40 bh 79,000.00 87,000.00
B MERCURY ML (TIDAK PAKAI BALAST)
1 ML 100 W Philips - E 27 bh 44,000.00 49,000.00
2 ML 160 W Philips - E 27 bh 47,000.00 52,000.00

Page 23
3 ML 250 W Philips - E 40 bh 75,000.00 82,000.00
4 ML 500 W Philips - E 40 bh 126,000.00 139,000.00
C SON NATRIUM
1 SON H 220 W Philips - E 40 (BHL 250 W) bh 235,000.00 260,000.00
2 SON H 350 W Philips - E 40 (BHL 400 W) bh 375,000.00 400,000.00
3 SON T 100 W Philips - E 27 (BSN 100 W) bh 205,000.00 225,000.00
4 SON T 250 W Philips - E 40 (BSN 250 W) bh 210,000.00 230,000.00
5 SON T 400 W Philips - E 40 (BSN 400 W) bh 215,000.00 235,000.00
6 SON T 150 W Philips bh 200,000.00 215,000.00
7 SON 150 W Philips - E 40 (BSN 150 W) bh 166,900.00 183,600.00
8 SON 250 W Philips - E 40 (BSN 250 W) bh 189,000.00 207,900.00
9 SON 400 W Philips - E 40 (BSN 400 W) bh 200,000.00 219,900.00
D LAMPU TL
1 TL 10 W Philips bh 11,000.00 12,000.00
2 TL 18 W Philips bh 13,000.00 14,000.00
2 TL 36 W Philips bh 16,000.00 18,000.00
3 Lampu TL 40 W Philips bh 19,000.00 23,000.00
E ESSENTIAL
1 Essential 8 W Philips bh 34,000.00 37,000.00
2 Essential 14 W Philips bh 37,000.00 40,000.00
3 Essential 18 W Philips bh 40,000.00 44,000.00
4 Essential 23 W Philips bh 44,000.00 49,000.00
5 Essential 23 W Philips (Kuning) bh 43,000.00 47,000.00
6 Essential 50 W Philips bh 120,000.00 135,000.00
7 DOP Candle Frosted 25 W - E 14 bh 6,000.00 6,500.00
8 DOP Philips 200 W bh 48,000.00 53,000.00
9 DOP 5 W (Pijar) bh 4,500.00 4,700.00
F LAMPU SOROT
1 PAR 38 Colour 80 W Philips bh 56,000.00 61,500.00
2 PAR 38 Clear 80 W Philips bh 44,000.00 48,000.00
3 PAR 38 Clear 120 W Philips bh 44,000.00 48,000.00
4 HPIT Plus 250 W bh 130,000.00 140,000.00
5 HPIT Plus 400 W Philips (BHL 400 W) bh 343,000.00 377,000.00
6 HPIT Plus 1000 W Philips (BHL 1000 W) bh 1,100,000.00 1,200,000.00
7 Halogen 300 W Philips (France) bh 44,000.00 48,000.00
8 Halogen 1000 W Philips (France) bh 73,000.00 80,000.00
9 Halogen 200 W Philips (Cina) bh 36,000.00 39,000.00
10 Halogen 300 W Philips (Cina) bh 37,000.00 40,000.00
11 Halogen 500 W Philips (Cina) bh 45,000.00 50,000.00
12 Halogen 1000 W Philips (Cina) bh 66,000.00 72,000.00
G LAMPU HIAS DAN ASCESSORIES
1 Lampu Selang Shinyoku (2 Line) - 100 M rol 4,500,000.00 5,000,000.00
2 Lampu Selang Shinyoku (3 Line) - 100 M rol 5,500,000.00 6,000,000.00
3 Jack Lampu Selang (3 Line) Putih bh 25,000.00 30,000.00
4 Jack Lampu Selang (3 Line) Hitam bh 35,000.00 40,000.00
5 Sambungan Sock (3 Line) bh 20,000.00 25,000.00
6 Penutup lampu Selang bh 2,000.00 2,500.00
7 Klem Mundek No. 12 dos 16,000.00 17,000.00
8 Automatic Circuit Lampu Selang KW 1 (kontroller) bh 277,000.00 306,000.00
9 Automatic Circuit Lampu Selang KW 2 bh 204,000.00 225,000.00
10 Lampu Christmast (Isi 100) dos 66,000.00 72,000.00
H BALAST
1 Balast TL 10 W Philips bh 27,000.00 29,000.00
2 Balast TL 18 W Philips bh 30,000.00 33,000.00
3 Balast TL 36 W bh 35,000.00 40,000.00
4 Balast BHL Philips 50 W bh 126,000.00 139,000.00
5 Balast BHL Philips 125 W bh 110,000.00 125,000.00
6 Balast BHL Philips 250 W bh 205,000.00 215,000.00
7 Balast BHL Philips 400 W bh 236,000.00 260,000.00
8 Balast BSN Philips 150 W bh 175,000.00 200,000.00
9 Balast BSN Philips 250 W bh 225,000.00 250,000.00
10 Balast BSN 400 W Philips bh 250,000.00 275,000.00
11 Balast BSN 150 W Philips Black (Polandia) bh 397,400.00 436,800.00
I TIMER DAN FOTO CELL

Page 24
1 Timer Legrand 16 A Type 03753 bh 482,000.00 530,000.00
2 Timer National 16 A TB 388 bh 660,000.00 726,000.00
3 Timer The Ben Sul 181 H bh 512,000.00 563,000.00
4 Foto Cell Selcon 3 A (KW 1) bh 80,000.00 88,000.00
5 Foto Cell Selcon 6 A (KW 1) bh 91,000.00 100,000.00
6 Foto Cell Selcon 10 A (KW 1) bh 95,000.00 105,000.00
J MCB
1 Merlin Gerin 32 A (1 Pas) bh 41,000.00 45,000.00
2 Merlin Gerin 32 A (3 Pas) bh 321,000.00 353,000.00
3 Merlin Gerin 50 A (1 Pas) bh 255,000.00 280,000.00
4 Merlin Gerin 50 A (3 Pas) bh 542,000.00 596,000.00
5 MCB 40 A bh 68,000.00 75,000.00
6 MCB 6 A bh 41,000.00 45,000.00
K STATER, SEKRING, IGNITOR, CAPASITOR
1 Stater Philips FS 2 (10 - 20 W) bh 4,000.00 4,500.00
2 Stater Philips FS 4 (40 - 65 W) bh 4,500.00 5,000.00
3 Sekring otomat Likon 6 A bh 57,000.00 63,000.00
4 Sekring otomat Likon 10 A bh 57,000.00 63,000.00
5 Sekring otomat Likon 25 A bh 69,000.00 76,000.00
6 Ignitor SN 58 bh 77,000.00 85,000.00
7 Ignitor SN 51 bh 71,000.00 78,000.00
8 Capasitor UF 50 bh 87,000.00 95,000.00
9 Capasitor UF 25 bh 75,000.00 85,000.00
10 Trafo TL 40 W bh 35,000.00 38,000.00
L KABEL
1 Kabel NYM 2 X 2.5 mm Eterna (100 M) rol 689,000.00 758,000.00
2 Kabel NYM 2 X 1.5 mm Eterna (100 M) rol 480,000.00 530,000.00
3 Kabel NYY 2 X 2.5 mm Eterna (100 M) rol 911,000.00 1,000,000.00
4 Kabel NYY 2 X 1.5 mm Eterna (100 M) rol 676,000.00 744,000.00
5 Kabel NYY 2 X 1 1/2 mm m' 6,800.00 7,500.00
6 Kabel plastik m' 4,000.00 6,000.00
M KAP LAMPU
1 Kap Lampu SRP 822 Philips 250 W (Lengkap) unit 2,981,000.00 3,278,000.00
2 Kap Lampu TL WD 40 (Outdoor) Kosong bh 90,000.00 100,000.00
3 Kap Lampu SON-T bh 2,981,000.00 3,278,000.00
4 Kap Lampu PAR 38 - 80 W bh 61,000.00 67,000.00
5 Kap Lampu PAR 38 - 120 W bh 69,000.00 76,000.00
6 Kap Lampu Industri Denlite Dia 12" E 27 (Lengkap) bh 114,000.00 126,000.00
7 Kap Lampu Industri Denlite Dia 16" E 40 (Lengkap) bh 160,000.00 176,000.00
8 Kap Hijau E. 27 bh 54,000.00 59,000.00
9 Kap hijau E. 40 bh 69,000.00 76,000.00
10 Kap TL / WD 40 W bh 58,000.00 63,000.00
N FITTING, CONECTING, DLL
1 Fitting Besi E. 27 bh 20,000.00 22,000.00
2 Fitting Besi E. 40 bh 33,500.00 37,000.00
3 Fiting Dop Gantung bh 114,500.00 126,000.00
4 Fitting Gantung "Kyoku Denbi Osaka" E 40 bh 129,700.00 142,000.00
5 Fitting Halogen 500 w bh 15,500.00 17,000.00
6 Fitting tempel E 40 bh 23,500.00 26,000.00
7 Fitting plastik 5 W bh 2,500.00 2,700.00
8 Fitting TL 40 W bh 2,500.00 2,700.00
9 Conector KW 1 bh 9,200.00 10,000.00
10 Conector KW 2 bh 5,500.00 6,000.00
11 Service bh 6,500.00 9,000.00
12 Isolasi Unibel Kecil bh 8,000.00 9,000.00
13 Isolasi Scot Merk 3 M bh 88,000.00 97,000.00
O MATERIAL PJU
1 Tiang Beton 7/100 bh 1,325,000.00 1,890,000.00
2 Tiang Beton 9/200 bh 1,935,000.00 2,940,000.00
3 Bok O.A Kast Type VI bh 1,295,000.00 1,500,000.00
4 Begel O.A Kast & Besi Canal bh 341,000.00 382,000.00
5 Stenlis TM/TR (Yoke Breket) bh 123,000.00 136,500.00
6 Laskas 1 Group bh 171,000.00 191,000.00
7 Laskas 2 Group bh 239,000.00 267,000.00

Page 25
8 Begel Tiang bh 82,000.00 92,500.00
9 Begel Ornamen bh 41,000.00 46,000.00
10 Ornamen Lampu bh 614,000.00 696,000.00
11 Kawat Seling 8 mm bh 20,000.00 22,500.00
12 Paralon 1.1/2" bh 48,000.00 54,000.00
13 Bohton 1.1/2" bh 4,700.00 5,200.00
14 Kap Lampu Besar Kosong Philips/400 bh 3,617,000.00 4,026,000.00
15 Kap. Lampu HP Kosong /400 bh 887,000.00 1,023,000.00
16 Kap Lampu GS Kosong MR-320 T/400 bh 3,208,000.00 3,617,000.00
17 Kap Lampu DS Kosong GR-321 T/400 bh 1,706,000.00 1,911,000.00
18 Kap Halogen 500 VA bh 211,000.00 257,000.00
19 Kap Halogen 1000 VA Kosong Philips bh 512,000.00 580,000.00
20 Trafo HPIT 1000 w bh 1,732,000.00 2,278,000.00
21 Condensator bh 79,000.00 102,000.00
22 Kapasitor 32 mF bh 79,000.00 126,000.00
23 Box MCB bh 4,500.00 8,500.00
24 Baterai Jam Solar Cell bh 735,000.00 893,000.00
25 Box OA KAS Type 6 + Besi Canal bh 1,297,000.00 1,890,000.00
26 Tiang Lampu Besi 9 M bh 1,940,000.00 3,150,000.00
27 Box Plat Besi 15 X 20 CM bh 168,000.00 242,000.00
28 Stop Kontak Isi 3 bh 11,000.00 26,000.00
29 Magnet Kontaktor 100 A bh 985,000.00 1,470,000.00
30 Magnet Kontaktor 65 A bh 840,000.00 1,155,000.00
31 PC Solar Cloch S/S FC - 707 Jam Dinding Seico bh 9,290,000.00 12,080,000.00
32 PC Solar Cell SL - 10 bh 4,042,000.00 5,255,000.00
33 PC Clock Controller QR 601 bh 9,187,000.00 11,944,000.00
34 PC Box - QF bh 473,000.00 614,000.00
35 Service Jam Dinding Perempatan bh 866,000.00 1,126,000.00
36 Lampu Jalan SL RL 793 E-40 + SON-T 250 W Artolite unit 2,522,000.00 68,000.00
37 Lampu Jalan SL RL 793 E-40 + SON-T 400 W Artolite unit 2,847,000.00 3,278,000.00
38 Lampu Jalan SL RL 793 E-40 + HPIT 250 W Artolite unit 2,483,000.00 3,700,000.00
39 Lampu Jalan SL RL 793 E-40 + HPIT 400 W Artolite unit 2,575,000.00 3,227,000.00
40 Tiang lampu 8 m
a. Pipa Black Steel 5, 4, 3, 2 + Plat bh 5,250,000.00 6,300,000.00
b. Pipa Galvanis 5, 4, 3, 2 + Plat bh 6,825,000.00 10,500,000.00
41 Tiang Lampu 9 m
a. Pipa Black Steel 5, 4, 3, 2 + Plat bh 5,775,000.00 6,825,000.00
b. Pipa Galvanis 5, 4, 3, 2 + Plat bh 7,350,000.00 11,550,000.00
42 Steker bh 7,500.00 10,000.00
43 Hadle 3Phase 30 A bh 300,000.00 325,000.00
44 Plat grounding bh 25,000.00 35,000.00
45 Obeng bh 25,000.00 40,000.00
46 Tang kombinasi bh 45,000.00 65,000.00
47 Tang lancip bh 30,000.00 40,000.00
48 Tes pen bh 15,000.00 20,000.00
49 Avometer bh 75,000.00 110,000.00
50 Tang ampere bh 125,000.00 150,000.00

XXII TANAMAN
1 Glodok Tiang tinggi 1 m btg 15,000.00 17,000.00
2 Tanjung tinggi 1 m btg 7,000.00 8,000.00
3 Palem Putri tinggi 1 m btg 15,000.00 17,000.00
4 Sawo Kecik tinggi 1 m btg 40,000.00 45,000.00
5 Palem Regu tinggi 1 m btg 15,000.00 20,000.00
6 Iris btg 1,500.00 2,000.00
7 Air Paq btg 1,500.00 2,000.00
8 Kamboja Jepang btg 35,000.00 38,000.00
9 Asoka btg 3,000.00 3,500.00
10 Plastik Polibag btg 12,000.00 12,500.00
11 Trembesi tinggi 1 m btg 15,000.00 17,000.00
12 Palem Ekor Tupai btg 35,000.00 40,000.00
13 Teh-tehan btg 1,500.00 2,000.00
14 Aglonema btg 10,000.00 15,000.00

Page 26
15 Puring btg 7,000.00 10,000.00
16 Xansivera btg 10,000.00 12,000.00
17 Kruilia btg 2,000.00 3,000.00
18 Pucuk Merah tinggi 1/2 m btg 17,000.00 20,000.00
19 Tree Colour tinggi 1 m btg 10,000.00 15,000.00
20 Taiwan Beauty btg 1,500.00 2,500.00
21 Palem Merah tinggi 1 m btg 50,000.00 55,000.00
22 Cemara Udang btg 40,000.00 50,000.00
23 Walisanga btg 10,000.00 12,000.00
24 Adam Hawa btg 1,500.00 1,500.00
25 Glodok Biasa tinggi 1 m btg 10,000.00 12,000.00

XXIII BAHAN KIMIA


1 Racun Ulat ltr 90,000.00 100,000.00
2 Round Up ltr 60,000.00 65,000.00
3 Furadan kg 17,000.00 19,000.00
4 Pupuk Bokasi kg 1,900.00 3,200.00
5 Pupuk Kandang sak 10,000.00 12,000.00
6 Pupuk KCL kg 3,000.00 3,500.00
7 Pupuk NPK kg 2,500.00 2,750.00
8 Pupuk TSP kg 2,200.00 2,500.00
9 Pupuk Urea kg 2,000.00 2,100.00

DAFTAR UPAH PEKERJA

HARGA
NO TENAGA KERJA (HARI) SAT
Terendah Tertinggi
1 MANDOR org 88,000.00 92,000.00
2 KEPALA TK. GALI TANAH org 77,000.00 80,500.00
3 KEPALA TK. BATU org 77,000.00 80,500.00
4 KEPALA TK. KAYU org 77,000.00 80,500.00
5 KEPALA TK. BESI org 77,000.00 80,500.00
6 KEPALA TK. CAT org 77,000.00 80,500.00
7 KEPALA TK. LISTRIK org 77,000.00 80,500.00

Page 27
8 KEPALA TK. PIPA org 77,000.00 80,500.00
9 TUKANG GALI TANAH org 71,500.00 74,700.00
10 TUKANG BATU org 71,500.00 74,700.00
11 TUKANG KAYU org 71,500.00 74,700.00
12 TUKANG BESI org 71,500.00 74,700.00
13 TUKANG CAT org 71,500.00 74,700.00
14 TUKANG PLITUR org 71,500.00 74,700.00
15 TUKANG ASPAL org 71,500.00 74,700.00
16 TUKANG PIPA org 71,500.00 74,700.00
17 TUKANG LISTRIK org 71,500.00 74,700.00
18 PEMBANTU TK. BATU org 55,000.00 57,500.00
19 PEMBANTU TK. KAYU org 55,000.00 57,500.00
20 PEMBANTU TK. BESI org 55,000.00 57,500.00
21 PEMBANTU TK. CAT org 55,000.00 57,500.00
22 PEMBANTU TK. LISTRIK org 55,000.00 57,500.00
23 PEMBANTU TK. PIPA org 55,000.00 57,500.00
24 MASINIS org 66,000.00 69,000.00
25 PEMBANTU MASINIS org 49,500.00 51,700.00
26 MEKANIK org 77,000.00 80,500.00
27 PEMBANTU MEKANIK org 49,500.00 51,700.00
28 OPERATOR org 60,500.00 63,200.00
29 PENGEMUDI/SOPIR org 60,500.00 63,200.00
30 TUKANG TANAM org 49,500.00 51,700.00
31 PENJAGA API org 49,500.00 51,700.00
32 PENJAGA MALAM org 49,500.00 51,700.00
33 SOPIR MATERIAL/TRUCK oh 66,000.00 69,000.00
34 OPERATOR (FINISHER, BULLDOZER) oh 66,000.00 69,000.00
35 OPERATOR SEMI TERLATIH oh 66,000.00 69,000.00
36 PEMBANTU OPERATOR oh 55,000.00 57,500.00
37 PEMBANTU SOPIR/ KENEK oh 49,500.00 51,700.00
38 BURUH LAPANGAN TAK TERLATIH oh 44,000.00 46,000.00
39 BURUH LAPANGAN AGAK TERLATIH oh 46,700.00 48,800.00
40 BURUH LAPANGAN TERLATIH oh 49,500.00 51,700.00
BIAYA (ONGKOS KERJA KHUSUS TENAGA PINTU AIR)
1 ONGKOS KERJA KONSTRUKSI Kg 5,000.00 5,000.00
2 ONGKOS KERJA MESIN Kg 7,000.00 7,000.00
3 ONGKOS KERJA KAYU m3 250,000.00 250,000.00
4 SANDBLASTING DAN CAT m2 40,000.00 40,000.00
5 PENGECATAN TANPA SAND m2 40,000.00 40,000.00

BUPATI PONOROGO

H. AMIN, SH

Page 28
DAFTAR REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN
( BIDANG CIPTA KARYA DAN TATA RUANG )

Kode AHSP
JENIS PEKERJAAN SAT
SNI TERENDAH TERTINGGI
2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
2.2.1.1 0 m2 - -
0 0 m2 - -
0 0 m2 - -
0 0 m' - -
0 0 m2 - -
0 0 m2 - -
0 0 m2 - -
0 0 m2 - -
0 0 m2 - -
0 0 m2 - -
0 0 bh - -
0 0 m2 - -
0 0 m3 - -
0 0 m3 - -
0 0 m2 - -
0 0 m2 - -

2.3.1 HARGA SATUAN PEKERJAAN TANAH


0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m2 - -
0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m3 - -
0 0 m2 - -
0 0 m3 - -

3.2.1 HARGA SATUAN PEKERJAAN PONDASI


0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -

4.1.1 HARGA SATUAN PEKERJAAN BETON


0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 Kg -
0 0 Kg -
0 0 Kg -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m3 -

4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


0 0 Kg -
0 0 Kg -
0 0 100 Kg -
0 0 m2 -
0 0 cm -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -
0 0 m2 -
0 0 m2 -

4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -

4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -

4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -

4.5.1 HARGA SATUAN PEKERJAAN LANGIT - LANGIT (PLAFOND)


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -

4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m2 -
0 0 m' -
0 0 m2 -
0 0 m' -
0 0 m2 -

4.6.1 HARGA SATUAN PEKERJAAN KAYU


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m3 -
0 0 m3 -
0 0 m3 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m' -
0 0 m' -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -

4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA


0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 Bh -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -

4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -
0 0 m2 -

5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 bh -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -
0 0 m' -

X.X.X HARGA SATUAN PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA AIR BERSIH
1 Pemasangan pipa serta peralatannya pvc dia. 32 mm ( 1 ' ) - SC.S12.5 m' -
2 0 m' -
3 0 m' -
4 0 m' -
5 0 m' -
6 0 m' -
7 0 m' -
8 0 m' -
9 0 m' -
10 0 m' -
11 0 m' -
12 0 m' -
13 0 m' -
14 0 m' -
15 0 m' -
16 0 m' -
17 0 m' -
18 0 m' -
19 0 m' -
20 0 m' -
21 0 m' -
22 0 m' -
23 0 m' -
24 0 m' -
25 0 m' -
26 0 m' -
27 0 m' -
28 0 m' -
ANALISA HARGA SATUAN PEKERJAAN (AHsP)

2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
2.2.1.1 Pembuatan 1 m2 Pagar sementara dari kayu tinggi 2 meter
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.020 88,000.00 1,760.00
JUMLAH TENAGA KERJA 39,600.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 1.250 22,000.00 27,500.00
Semen Portland kg 5.000 1,400.00 7,000.00
Pasir beton m3 0.005 200,000.00 1,000.00
Koral beton m3 0.009 185,300.00 1,667.70
Kayu 5/7 m3 0.072 4,000,000.00 288,000.00
Paku biasa 2"-5" kg 0.060 14,500.00 870.00
Residu Ltr 0.400 12,800.00 5,120.00
JUMLAH HARGA BAHAN 331,157.70
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 370,757.70
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 370,757.70
2.2.1.2 Pembuatan 1 m2 Pagar sementara dari seng gelombang tinggi 2 meter
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.400 71,500.00 28,600.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.020 88,000.00 1,760.00
JUMLAH TENAGA KERJA 42,900.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 1.250 22,000.00 27,500.00
Semen Portland Kg 2.500 1,400.00 3,500.00
Seng Gelombang Lbr 1.200 58,300.00 69,960.00
Pasir beton m3 0.005 200,000.00 1,000.00
Koral beton m3 0.009 185,300.00 1,667.70
Kayu 5/7 m3 0.072 4,000,000.00 288,000.00
Paku biasa 2"-5" Kg 0.060 14,500.00 870.00
Residu Ltr 0.450 12,800.00 5,760.00
JUMLAH HARGA BAHAN 398,257.70
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 441,157.70
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 441,157.70
2.2.1.3 Pembuatan 1 m2 Pagar sementara dari kawat duri tinggi 1,8 meter
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.020 88,000.00 1,760.00
JUMLAH TENAGA KERJA 35,750.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 1.000 22,000.00 22,000.00
Semen Portland Kg 2.000 1,400.00 2,800.00
Kawat Duri m' 25.000 13,000.00 325,000.00
Pasir beton m3 0.005 200,000.00 1,000.00
Koral beton m3 0.009 185,300.00 1,667.70
Paku biasa 2"-5" Kg 0.060 14,500.00 870.00
JUMLAH HARGA BAHAN 353,337.70
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 389,087.70
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 389,087.70
2.2.1.4 Pengukuran dan pemasangan 1 m' Bouwplank
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Kayu balok 5/7 Btg 1.000 28,000.00 28,000.00
Paku 2" - 3" Kg 2.000 20,000.00 40,000.00
Kayu papan 3/20 m' 25.000 - -
JUMLAH HARGA BAHAN 68,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 81,860.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 81,860.00
2.2.1.5 Pembuatan 1 m2 kantor sementara dengan lantai plesteran
A. TENAGA
Pekerja L.01 OH 2.000 55,000.00 110,000.00
Tukang Kayu L.02 OH 2.000 71,500.00 143,000.00
Tukang Batu L.02 OH 1.000 71,500.00 71,500.00
Kepala Tukang L.03 OH 0.300 77,000.00 23,100.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 352,000.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 1.250 22,000.00 27,500.00
Kayu 5/7 m3 0.180 4,000,000.00 720,000.00
Paku biasa Kg 0.080 14,500.00 1,160.00
Besi strip Kg 1.100 15,000.00 16,500.00
Semen Portland Kg 35.000 1,400.00 49,000.00
Pasir pasang m3 0.150 132,000.00 19,800.00
Pasir beton m3 0.100 200,000.00 20,000.00
Koral beton m3 0.150 185,300.00 27,795.00
Bata merah Bh 30.000 750.00 22,500.00
Seng plat Lbr 0.250 49,500.00 12,375.00
Jendela nako Bh 2.000 - -
Kaca polos m2 0.080 93,500.00 7,480.00
Kunci tanam Bh 0.150 47,500.00 7,125.00
Plywood 4 mm Lbr 0.060 95,000.00 5,700.00
JUMLAH HARGA BAHAN 936,935.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,288,935.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,288,935.00
2.2.1.6 Pembuatan 1 m2 rumah jaga (konstruksi kayu)
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 1.500 71,500.00 107,250.00
Kepala Tukang L.03 OH 0.150 77,000.00 11,550.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 178,200.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 3.000 22,000.00 66,000.00
Kayu 5/7 m3 0.276 4,000,000.00 1,104,000.00
Paku biasa Kg 0.700 14,500.00 10,150.00
Seng Gelombang Kg 1.500 58,300.00 87,450.00
JUMLAH HARGA BAHAN 1,267,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,445,800.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,445,800.00
2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 2.000 71,500.00 143,000.00
Kepala Tukang L.03 OH 0.200 77,000.00 15,400.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 217,800.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 1.700 22,000.00 37,400.00
Kayu 5/7 m3 0.210 4,000,000.00 840,000.00
Paku biasa Kg 0.300 14,500.00 4,350.00
Semen Portland Kg 10.500 1,400.00 14,700.00
Pasir beton m3 0.030 200,000.00 6,000.00
Koral beton m3 0.050 185,300.00 9,265.00
Seng gelombang Lbr 1.500 58,300.00 87,450.00
Seng plat Lbr 0.250 49,500.00 12,375.00
JUMLAH HARGA BAHAN 1,011,540.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,229,340.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,229,340.00
2.2.1.8 Pembuatan 1 m2 bedeng pekerja
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 2.000 71,500.00 143,000.00
Kepala Tukang L.03 OH 0.200 77,000.00 15,400.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 217,800.00
B. BAHAN
Dolken kayu Ø 8 - 10 /400 cm Btg 1.250 22,000.00 27,500.00
Kayu 5/7 m3 0.186 4,000,000.00 744,000.00
Paku biasa Kg 0.300 14,500.00 4,350.00
Semen Portland Kg 18.000 1,400.00 25,200.00
Pasir beton m3 0.030 200,000.00 6,000.00
Koral beton m3 0.050 185,300.00 9,265.00
Seng gelombang Lbr 1.500 58,300.00 87,450.00
Plywood 4 mm Lbr 1.350 95,000.00 128,250.00
JUMLAH HARGA BAHAN 1,032,015.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,249,815.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,249,815.00
2.2.1.9 Pembersihan 1 m2 lapangan dan perataan
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 9,900.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 9,900.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 9,900.00
2.2.1.10 Pembuatan 1 m2 steger/perancah dari bambu
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 2.000 71,500.00 143,000.00
Kepala Tukang L.03 OH 0.200 77,000.00 15,400.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 217,800.00
B. BAHAN
Bambu Ø 6 - 8 /600 cm Btg 1.250 13,700.00 17,125.00
Tali Ijuk m3 0.186 20,900.00 3,887.40
JUMLAH HARGA BAHAN 21,012.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 238,812.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 238,812.40
2.2.1.11 Pembuatan 1 bh kotak adukan ukuran 40 x 50 x 25 cm
A. TENAGA
Tukang Kayu L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.030 77,000.00 2,310.00
JUMLAH TENAGA KERJA 23,760.00
B. BAHAN
Kayu papan kelas III m3 0.036 6,250,000.00 225,000.00
Kayu balok 5/7 kelas III m3 0.014 5,150,000.00 72,100.00
Paku biasa kg 0.080 14,500.00 1,160.00
JUMLAH HARGA BAHAN 298,260.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 322,020.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 322,020.00
2.2.1.12 Pembuatan 1 m2 jalan sementara
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 55,440.00
B. BAHAN
Batu belah 15/20 m3 0.150 148,500.00 22,275.00
Batu pecah 5/7 m3 0.090 154,000.00 13,860.00
Pasir pasang m3 0.010 132,000.00 1,320.00
JUMLAH HARGA BAHAN 37,455.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 92,895.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 92,895.00
2.2.1.13 Pembongkaran 1 m3 beton bertulang
A. TENAGA
Pekerja L.01 OH 13.334 55,000.00 733,370.00
Mandor L.04 OH 0.666 88,000.00 58,608.00
JUMLAH TENAGA KERJA 791,978.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 791,978.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 791,978.00
2.2.1.14 Pembongkaran 1 m3 dinding tembok bata
A. TENAGA
Pekerja L.01 OH 6.667 55,000.00 366,685.00
Mandor L.04 OH 0.333 88,000.00 29,304.00
JUMLAH TENAGA KERJA 395,989.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 395,989.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 395,989.00
2.2.1.15 Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm
A. TENAGA
Pekerja L.01 OH 0.042 55,000.00 2,310.00
Tukang L.02 OH 0.004 71,500.00 286.00
Kepala Tukang L.03 OH 0.002 77,000.00 154.00
Mandor L.04 OH 0.042 88,000.00 3,696.00
JUMLAH TENAGA KERJA 6,446.00
B. BAHAN
Kawat jaring Lbr 0.1434 192,500.00 27,604.50
JUMLAH HARGA BAHAN 27,604.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 34,050.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 34,050.50
2.2.1.16 Pemasangan 1 m2 panel beton pracetak 5 x 50 x 213 cm
A. TENAGA
Pekerja L.01 OH 0.375 55,000.00 20,625.00
Tukang L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.019 88,000.00 1,672.00
JUMLAH TENAGA KERJA 32,158.50
B. BAHAN
Panel beton pracetak Lbr 0.986 253,000.00 249,458.00
Kolom beton pracetak Btg 0.525 363,000.00 190,575.00
Semen PC Kg 45.000 1,400.00 63,000.00
Pasir beton m3 0.074 200,000.00 14,800.00
Koral m3 0.146 185,300.00 27,053.80
JUMLAH HARGA BAHAN 544,886.80
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 577,045.30
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 577,045.30

2.3.1 HARGA SATUAN PEKERJAAN TANAH

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m
A. TENAGA
Pekerja L.01 OH 0.750 71,500.00 53,625.00
Mandor L.04 OH 0.025 88,000.00 2,200.00
JUMLAH TENAGA KERJA 55,825.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 55,825.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 55,825.00
2.3.1.2 Penggalian 1 m3 tanah biasa sedalam 2 m
A. TENAGA
Pekerja L.01 OH 0.900 71,500.00 64,350.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
JUMLAH TENAGA KERJA 68,310.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 68,310.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 68,310.00
2.3.1.3 Penggalian 1 m3 tanah biasa sedalam 3 m
A. TENAGA
Pekerja L.01 OH 1.050 71,500.00 75,075.00
Mandor L.04 OH 0.067 88,000.00 5,896.00
JUMLAH TENAGA KERJA 80,971.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 80,971.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 80,971.00
2.3.1.4 Menggali 1 m3 tanah keras sedalam 1 m
A. TENAGA
Pekerja L.01 OH 1.000 71,500.00 71,500.00
Mandor L.04 OH 0.032 88,000.00 2,816.00
JUMLAH TENAGA KERJA 74,316.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 74,316.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 74,316.00
2.3.1.5 Menggali 1 m3 tanah cadas sedalam 1 m
A. TENAGA
Pekerja L.01 OH 1.500 71,500.00 107,250.00
Mandor L.04 OH 0.060 88,000.00 5,280.00
JUMLAH TENAGA KERJA 112,530.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 112,530.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 112,530.00
2.3.1.6 Menggali 1 m3 tanah lumpur sedalam 1 m
A. TENAGA
Pekerja L.01 OH 1.200 71,500.00 85,800.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
JUMLAH TENAGA KERJA 89,760.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 89,760.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 89,760.00
2.3.1.7 Pengerjaan stripping 1 m2 tanah tebing setinggi 1 m
A. TENAGA
Pekerja L.01 OH 0.050 71,500.00 3,575.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 4,015.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,015.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 4,015.00
2.3.1.8 Pembuangan 1 m3 tanah sejauh 30 m
A. TENAGA
Pekerja L.01 OH 0.330 55,000.00 18,150.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 19,030.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 19,030.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 19,030.00
2.3.1.9 Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
A. TENAGA
Pekerja L.01 OH 0.500 55,000.00 27,500.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 31,900.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 31,900.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 31,900.00
2.3.1.10 Pemadatan tanah 1 m3 tanah (per 20 cm)
A. TENAGA
Pekerja L.01 OH 0.500 55,000.00 27,500.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 31,900.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 31,900.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 31,900.00
2.3.1.11 Pengurugan 1 m3 dengan pasir urug
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 17,380.00
B. BAHAN
Pasir urug m3 1.200 70,000.00 84,000.00
JUMLAH HARGA BAHAN 84,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 101,380.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 101,380.00
2.3.1.12 Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL
A. TENAGA
Pekerja L.01 OH 0.800 55,000.00 44,000.00
Tukang L.02 OH 0.400 71,500.00 28,600.00
Kepala Tukang L.03 OH 0.040 77,000.00 3,080.00
Mandor L.04 OH 0.080 88,000.00 7,040.00
JUMLAH TENAGA KERJA 82,720.00
B. BAHAN
Kapur Padam m3 0.135 280,000.00 37,800.00
Pasir Pasang m3 0.400 132,000.00 52,800.00
Tanah Liat m3 0.948 36,000.00 34,128.00
JUMLAH HARGA BAHAN 124,728.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 207,448.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 207,448.00
2.3.1.13 Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 9,570.00
B. BAHAN
Ijuk m3 6.000 6,500.00 39,000.00
JUMLAH HARGA BAHAN 39,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 48,570.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 48,570.00
2.3.1.14 Pengurugan 1 m3 sirtu padat
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Mandor L.04 OH 0.025 88,000.00 2,200.00
JUMLAH TENAGA KERJA 15,950.00
B. BAHAN
Sirtu m3 1.200 68,000.00 81,600.00
JUMLAH HARGA BAHAN 81,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 97,550.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 97,550.00

3.2.1 HARGA SATUAN PEKERJAAN PONDASI


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
3.2.1.1 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Semen Portland kg 202.000 1,400.00 282,800.00
Pasir pasang m3 0.485 132,000.00 64,020.00
JUMLAH HARGA BAHAN 525,020.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 673,520.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 673,520.00
3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Semen Portland kg 163.000 1,400.00 228,200.00
Pasir pasang m3 0.520 132,000.00 68,640.00
JUMLAH HARGA BAHAN 475,040.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 623,540.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 623,540.00
3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 5PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Semen Portland kg 136.000 1,400.00 190,400.00
Pasir pasang m3 0.544 132,000.00 71,808.00
JUMLAH HARGA BAHAN 440,408.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 588,908.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 588,908.00
3.2.1.4 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 6PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Semen Portland kg 117.000 1,400.00 163,800.00
Pasir pasang m3 0.561 132,000.00 74,052.00
JUMLAH HARGA BAHAN 416,052.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 564,552.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 564,552.00
3.2.1.5 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 8PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Semen Portland kg 91.000 1,400.00 127,400.00
Pasir pasang m3 0.584 132,000.00 77,088.00
JUMLAH HARGA BAHAN 382,688.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 531,188.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 531,188.00
3.2.1.6 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 1KP : 2PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Kapur m3 0.170 280,000.00 47,600.00
Semen Portland kg 0.170 1,400.00 238.00
Pasir pasang m3 0.340 132,000.00 44,880.00
JUMLAH HARGA BAHAN 270,918.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 419,418.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 419,418.00
3.2.1.7 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 3KP : 10PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Kapur m3 0.147 280,000.00 41,160.00
Semen Portland kg 61.000 1,400.00 85,400.00
Pasir pasang m3 0.492 132,000.00 64,944.00
JUMLAH HARGA BAHAN 369,704.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 518,204.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 518,204.00
3.2.1.8 Pemasangan 1 m3 pondasi batu belah campuran 1/4PC : 1KP : 4PP
A. TENAGA
Pekerja L.01 OH 1.500 55,000.00 82,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 148,500.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Kapur m3 0.131 280,000.00 36,680.00
Semen Portland kg 41.000 1,400.00 57,400.00
Pasir pasang m3 0.523 132,000.00 69,036.00
JUMLAH HARGA BAHAN 341,316.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 489,816.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 489,816.00
3.2.1.9 Pemasangan 1 m3 batu kosong (anstamping)
A. TENAGA
Pekerja L.01 OH 0.780 55,000.00 42,900.00
Tukang Batu L.02 OH 0.390 71,500.00 27,885.00
Kepala Tukang L.03 OH 0.039 77,000.00 3,003.00
Mandor L.04 OH 0.039 88,000.00 3,432.00
JUMLAH TENAGA KERJA 77,220.00
B. BAHAN
Batu belah m3 1.200 148,500.00 178,200.00
Pasir urug m3 0.432 70,000.00 30,240.00
JUMLAH HARGA BAHAN 208,440.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 285,660.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 285,660.00
3.2.1.10 Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1PC : 2PB : 3KR dan 40% batu belah
A. TENAGA
Pekerja L.01 OH 3.400 55,000.00 187,000.00
Tukang Batu L.02 OH 0.850 71,500.00 60,775.00
Kepala Tukang L.03 OH 0.085 77,000.00 6,545.00
Mandor L.04 OH 0.170 88,000.00 14,960.00
JUMLAH TENAGA KERJA 269,280.00
B. BAHAN
Batu belah m3 0.480 148,500.00 71,280.00
Semen Portland Kg 194.000 1,400.00 271,600.00
Pasir beton m3 0.312 200,000.00 62,400.00
Kerikil m3 0.468 185,300.00 86,720.40
Besi beton Kg 126.000 10,300.00 1,297,800.00
Kawat beton Kg 1.800 15,000.00 27,000.00
JUMLAH HARGA BAHAN 1,816,800.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 2,086,080.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 2,086,080.40
3.2.1.11 Pemasangan 1 m3 pondasi sumuran, diameter 100 cm
A. TENAGA
Pekerja L.01 OH 2.400 55,000.00 132,000.00
Tukang Batu L.02 OH 0.800 71,500.00 57,200.00
Kepala Tukang L.03 OH 0.080 77,000.00 6,160.00
Mandor L.04 OH 0.119 88,000.00 10,472.00
JUMLAH TENAGA KERJA 205,832.00
B. BAHAN
Batu belah m3 0.450 148,500.00 66,825.00
Semen Portland Kg 194.000 1,400.00 271,600.00
Pasir beton m3 0.312 200,000.00 62,400.00
Kerikil m3 0.468 185,300.00 86,720.40
JUMLAH HARGA BAHAN 487,545.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 693,377.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 693,377.40

4.1.1 HARGA SATUAN PEKERJAAN BETON

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.1.1.1 Membuat 1 m3 beton mutu fc = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 247.000 1,400.00 345,800.00
Pasir Beton m3 0.621 200,000.00 124,142.86
Kerikil (max 30 mm) m3 0.740 185,300.00 137,122.00
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 624,264.86
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 744,137.36
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 744,137.36
4.1.1.2 Membuat 1 m3 beton mutu fc = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 276.000 1,400.00 386,400.00
Pasir Beton m3 0.591 200,000.00 118,285.71
Kerikil (max 30 mm) m3 0.750 185,300.00 138,906.37
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 660,792.08
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 780,664.58
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 780,664.58
4.1.1.3 Membuat 1 m3 beton mutu fc = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 299.000 1,400.00 418,600.00
Pasir Beton m3 0.571 200,000.00 114,142.86
Kerikil (max 30 mm) m3 0.753 185,300.00 139,592.67
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 689,535.52
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 809,408.02
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 809,408.02

CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f', = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
A. TENAGA
Pekerja L.01 OH 1.200 55,000.00 66,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.060 88,000.00 5,280.00
JUMLAH TENAGA KERJA 87,120.00
B. BAHAN
Semen Portland Kg 230.000 1,400.00 322,000.00
Pasir Beton Kg 0.638 200,000.00 127,571.43
Kerikil (max 30 mm) Kg 0.761 185,300.00 140,965.26
Air Ltr 200.000 80.00 16,000.00
JUMLAH HARGA BAHAN 606,536.69
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 693,656.69
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 693,656.69
4.1.1.5 Membuat 1 m3 beton mutu fc = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 326.000 1,400.00 456,400.00
Pasir Beton Kg 0.543 200,000.00 108,571.43
Kerikil (max 30 mm) Kg 0.762 185,300.00 141,239.78
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 723,411.21
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 843,283.71
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 843,283.71
4.1.1.6 Membuat 1 m3 beton mutu fc = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 352.000 1,400.00 492,800.00
Pasir Beton Kg 0.522 200,000.00 104,428.57
Kerikil (max 30 mm) Kg 0.764 185,300.00 141,514.30
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 755,942.87
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 875,815.37
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 875,815.37
4.1.1.7 Membuat 1 m3 beton mutu fc = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 371.000 1,400.00 519,400.00
Pasir Beton Kg 0.499 200,000.00 99,714.29
Kerikil (max 30 mm) Kg 0.776 185,300.00 143,710.44
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 780,024.73
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 899,897.23
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 899,897.23
4.1.1.8 Membuat 1 m3 beton mutu fc = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 384.000 1,400.00 537,600.00
Pasir Beton Kg 0.494 200,000.00 98,857.14
Kerikil (max 30 mm) Kg 0.770 185,300.00 142,612.37
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 796,269.51
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 916,142.01
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 916,142.01
4.1.1.9 Membuat 1 m3 beton mutu fc = 24,0 MPa (K 275), slump (12 ± 2) cm, w/o = 0,53
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 406.000 1,400.00 568,400.00
Pasir Beton Kg 0.489 200,000.00 97,714.29
Kerikil (max 30 mm) Kg 0.760 185,300.00 140,828.00
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 824,142.29
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 944,014.79
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 944,014.79
4.1.1.10 Membuat 1 m3 beton mutu fc = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
A. TENAGA
Pekerja L.01 OH 1.650 55,000.00 90,750.00
Tukang Batu L.02 OH 0.275 71,500.00 19,662.50
Kepala Tukang L.03 OH 0.028 77,000.00 2,156.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 119,872.50
B. BAHAN
Semen Portland Kg 413.000 1,400.00 578,200.00
Pasir Beton Kg 0.486 200,000.00 97,285.71
Kerikil (max 30 mm) Kg 0.756 185,300.00 140,141.70
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 832,827.42
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 952,699.92
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 952,699.92
4.1.1.11 Membuat 1 m3 beton mutu fc = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
A. TENAGA
Pekerja L.01 OH 2.100 55,000.00 115,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.105 88,000.00 9,240.00
JUMLAH TENAGA KERJA 152,460.00
B. BAHAN
Semen Portland Kg 439.000 1,400.00 614,600.00
Pasir Beton Kg 0.479 200,000.00 95,714.29
Kerikil (max 30 mm) Kg 0.745 185,300.00 138,082.81
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 865,597.10
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,018,057.10
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,018,057.10
4.1.1.12 Membuat 1 m3 beton mutu fc = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
A. TENAGA
Pekerja L.01 OH 2.100 55,000.00 115,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.105 88,000.00 9,240.00
JUMLAH TENAGA KERJA 152,460.00
B. BAHAN
Semen Portland Kg 448.000 1,400.00 627,200.00
Pasir Beton Kg 0.476 200,000.00 95,285.71
Kerikil (max 30 mm) Kg 0.741 185,300.00 137,259.26
Air Ltr 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 876,944.97
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,029,404.97
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,029,404.97
4.1.1.13 Membuat 1 m3 beton kedap air dengan strorox - 100
A. TENAGA
Pekerja L.01 OH 2.100 55,000.00 115,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.105 88,000.00 9,240.00
JUMLAH TENAGA KERJA 152,460.00
B. BAHAN
Semen Portland Kg 400.000 1,400.00 560,000.00
Pasir Beton Kg 0.480 200,000.00 96,000.00
KR (Kerikil 2/3cm) Kg 0.800 185,300.00 148,240.00
Strorox —100 Kg 1.200 27,500.00 33,000.00
JUMLAH HARGA BAHAN 837,240.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 989,700.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 989,700.00
4.1.1.14 Pemasangan 1 m' PVC Waterstop lebar 150 mm
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Batu/Pipa L.02 OH 0.030 71,500.00 2,145.00
Kepala Tukang L.03 OH 0.003 77,000.00 231.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 5,940.00
B. BAHAN
Waterstop lebar 150 mm m' 1.050 8,300.00 8,715.00
JUMLAH HARGA BAHAN 8,715.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,655.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 14,655.00
4.1.1.15 Pemasangan 1 m' PVC Waterstop lebar 200 mm
A. TENAGA
Pekerja L.01 OH 0.070 55,000.00 3,850.00
Tukang Batu/Pipa L.02 OH 0.035 71,500.00 2,502.50
Kepala Tukang L.03 OH 0.004 77,000.00 308.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 7,276.50
B. BAHAN
Waterstop lebar 200 mm m' 1.050 12,300.00 12,915.00
JUMLAH HARGA BAHAN 12,915.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 20,191.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 20,191.50
4.1.1.16 Pemasangan 1 m' PVC Waterstop lebar 230 mm - 320 mm
A. TENAGA
Pekerja L.01 OH 0.080 55,000.00 4,400.00
Tukang Batu/Pipa L.02 OH 0.040 71,500.00 2,860.00
Kepala Tukang L.03 OH 0.004 77,000.00 308.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 7,920.00
B. BAHAN
Waterstop lebar 230 mm - 320 mm m' 1.050 41,300.00 43,365.00
JUMLAH HARGA BAHAN 43,365.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 51,285.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 51,285.00
4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir
A. TENAGA
Pekerja L.01 OH 0.070 55,000.00 3,850.00
Tukang Besi L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 9,746.00
B. BAHAN
Besi beton (polos/ulir) Kg 10.500 10,300.00 108,150.00
Kawat beton Kg 0.150 15,000.00 2,250.00
JUMLAH HARGA BAHAN 110,400.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 120,146.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 120,146.00
4.1.1.18 Pembesian 10 kg kabel presstressed polos/strands
A. TENAGA
Pekerja L.01 OH 0.050 55,000.00 2,750.00
Tukang Besi L.02 OH 0.050 71,500.00 3,575.00
Kepala Tukang L.03 OH 0.005 77,000.00 385.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 6,974.00
B. BAHAN
Besi beton (polos/ulir) Kg 10.500 10,300.00 108,150.00
Kawat beton Kg 0.100 15,000.00 1,500.00
JUMLAH HARGA BAHAN 109,650.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 116,624.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 116,624.00
4.1.1.19 Pembesian 10 kg jaring kawat baja (wire mesh)
A. TENAGA
Pekerja L.01 OH 0.025 55,000.00 1,375.00
Tukang Besi L.02 OH 0.025 71,500.00 1,787.50
Kepala Tukang L.03 OH 0.002 77,000.00 154.00
Mandor L.04 OH 0.001 88,000.00 88.00
JUMLAH TENAGA KERJA 3,404.50
B. BAHAN
Jaring kawat baja dilas Kg 10.200 45,000.00 459,000.00
Kawat beton Kg 0.050 15,000.00 750.00
JUMLAH HARGA BAHAN 459,750.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 463,154.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 463,154.50
4.1.1.-- Pemasangan 1 m2 bekisting untuk balok dan kolom praktis
A. TENAGA
Pekerja L.01 OH 0.520 55,000.00 28,600.00
Tukang Besi L.02 OH 0.260 55,000.00 14,300.00
Kepala Tukang L.03 OH 0.026 71,500.00 1,859.00
Mandor L.04 OH 0.026 77,000.00 2,002.00
JUMLAH TENAGA KERJA 46,761.00
B. BAHAN
Kayu kelas III m3 0.045 3,575,000.00 160,875.00
Paku 5 - 10 cm Kg 0.300 14,500.00 4,350.00
Minyak bekisting Ltr 0.100 4,700.00 470.00
JUMLAH HARGA BAHAN 165,695.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 212,456.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 212,456.00
4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi
A. TENAGA
Pekerja L.01 OH 0.520 55,000.00 28,600.00
Tukang Besi L.02 OH 0.260 71,500.00 18,590.00
Kepala Tukang L.03 OH 0.026 77,000.00 2,002.00
Mandor L.04 OH 0.026 88,000.00 2,288.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Kayu kelas III m3 0.040 3,575,000.00 143,000.00
Paku 5 - 10 cm Kg 0.300 14,500.00 4,350.00
Minyak bekisting Ltr 0.100 4,700.00 470.00
JUMLAH HARGA BAHAN 147,820.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 199,300.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 199,300.00
4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof
A. TENAGA
Pekerja L.01 OH 0.520 55,000.00 28,600.00
Tukang Kayu L.02 OH 0.260 71,500.00 18,590.00
Kepala Tukang L.03 OH 0.026 77,000.00 2,002.00
Mandor L.04 OH 0.026 88,000.00 2,288.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Kayu kelas III m3 0.045 3,575,000.00 160,875.00
Paku 5 - 10 cm Kg 0.300 14,500.00 4,350.00
Minyak bekisting Ltr 0.100 4,700.00 470.00
JUMLAH HARGA BAHAN 165,695.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 217,175.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 217,175.00
4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom
A. TENAGA
Pekerja L.01 OH 0.660 55,000.00 36,300.00
Tukang Kayu L.02 OH 0.330 71,500.00 23,595.00
Kepala Tukang L.03 OH 0.033 77,000.00 2,541.00
Mandor L.04 OH 0.033 88,000.00 2,904.00
JUMLAH TENAGA KERJA 65,340.00
B. BAHAN
Kayu kelas III m3 0.040 3,575,000.00 143,000.00
Paku 5 - 12 cm Kg 0.400 14,500.00 5,800.00
Minyak bekisting Ltr 0.200 4,700.00 940.00
Balok kayu kelas II m3 0.015 8,000,000.00 120,000.00
Plywood tebal 9 mm Lbr 0.350 137,200.00 48,020.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 2.000 22,000.00 44,000.00
JUMLAH HARGA BAHAN 361,760.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 427,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 427,100.00
4.1.1.23 Pemasangan 1 m2 bekisting untuk balok
A. TENAGA
Pekerja L.01 OH 0.660 55,000.00 36,300.00
Tukang Kayu L.02 OH 0.330 71,500.00 23,595.00
Kepala Tukang L.03 OH 0.033 77,000.00 2,541.00
Mandor L.04 OH 0.033 88,000.00 2,904.00
JUMLAH TENAGA KERJA 65,340.00
B. BAHAN
Kayu kelas III m3 0.040 3,575,000.00 143,000.00
Paku 5 - 12 cm Kg 0.400 14,500.00 5,800.00
Minyak bekisting Ltr 0.200 4,700.00 940.00
Balok kayu kelas II m3 0.018 8,000,000.00 144,000.00
Plywood tebal 9 mm Lbr 0.350 137,200.00 48,020.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 2.000 22,000.00 44,000.00
JUMLAH HARGA BAHAN 385,760.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 451,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 451,100.00
4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai
A. TENAGA
Pekerja L.01 OH 0.660 55,000.00 36,300.00
Tukang Kayu L.02 OH 0.330 71,500.00 23,595.00
Kepala Tukang L.03 OH 0.033 77,000.00 2,541.00
Mandor L.04 OH 0.033 88,000.00 2,904.00
JUMLAH TENAGA KERJA 65,340.00
B. BAHAN
Kayu kelas III m3 0.040 3,575,000.00 143,000.00
Paku 5 - 12 cm Kg 0.400 14,500.00 5,800.00
Minyak bekisting Ltr 0.200 4,700.00 940.00
Balok kayu kelas II m3 0.015 8,000,000.00 120,000.00
Plywood tebal 9 mm Lbr 0.350 137,200.00 48,020.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 6.000 22,000.00 132,000.00
JUMLAH HARGA BAHAN 449,760.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 515,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 515,100.00
4.1.1.25 Pemasangan 1 m2 bekisting untuk dinding
A. TENAGA
Pekerja L.01 OH 0.660 55,000.00 36,300.00
Tukang Kayu L.02 OH 0.330 71,500.00 23,595.00
Kepala Tukang L.03 OH 0.033 77,000.00 2,541.00
Mandor L.04 OH 0.033 88,000.00 2,904.00
JUMLAH TENAGA KERJA 65,340.00
B. BAHAN
Kayu kelas III m3 0.030 3,575,000.00 107,250.00
Paku 5 - 12 cm Kg 0.400 14,500.00 5,800.00
Minyak bekisting Ltr 0.200 4,700.00 940.00
Balok kayu kelas II m3 0.020 8,000,000.00 160,000.00
Plywood tebal 9 mm Lbr 0.350 137,200.00 48,020.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 3.000 22,000.00 66,000.00
Formite/penjaga jarakbekisting (spacer) Bh 4.000 6,000.00 24,000.00
JUMLAH HARGA BAHAN 412,010.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 477,350.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 477,350.00
4.1.1.26 Pemasangan 1 m2 bekisting untuk tangga
A. TENAGA
Pekerja L.01 OH 0.660 55,000.00 36,300.00
Tukang Kayu L.02 OH 0.330 71,500.00 23,595.00
Kepala Tukang L.03 OH 0.033 77,000.00 2,541.00
Mandor L.04 OH 0.033 88,000.00 2,904.00
JUMLAH TENAGA KERJA 65,340.00
B. BAHAN
Kayu kelas III m3 0.030 3,575,000.00 107,250.00
Paku 5 - 12 cm Kg 0.400 14,500.00 5,800.00
Minyak bekisting Ltr 0.150 4,700.00 705.00
Balok kayu kelas II m3 0.015 8,000,000.00 120,000.00
Plywood tebal 9 mm Lbr 0.350 137,200.00 48,020.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 2.000 22,000.00 44,000.00
JUMLAH HARGA BAHAN 325,775.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 391,115.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 391,115.00
4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.050 71,500.00 3,575.00
Kepala Tukang L.03 OH 0.005 77,000.00 385.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 12,914.00
B. BAHAN
Kayu kelas III (papan) m3 0.0264 6,250,000.00 165,000.00
Paku 5 - 12 cm Kg 0.600 14,500.00 8,700.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 0.500 22,000.00 11,000.00
JUMLAH HARGA BAHAN 184,700.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 197,614.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 197,614.00
4.1.1.28 Pembuatan 1 m3 pondasi beton bertulang (150 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 5.300 55,000.00 291,500.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.300 71,500.00 92,950.00
Tukang besi L.02 OH 1.050 71,500.00 75,075.00
Kepala tukang L.03 OH 0.262 77,000.00 20,174.00
Mandor L.04 OH 0.265 88,000.00 23,320.00
JUMLAH TENAGA KERJA 522,681.50
B. BAHAN
Kayu kelas III m3 0.200 3,575,000.00 715,000.00
Paku 5 - 12 cm Kg 1.500 14,500.00 21,750.00
Minyak bekisting Ltr 0.400 4,700.00 1,880.00
Besi beton polos Kg 157.500 10,300.00 1,622,250.00
Kawat beton Kg 2.250 15,000.00 33,750.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
JUMLAH HARGA BAHAN 3,123,123.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 3,645,804.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 3,645,804.50
4.1.1.29 Pembuatan 1 m3 sloof beton bertulang (200 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 5.650 55,000.00 310,750.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.560 71,500.00 111,540.00
Tukang besi L.02 OH 1.400 71,500.00 100,100.00
Kepala tukang L.03 OH 0.323 77,000.00 24,871.00
Mandor L.04 OH 0.283 88,000.00 24,904.00
JUMLAH TENAGA KERJA 591,827.50
B. BAHAN
Kayu kelas III m3 0.270 3,575,000.00 965,250.00
Paku 5 - 12 cm Kg 2.000 14,500.00 29,000.00
Minyak bekisting Ltr 0.600 4,700.00 2,820.00
Besi beton polos Kg 210.000 10,300.00 2,163,000.00
Kawat beton Kg 3.000 15,000.00 45,000.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
JUMLAH HARGA BAHAN 3,933,563.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,525,390.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 4,525,390.50
4.1.1.30 Pembuatan 1 m3 kolom beton bertulang (300 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 7.050 55,000.00 387,750.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.650 71,500.00 117,975.00
Tukang besi L.02 OH 2.100 71,500.00 150,150.00
Kepala tukang L.03 OH 0.403 77,000.00 31,031.00
Mandor L.04 OH 0.353 88,000.00 31,064.00
JUMLAH TENAGA KERJA 737,632.50
B. BAHAN
Kayu kelas III m3 0.400 3,575,000.00 1,430,000.00
Paku 5 - 12 cm Kg 4.000 14,500.00 58,000.00
Minyak bekisting Ltr 2.000 4,700.00 9,400.00
Besi beton polos Kg 315.000 10,300.00 3,244,500.00
Kawat beton Kg 4.500 15,000.00 67,500.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
Kayu kelas II (balok) m3 0.150 8,000,000.00 1,200,000.00
Plywood 9 mm Lbr 3.500 137,200.00 480,200.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 20.000 22,000.00 440,000.00
JUMLAH HARGA BAHAN 7,658,093.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 8,395,725.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 8,395,725.50
4.1.1.31 Pembuatan 1 m3 balok beton bertulang (200 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 6.350 55,000.00 349,250.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.650 71,500.00 117,975.00
Tukang besi L.02 OH 1.400 71,500.00 100,100.00
Kepala tukang L.03 OH 0.333 77,000.00 25,641.00
Mandor L.04 OH 0.318 88,000.00 27,984.00
JUMLAH TENAGA KERJA 640,612.50
B. BAHAN
Kayu kelas III m3 0.320 3,575,000.00 1,144,000.00
Paku 5 - 12 cm Kg 3.200 14,500.00 46,400.00
Minyak bekisting Ltr 1.600 4,700.00 7,520.00
Besi beton polos Kg 210.000 10,300.00 2,163,000.00
Kawat beton Kg 3.000 15,000.00 45,000.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
Kayu kelas II (balok) m3 0.140 8,000,000.00 1,120,000.00
Plywood 9 mm Lbr 2.800 137,200.00 384,160.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 16.000 22,000.00 352,000.00
JUMLAH HARGA BAHAN 5,990,573.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 6,631,185.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 6,631,185.50
4.1.1.32 Pembuatan 1 m3 plat beton bertulang (150 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 5.300 55,000.00 291,500.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.300 71,500.00 92,950.00
Tukang besi L.02 OH 1.050 71,500.00 75,075.00
Kepala tukang L.03 OH 0.265 77,000.00 20,405.00
Mandor L.04 OH 0.265 88,000.00 23,320.00
JUMLAH TENAGA KERJA 522,912.50
B. BAHAN
Kayu kelas III m3 0.320 3,575,000.00 1,144,000.00
Paku 5 - 12 cm Kg 3.200 14,500.00 46,400.00
Minyak bekisting Ltr 1.600 4,700.00 7,520.00
Besi beton polos Kg 157.500 10,300.00 1,622,250.00
Kawat beton Kg 2.250 15,000.00 33,750.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
Kayu kelas II (balok) m3 0.120 8,000,000.00 960,000.00
Plywood 9 mm Lbr 2.800 137,200.00 384,160.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 32.000 22,000.00 704,000.00
JUMLAH HARGA BAHAN 5,630,573.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 6,153,485.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 6,153,485.50
4.1.1.33 Pembuatan 1 m3 dinding beton bertulang (150 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 5.300 55,000.00 291,500.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.300 71,500.00 92,950.00
Tukang besi L.02 OH 1.050 71,500.00 75,075.00
Kepala tukang L.03 OH 0.262 77,000.00 20,174.00
Mandor L.04 OH 0.265 88,000.00 23,320.00
JUMLAH TENAGA KERJA 522,681.50
B. BAHAN
Kayu kelas III m3 0.240 3,575,000.00 858,000.00
Paku 5 - 12 cm Kg 3.200 14,500.00 46,400.00
Minyak bekisting Ltr 1.600 4,700.00 7,520.00
Besi beton polos Kg 157.500 10,300.00 1,622,250.00
Kawat beton Kg 2.250 15,000.00 33,750.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
Kayu kelas II (balok) m3 0.160 8,000,000.00 1,280,000.00
Plywood 9 mm Lbr 2.800 137,200.00 384,160.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 24.000 22,000.00 528,000.00
JUMLAH HARGA BAHAN 5,488,573.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 6,011,254.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 6,011,254.50
4.1.1.34 Pembuatan 1 m3 dinding beton bertulang 200 kg besi + bekisting)
A. TENAGA
Pekerja L.01 OH 5.650 55,000.00 310,750.00
Tukang batu L.02 OH 0.275 71,500.00 19,662.50
Tukang kayu L.02 OH 1.560 71,500.00 111,540.00
Tukang besi L.02 OH 1.400 71,500.00 100,100.00
Kepala tukang L.03 OH 0.323 77,000.00 24,871.00
Mandor L.04 OH 0.283 88,000.00 24,904.00
JUMLAH TENAGA KERJA 591,827.50
B. BAHAN
Kayu kelas III m3 0.250 3,575,000.00 893,750.00
Paku 5 - 12 cm Kg 3.000 14,500.00 43,500.00
Minyak bekisting Ltr 1.200 4,700.00 5,640.00
Besi beton polos Kg 210.000 10,300.00 2,163,000.00
Kawat beton Kg 3.000 15,000.00 45,000.00
Semen Portland Kg 336.000 1,400.00 470,400.00
Pasir beton m3 0.540 200,000.00 108,000.00
Kerikil m3 0.810 185,300.00 150,093.00
Kayu kelas II (balok) m3 0.105 8,000,000.00 840,000.00
Plywood 9 mm Lbr 2.500 137,200.00 343,000.00
Dolken kayu galam, Ø (8-10) cm, pjg 4 m Btg 14.000 22,000.00 308,000.00
JUMLAH HARGA BAHAN 5,370,383.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,962,210.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 5,962,210.50
4.1.1.35 Pembuatan 1 m3 kolom praktis beton bertulang (11 x 11) cm
A. TENAGA
Pekerja L.01 OH 0.180 55,000.00 9,900.00
Tukang batu L.02 OH 0.020 71,500.00 1,430.00
Tukang kayu L.02 OH 0.020 71,500.00 1,430.00
Tukang besi L.02 OH 0.020 71,500.00 1,430.00
Kepala tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.009 88,000.00 792.00
JUMLAH TENAGA KERJA 15,444.00
B. BAHAN
Kayu kelas III m3 0.002 3,575,000.00 7,150.00
Paku 5 - 12 cm Kg 0.010 14,500.00 145.00
Besi beton polos Kg 3.000 10,300.00 30,900.00
Kawat beton Kg 0.450 15,000.00 6,750.00
Semen Portland Kg 4.000 1,400.00 5,600.00
Pasir beton m3 0.006 200,000.00 1,200.00
Kerikil m3 0.009 185,300.00 1,667.70
JUMLAH HARGA BAHAN 53,412.70
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 68,856.70
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 68,856.70
4.1.1.36 Pembuatan 1 m3 ring balok beton bertulang (10 x 15) cm
A. TENAGA
Pekerja L.01 OH 0.297 55,000.00 16,335.00
Tukang batu L.02 OH 0.033 71,500.00 2,359.50
Tukang kayu L.02 OH 0.033 71,500.00 2,359.50
Tukang besi L.02 OH 0.033 71,500.00 2,359.50
Kepala tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,503.50
B. BAHAN
Kayu kelas III m3 0.003 3,575,000.00 10,725.00
Paku 5 - 12 cm Kg 0.020 14,500.00 290.00
Besi beton polos Kg 3.600 10,300.00 37,080.00
Kawat beton Kg 0.050 15,000.00 750.00
Semen Portland Kg 5.500 1,400.00 7,700.00
Pasir beton m3 0.009 200,000.00 1,800.00
Kerikil m3 0.015 185,300.00 2,779.50
JUMLAH HARGA BAHAN 61,124.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 86,628.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 86,628.00

4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.2.1.1 Pemasangan 1 kg besi profil
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Las Konstruksi L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 8,316.00
B. BAHAN
Besi profil Kg 1.150 13,200.00 15,180.00
JUMLAH HARGA BAHAN 15,180.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 23,496.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 23,496.00
4.2.1.2
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Las Konstruksi L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 8,316.00
B. BAHAN
Besi Baja IWF Kg 1.150 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 8,316.00
E. Overhead & Profit (15%) 15% x D 1,247.40
F. Harga Satuan Pekerjaan (D+E) 9,563.40
4.2.1.3 Pengerjaan 100 kg pekerjaan perakitan
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Besi Konstruksi L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.001 77,000.00 77.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,167.00
B. BAHAN
Solar Ltr 1.000 11,500.00 11,500.00
Minyak pelumas Ltr 0.100 27,500.00 2,750.00
JUMLAH HARGA BAHAN 14,250.00
C. PERALATAN
Sewa Alat Jam 0.800 - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 27,417.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 27,417.00
4.2.1.4 Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
A. TENAGA
Pekerja L.01 OH 1.050 55,000.00 57,750.00
Tukang Las Biasa L.02 OH 1.050 71,500.00 75,075.00
Kepala Tukang L.03 OH 0.105 77,000.00 8,085.00
Mandor L.04 OH 0.052 88,000.00 4,576.00
JUMLAH TENAGA KERJA 145,486.00
B. BAHAN
Besi siku L 30.30.3 Kg 15.000 5,600.00 84,000.00
Besi plat baja Kg 32.800 10,800.00 354,240.00
Kawat las Kg 0.050 36,500.00 1,825.00
JUMLAH HARGA BAHAN 438,240.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 583,726.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 583,726.00
4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik
A. TENAGA
Pekerja L.01 OH 0.040 55,000.00 2,200.00
Tukang Las Konstruksi L.02 OH 0.020 71,500.00 1,430.00
Kepala Tukang L.03 OH 0.002 77,000.00 154.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 3,960.00
B. BAHAN
Kawat las listrik Kg 0.400 36,500.00 14,600.00
Solar Ltr 0.300 11,500.00 3,450.00
Minyak pelumas Ltr 0.040 27,500.00 1,100.00
JUMLAH HARGA BAHAN 18,050.00
C. PERALATAN
Sewa Alat Jam 0.170 - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 22,010.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 22,010.00
4.2.1.6 Pembuatan 1 m2 rangka jendela besi scuare tube (25 x 5) cm
A. TENAGA
Pekerja L.01 OH 0.650 55,000.00 35,750.00
Tukang Las Biasa L.02 OH 0.650 71,500.00 46,475.00
Kepala Tukang L.03 OH 0.065 77,000.00 5,005.00
Mandor L.04 OH 0.032 88,000.00 2,816.00
JUMLAH TENAGA KERJA 90,046.00
B. BAHAN
Besi scuare tube m' 4.760 6,000.00 28,560.00
Besi lis kaca (1 x 1) cm m' 4.522 - -
Pengelasan cm 20.000 2,201.00 44,020.00
JUMLAH HARGA BAHAN 28,560.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 118,606.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 118,606.00
4.2.1.7 Pemasangan 1 m2 pintu rolling door besi
A. TENAGA
Pekerja L.01 OH 1.200 55,000.00 66,000.00
Tukang Las Biasa L.02 OH 1.200 71,500.00 85,800.00
Kepala Tukang L.03 OH 0.120 77,000.00 9,240.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 161,568.00
B. BAHAN
Pintu Gulung Besi m2 1.000 363,000.00 363,000.00
JUMLAH HARGA BAHAN 363,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 524,568.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 524,568.00
4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC
A. TENAGA
Pekerja L.01 OH 0.440 55,000.00 24,200.00
Tukang L.02 OH 0.440 71,500.00 31,460.00
Kepala Tukang L.03 OH 0.044 77,000.00 3,388.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 60,984.00
B. BAHAN
Pintu Lipat m2 1.000 410,000.00 410,000.00
JUMLAH HARGA BAHAN 410,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 470,984.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 470,984.00
4.2.1.9 Pemasangan 1 m2 sunscreen alumunium
A. TENAGA
Pekerja L.01 OH 0.080 55,000.00 4,400.00
Tukang L.02 OH 0.800 71,500.00 57,200.00
Kepala Tukang L.03 OH 0.080 77,000.00 6,160.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 68,112.00
B. BAHAN
Sunscreen alumunium m2 1.000 385,000.00 385,000.00
JUMLAH HARGA BAHAN 385,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 453,112.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 453,112.00
4.2.1.10 Pemasangan 1 m2 rolling door alumunium
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Khusus Alumunium L.02 OH 1.000 71,500.00 71,500.00
Kepala Tukang L.03 OH 0.100 77,000.00 7,700.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 138,600.00
B. BAHAN
Rolling Door Alumunium m2 1.000 423,500.00 423,500.00
JUMLAH HARGA BAHAN 423,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 562,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 562,100.00
4.2.1.11 Pemasangan 1 m' kusen pintu alumunium
A. TENAGA
Pekerja L.01 OH 0.043 55,000.00 2,365.00
Tukang Khusus Alumunium L.02 OH 0.043 71,500.00 3,074.50
Kepala Tukang L.03 OH 0.0043 77,000.00 331.10
Mandor L.04 OH 0.0021 88,000.00 184.80
JUMLAH TENAGA KERJA 5,955.40
B. BAHAN
Profil alluminium m' 1.100 22,000.00 24,200.00
Skrup fixer Bh 2.000 900.00 1,800.00
Sealant Tube 0.060 28,000.00 1,680.00
JUMLAH HARGA BAHAN 27,680.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 33,635.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 33,635.40
4.2.1.12 Pemasangan 1 m2 pintu alumunium strip lebar 8 cm
A. TENAGA
Pekerja L.01 OH 0.085 55,000.00 4,675.00
Tukang Khusus Alumunium L.02 OH 0.085 71,500.00 6,077.50
Kepala Tukang L.03 OH 0.0085 77,000.00 654.50
Mandor L.04 OH 0.0042 88,000.00 369.60
JUMLAH TENAGA KERJA 11,776.60
B. BAHAN
Profil alluminium m' 4.400 22,000.00 96,800.00
Alumunium Strip m' 14.600 42,000.00 613,200.00
JUMLAH HARGA BAHAN 710,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 721,776.60
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 721,776.60
4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alumunium
A. TENAGA
Pekerja L.01 OH 0.085 55,000.00 4,675.00
Tukang Alumunium/Kaca L.02 OH 0.085 71,500.00 6,077.50
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 11,885.50
B. BAHAN
Pintu alluminium m' 4.400 302,500.00 1,331,000.00
Profil kaca m' 4.500 8,200.00 36,900.00
Sealant Tube 0.270 28,000.00 7,560.00
JUMLAH HARGA BAHAN 1,375,460.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,387,345.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,387,345.50
4.2.1.14 Pemasangan 1 m2 Venetions blinds dan Vertical blinds
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 48,554.00
B. BAHAN
Venetions blinds dan Vertical blinds m2 1.000 278,300.00 278,300.00
JUMLAH HARGA BAHAN 278,300.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 326,854.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 326,854.00
4.2.1.15 Pemasangan 1 m2 terali besi strip (2 x 3) mm
A. TENAGA
Pekerja L.01 OH 1.670 55,000.00 91,850.00
Tukang L.02 OH 1.670 71,500.00 119,405.00
Kepala Tukang L.03 OH 0.167 77,000.00 12,859.00
Mandor L.04 OH 0.083 88,000.00 7,304.00
JUMLAH TENAGA KERJA 231,418.00
B. BAHAN
Besi strip Kg 6.177 15,000.00 92,655.00
Pengelasan cm 27.080 2,201.00 59,603.08
JUMLAH HARGA BAHAN 152,258.08
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 383,676.08
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 383,676.08
4.2.1.16 Pemasangan 1 m2 kawat nyamuk
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Kawat nyamuk m2 1.100 49,500.00 54,450.00
Pengelasan cm 11.11 2,201.00 24,453.11
Baja strip (0,2 x 2) cm Kg 1.716 - -
JUMLAH HARGA BAHAN 78,903.11
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 92,763.11
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 92,763.11
4.2.1.17 Pemasangan 1 m2 jendela nako dan teralis
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.001 88,000.00 88.00
JUMLAH TENAGA KERJA 26,928.00
B. BAHAN
Jendela nako (rangka + kaca 5 mm) m2 1.100 57,200.00 62,920.00
Paku skrup 1 - 2.5 cm Bh 10.000 - -
Besi strip m' 7.000 15,000.00 105,000.00
JUMLAH HARGA BAHAN 167,920.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 194,848.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 194,848.00
4.2.1.18 Pemasangan 1 m' talang datar/ jurai seng bjls 28 lebar 90 cm
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang L.02 OH 0.400 71,500.00 28,600.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 42,405.00
B. BAHAN
Seng plat m' 1.050 23,900.00 25,095.00
Paku 1 - 2.5 cm Kg 0.015 14,500.00 217.50
Papan kayu kelas II atau III m3 0.019 6,250,000.00 118,750.00
JUMLAH HARGA BAHAN 144,062.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 186,467.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 186,467.50
4.2.1.19 Pemasangan 1 m' talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.030 77,000.00 2,310.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 32,714.00
B. BAHAN
Seng plat m' 1.050 23,900.00 25,095.00
Paku 1 - 2.5 cm Kg 0.010 14,500.00 145.00
Besi Strip m3 0.500 15,000.00 7,500.00
JUMLAH HARGA BAHAN 32,740.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,454.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 65,454.00
4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1 x 40.40.2 mm, modul 60 x 120 cm, dinding partisi
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Besi L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 34,694.00
B. BAHAN
Rangka metal hollow 40.40.2 mm m' 3.500 19,875.00 69,562.50
Accesoris (perkuatan las dll) 100% x rangkaLs 1.000 19,875.00 19,875.00
JUMLAH HARGA BAHAN 89,437.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 124,131.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 124,131.50
4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1 x 40.40.2 mm, modul 60 x 60 cm, plafon
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang Besi L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 48,554.00
B. BAHAN
Rangka metal hollow 40.40.2 mm m' 4.000 19,875.00 79,500.00
Accesoris (perkuatan las dll) 100% x rangkaLs 1.000 19,875.00 19,875.00
JUMLAH HARGA BAHAN 99,375.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 147,929.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 147,929.00

4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.4.1.1 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1 bata, campuran 1PC : 2PP
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Bata merah m2 140.000 750.00 105,000.00
Semen Portland Kg 43.500 1,400.00 60,900.00
Pasir Pasang m3 0.080 132,000.00 10,560.00
JUMLAH HARGA BAHAN 176,460.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 227,940.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 227,940.00
4.4.1.2 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1 bata, campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Bata merah m2 140.000 750.00 105,000.00
Semen Portland Kg 32.950 1,400.00 46,130.00
Pasir Pasang m3 0.091 132,000.00 12,012.00
JUMLAH HARGA BAHAN 163,142.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 214,622.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 214,622.00
4.4.1.3 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1 bata, campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Bata merah m2 140.000 750.00 105,000.00
Semen Portland Kg 26.550 1,400.00 37,170.00
Pasir Pasang m3 0.093 132,000.00 12,276.00
JUMLAH HARGA BAHAN 154,446.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 205,926.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 205,926.00
4.4.1.4 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1 bata, campuran 1PC : 5PP
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Bata merah m2 140.000 750.00 105,000.00
Semen Portland Kg 22.200 1,400.00 31,080.00
Pasir Pasang m3 0.102 132,000.00 13,464.00
JUMLAH HARGA BAHAN 149,544.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 201,024.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 201,024.00
4.4.1.5 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1 bata, campuran 1PC : 6PP
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Bata merah m2 140.000 750.00 105,000.00
Semen Portland Kg 18.500 1,400.00 25,900.00
Pasir Pasang m3 0.122 132,000.00 16,104.00
JUMLAH HARGA BAHAN 147,004.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 198,484.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 198,484.00
4.4.1.6 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1 bata, campuran 1PC : 3KP : 10PP
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 51,480.00
B. BAHAN
Bata merah m2 140.000 750.00 105,000.00
Semen Portland Kg 10.800 1,400.00 15,120.00
Pasir Pasang m3 0.0925 132,000.00 12,210.00
Kapur Padam m3 0.0275 280,000.00 7,700.00
JUMLAH HARGA BAHAN 140,030.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 191,510.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 191,510.00
4.4.1.7 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 2PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 18.950 1,400.00 26,530.00
Pasir Pasang m3 0.038 132,000.00 5,016.00
JUMLAH HARGA BAHAN 84,046.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 109,786.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 109,786.00
4.4.1.8 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 14.370 1,400.00 20,118.00
Pasir Pasang m3 0.040 132,000.00 5,280.00
JUMLAH HARGA BAHAN 77,898.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 103,638.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 103,638.00
4.4.1.9 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 11.500 1,400.00 16,100.00
Pasir Pasang m3 0.043 132,000.00 5,676.00
JUMLAH HARGA BAHAN 74,276.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 100,016.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 100,016.00
4.4.1.10 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 5PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 9.680 1,400.00 13,552.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
JUMLAH HARGA BAHAN 71,992.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 97,732.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 97,732.00
4.4.1.11 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 6PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 8.320 1,400.00 11,648.00
Pasir Pasang m3 0.049 132,000.00 6,468.00
JUMLAH HARGA BAHAN 70,616.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 96,356.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 96,356.00
4.4.1.12 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 8PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 6.500 1,400.00 9,100.00
Pasir Pasang m3 0.050 132,000.00 6,600.00
JUMLAH HARGA BAHAN 68,200.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 93,940.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 93,940.00
4.4.1.13 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1PC : 3KP : 10PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 750.00 52,500.00
Semen Portland Kg 4.500 1,400.00 6,300.00
Pasir Pasang m3 0.0500 132,000.00 6,600.00
Kapur Padam m3 0.0150 280,000.00 4,200.00
JUMLAH HARGA BAHAN 69,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 95,340.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 95,340.00
4.4.1.14 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1SM : 1KP : 1PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 1,400.00 98,000.00
Semen Merah Kg 0.018 105,000.00 1,890.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Kapur Padam m3 0.018 280,000.00 5,040.00
JUMLAH HARGA BAHAN 107,306.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 133,046.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 133,046.00
4.4.1.15 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 bata, campuran 1SM : 1KP : 2PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Bata merah m2 70.000 1,400.00 98,000.00
Semen Merah Kg 0.014 105,000.00 1,470.00
Pasir Pasang m3 0.014 132,000.00 1,848.00
Kapur Padam m3 0.018 280,000.00 5,040.00
JUMLAH HARGA BAHAN 106,358.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 132,098.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 132,098.00
4.4.1.16 Pemasangan 1 m2 dinding conblock HB20 campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 32,714.00
B. BAHAN
HB 20 m2 12.500 14,300.00 178,750.00
Semen Portland Kg 30.320 1,400.00 42,448.00
Pasir Pasang m3 0.728 132,000.00 96,096.00
Besi angkur φ = 8 mm Kg 0.280 17,500.00 4,900.00
JUMLAH HARGA BAHAN 322,194.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 354,908.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 354,908.00
4.4.1.17 Pemasangan 1 m2 dinding conblock HB20 campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 32,714.00
B. BAHAN
HB 20 m2 12.500 14,300.00 178,750.00
Semen Portland Kg 24.260 1,400.00 33,964.00
Pasir Pasang m3 0.772 132,000.00 101,904.00
Besi angkur φ = 8 mm Kg 0.280 17,500.00 4,900.00
JUMLAH HARGA BAHAN 319,518.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 352,232.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 352,232.00
4.4.1.18 Pemasangan 1 m2 dinding conblock HB15 campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.320 55,000.00 17,600.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.016 88,000.00 1,408.00
JUMLAH TENAGA KERJA 28,512.00
B. BAHAN
HB 15 m2 12.500 11,000.00 137,500.00
Semen Portland Kg 22.740 1,400.00 31,836.00
Pasir Pasang m3 0.550 132,000.00 72,600.00
Besi angkur φ = 8 mm Kg 0.280 17,500.00 4,900.00
JUMLAH HARGA BAHAN 246,836.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 275,348.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 275,348.00
4.4.1.19 Pemasangan 1 m2 dinding conblock HB15 campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 0.320 55,000.00 17,600.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.016 88,000.00 1,408.00
JUMLAH TENAGA KERJA 28,512.00
B. BAHAN
HB 15 m2 12.500 11,000.00 137,500.00
Semen Portland Kg 18.200 1,400.00 25,480.00
Pasir Pasang m3 0.582 132,000.00 76,824.00
Besi angkur φ = 8 mm Kg 0.280 17,500.00 4,900.00
JUMLAH HARGA BAHAN 244,704.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 273,216.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 273,216.00
4.4.1.20 Pemasangan 1 m2 dinding conblock HB10 campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
HB 10 m2 12.500 8,800.00 110,000.00
Semen Portland Kg 15.160 1,400.00 21,224.00
Pasir Pasang m3 0.364 132,000.00 48,048.00
Besi angkur φ = 8 mm Kg 0.280 17,500.00 4,900.00
JUMLAH HARGA BAHAN 184,172.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 209,912.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 209,912.00
4.4.1.21 Pemasangan 1 m2 dinding conblock HB10 campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
HB 10 m2 12.500 8,800.00 110,000.00
Semen Portland Kg 12.130 1,400.00 16,982.00
Pasir Pasang m3 0.388 132,000.00 51,216.00
Besi angkur φ = 8 mm Kg 0.280 17,500.00 4,900.00
JUMLAH HARGA BAHAN 183,098.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 208,838.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 208,838.00
4.4.1.22 Pemasangan 1 m2 dinding terawang (rooster) 12 x 11 x 24 campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Batu rooster m2 30.000 9,900.00 297,000.00
Semen Portland Kg 14.000 1,400.00 19,600.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
JUMLAH HARGA BAHAN 320,824.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 346,564.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 346,564.00
4.4.1.23 Pemasangan 1 m2 dinding terawang (rooster) 12 x 11 x 24 campuran 1PC : 4PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Batu rooster m2 30.000 9,900.00 297,000.00
Semen Portland Kg 11.000 1,400.00 15,400.00
Pasir Pasang m3 0.035 132,000.00 4,620.00
JUMLAH HARGA BAHAN 317,020.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 342,760.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 342,760.00
4.4.1.24 Pemasangan 1 m2 dinding bata berongga ekspose 5 x 11 x 24 campuran 1PC : 3PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Bata berongga ekspose m2 70.000 2,000.00 140,000.00
Semen Portland Kg 14.000 1,400.00 19,600.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
JUMLAH HARGA BAHAN 163,824.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 193,524.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 193,524.00

4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.4.2.1 Pemasangan 1 m2 plesteran 1PC : 1PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 15.504 1,400.00 21,705.60
Pasir Pasang m3 0.016 132,000.00 2,112.00
JUMLAH HARGA BAHAN 23,817.60
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 53,517.60
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 53,517.60
4.4.2.2 Pemasangan 1 m2 plesteran 1PC : 2PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 10.224 1,400.00 14,313.60
Pasir Pasang m3 0.020 132,000.00 2,640.00
JUMLAH HARGA BAHAN 16,953.60
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 46,653.60
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 46,653.60
4.4.2.3 Pemasangan 1 m2 plesteran 1PC : 3PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 7.776 1,400.00 10,886.40
Pasir Pasang m3 0.023 132,000.00 3,036.00
JUMLAH HARGA BAHAN 13,922.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 43,622.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 43,622.40
4.4.2.4 Pemasangan 1 m2 plesteran 1PC : 4PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 6.240 1,400.00 8,736.00
Pasir Pasang m3 0.024 132,000.00 3,168.00
JUMLAH HARGA BAHAN 11,904.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 41,604.00
E. Overhead & Profit (15%) 15% x D
F. Harga Satuan Pekerjaan (D+E) 41,604.00
4.4.2.5 Pemasangan 1 m2 plesteran 1PC : 5PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 5.184 1,400.00 7,257.60
Pasir Pasang m3 0.026 132,000.00 3,432.00
JUMLAH HARGA BAHAN 10,689.60
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 40,389.60
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 40,389.60
4.4.2.6 Pemasangan 1 m2 plesteran 1PC : 6PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 4.416 1,400.00 6,182.40
Pasir Pasang m3 0.027 132,000.00 3,564.00
JUMLAH HARGA BAHAN 9,746.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,446.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 39,446.40
4.4.2.7 Pemasangan 1 m2 plesteran 1PC : 7PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 3.936 1,400.00 5,510.40
Pasir Pasang m3 0.028 132,000.00 3,696.00
JUMLAH HARGA BAHAN 9,206.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 38,906.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 38,906.40
4.4.2.8 Pemasangan 1 m2 plesteran 1PC : 8PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 3.456 1,400.00 4,838.40
Pasir Pasang m3 0.029 132,000.00 3,828.00
JUMLAH HARGA BAHAN 8,666.40
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 38,366.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 38,366.40
4.4.2.9 Pemasangan 1 m2 plesteran 1PC : ⅟2KP : 3PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.360 55,000.00 19,800.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 30,888.00
B. BAHAN
Semen Portland Kg 5.760 1,400.00 8,064.00
Pasir Pasang m3 0.013 132,000.00 1,716.00
Kapur Padam m3 0.003 280,000.00 840.00
JUMLAH HARGA BAHAN 10,620.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 41,508.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 41,508.00
4.4.2.10 Pemasangan 1 m2 plesteran 1PC : 2KP : 8PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.360 55,000.00 19,800.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 30,888.00
B. BAHAN
Semen Portland Kg 3.000 1,400.00 4,200.00
Pasir Pasang m3 0.020 132,000.00 2,640.00
Kapur Padam m3 0.005 280,000.00 1,400.00
JUMLAH HARGA BAHAN 8,240.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,128.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 39,128.00
4.4.2.11 Pemasangan 1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.360 55,000.00 19,800.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 30,888.00
B. BAHAN
Semen Merah m3 0.009 105,000.00 945.00
Pasir Pasang m3 0.009 132,000.00 1,188.00
Kapur Padam m3 0.009 280,000.00 2,520.00
JUMLAH HARGA BAHAN 4,653.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 35,541.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 35,541.00
4.4.2.12 Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.360 55,000.00 19,800.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 30,888.00
B. BAHAN
Semen Merah m3 0.007 105,000.00 735.00
Pasir Pasang m3 0.015 132,000.00 1,980.00
Kapur Padam m3 0.007 280,000.00 1,960.00
JUMLAH HARGA BAHAN 4,675.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 35,563.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 35,563.00
4.4.2.13 Pemasangan 1 m2 plesteran 1PC : 1PP tebal 20 mm
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 39,776.00
B. BAHAN
Semen Portland Kg 13.632 1,400.00 19,084.80
Pasir Pasang m3 0.027 132,000.00 3,564.00
JUMLAH HARGA BAHAN 22,648.80
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 62,424.80
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 62,424.80
4.4.2.14 Pemasangan 1 m2 plesteran 1PC : 3PP tebal 20 mm
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 39,776.00
B. BAHAN
Semen Portland Kg 10.368 1,400.00 14,515.20
Pasir Pasang m3 0.031 132,000.00 4,092.00
JUMLAH HARGA BAHAN 18,607.20
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 58,383.20
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 58,383.20
4.4.2.15 Pemasangan 1 m2 plesteran 1PC : 4PP tebal 20 mm
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 39,776.00
B. BAHAN
Semen Portland Kg 8.320 1,400.00 11,648.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
JUMLAH HARGA BAHAN 15,872.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 55,648.00
E. Overhead & Profit (15%) 15% x D
F. Harga Satuan Pekerjaan (D+E) 55,648.00
4.4.2.16 Pemasangan 1 m2 plesteran 1PC : 5PP tebal 20 mm
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 39,776.00
B. BAHAN
Semen Portland Kg 6.912 1,400.00 9,676.80
Pasir Pasang m3 0.035 132,000.00 4,620.00
JUMLAH HARGA BAHAN 14,296.80
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 54,072.80
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 54,072.80
4.4.2.17 Pemasangan 1 m2 plesteran 1PC : 6PP tebal 20 mm
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Batu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 39,776.00
B. BAHAN
Semen Portland Kg 5.888 1,400.00 8,243.20
Pasir Pasang m3 0.036 132,000.00 4,752.00
JUMLAH HARGA BAHAN 12,995.20
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 52,771.20
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 52,771.20
4.4.2.18 Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 20 mm
A. TENAGA
Pekerja L.01 OH 0.440 55,000.00 24,200.00
Tukang Batu L.02 OH 0.220 71,500.00 15,730.00
Kepala Tukang L.03 OH 0.022 77,000.00 1,694.00
Mandor L.04 OH 0.022 88,000.00 1,936.00
JUMLAH TENAGA KERJA 43,560.00
B. BAHAN
Semen Merah m3 0.009 105,000.00 945.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Kapur Padam m3 0.009 280,000.00 2,520.00
JUMLAH HARGA BAHAN 5,841.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 49,401.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 49,401.00
4.4.2.19 Pemasangan 1 m2 berapen 1PC : 5PP tebal 15 mm
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Batu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 14,932.50
B. BAHAN
Semen Portland Kg 5.184 1,400.00 7,257.60
Pasir Pasang m3 0.026 132,000.00 3,432.00
JUMLAH HARGA BAHAN 10,689.60
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 25,622.10
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 25,622.10
4.4.2.20 Pemasangan 1 m2 plesteran skoning 1PC : 3PP tebal 10 mm
A. TENAGA
Pekerja L.01 OH 0.080 55,000.00 4,400.00
Tukang Batu L.02 OH 0.400 71,500.00 28,600.00
Kepala Tukang L.03 OH 0.040 77,000.00 3,080.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 36,432.00
B. BAHAN
Semen Portland Kg 0.500 1,400.00 700.00
Pasir Pasang m3 0.013 132,000.00 1,716.00
JUMLAH HARGA BAHAN 2,416.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 38,848.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 38,848.00
4.4.2.21 Pemasangan 1 m2 plesteran granit 1PC : 2granit tebal 1 cm
A. TENAGA
Pekerja L.01 OH 0.450 55,000.00 24,750.00
Tukang Batu L.02 OH 0.225 71,500.00 16,087.50
Kepala Tukang L.03 OH 0.023 77,000.00 1,771.00
Mandor L.04 OH 0.023 88,000.00 2,024.00
JUMLAH TENAGA KERJA 44,632.50
B. BAHAN
Semen Portland Kg 10.000 1,400.00 14,000.00
Batu Granit Kg 15.000 3,800.00 57,000.00
JUMLAH HARGA BAHAN 71,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 115,632.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 115,632.50
4.4.2.22 Pemasangan 1 m2 plesteran teraso 1PC : 2 teraso tebal 1 cm
A. TENAGA
Pekerja L.01 OH 0.450 55,000.00 24,750.00
Tukang Batu L.02 OH 0.225 71,500.00 16,087.50
Kepala Tukang L.03 OH 0.023 77,000.00 1,771.00
Mandor L.04 OH 0.023 88,000.00 2,024.00
JUMLAH TENAGA KERJA 44,632.50
B. BAHAN
Semen Portland Kg 10.000 1,400.00 14,000.00
Batu Teraso Kg 15.000 5,500.00 82,500.00
JUMLAH HARGA BAHAN 96,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 141,132.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 141,132.50
4.4.2.23 Pemasangan 1 m2 plesteran ciprat 1PC : 2PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Semen Portland Kg 4.320 1,400.00 6,048.00
Pasir Pasang m3 0.006 132,000.00 792.00
JUMLAH HARGA BAHAN 6,840.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 32,580.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 32,580.00
4.4.2.24 Pemasangan 1 m2 finishing siar pasangan bata merah
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Batu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 14,932.50
B. BAHAN
Semen Portland Kg 3.108 1,400.00 4,351.20
JUMLAH HARGA BAHAN 4,351.20
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 19,283.70
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 19,283.70
4.4.2.25 Pemasangan 1 m2 finishing siar pasangan conblock ekspose
A. TENAGA
Pekerja L.01 OH 0.070 55,000.00 3,850.00
Tukang Batu L.02 OH 0.035 71,500.00 2,502.50
Kepala Tukang L.03 OH 0.004 77,000.00 308.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 7,012.50
B. BAHAN
Semen Portland Kg 1.600 1,400.00 2,240.00
JUMLAH HARGA BAHAN 2,240.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 9,252.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 9,252.50
4.4.2.26 Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1PC : 2PP
A. TENAGA
Pekerja L.01 OH 0.300 55,000.00 16,500.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 29,700.00
B. BAHAN
Semen Portland Kg 6.340 1,400.00 8,876.00
Pasir Pasang m3 0.012 132,000.00 1,584.00
JUMLAH HARGA BAHAN 10,460.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 40,160.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 40,160.00
4.4.2.27 Pemasangan 1 m2 acian
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Batu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 19,800.00
B. BAHAN
Semen Portland Kg 3.250 1,400.00 4,550.00
JUMLAH HARGA BAHAN 4,550.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 24,350.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 24,350.00
4.4.2.28 Pemasangan 1 m benangan dan kol-kolan
A. TENAGA
Pekerja L.01 OH 0.200 - -
Tukang Batu L.02 OH 0.120 55,000.00 6,600.00
Kepala Tukang L.03 OH 0.010 - -
Mandor L.04 OH 0.010 - -
JUMLAH TENAGA KERJA 6,600.00
B. BAHAN
Semen Portland Kg 0.130 1,400.00 182.00
Pasir m3 0.009 132,000.00 1,188.00
JUMLAH HARGA BAHAN 1,370.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 7,970.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 7,970.00

4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.4.3.1 Pemasangan 1 m2 Iantai ubin PC abu-abu ukuran 40 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Batu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 24,832.50
B. BAHAN
Ubin abu-abu 40 x 40 cm Bh 6.630 5,500.00 36,465.00
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
JUMLAH HARGA BAHAN 56,125.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 80,957.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 80,957.50
4.4.3.2 Pemasangan 1 m2 Iantai ubin PC abu-abu ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.260 55,000.00 14,300.00
Tukang Batu L.02 OH 0.130 71,500.00 9,295.00
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Ubin abu-abu 30 x 30 cm Bh 11.870 2,900.00 34,423.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
JUMLAH HARGA BAHAN 54,363.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 80,103.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 80,103.00
4.4.3.3 Pemasangan 1 m2 Iantai ubin PC abu-abu ukuran 20 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.270 55,000.00 14,850.00
Tukang Batu L.02 OH 0.135 71,500.00 9,652.50
Kepala Tukang L.03 OH 0.014 77,000.00 1,078.00
Mandor L.04 OH 0.014 88,000.00 1,232.00
JUMLAH TENAGA KERJA 26,812.50
B. BAHAN
Ubin abu-abu 20 x 20 cm Bh 26.500 1,100.00 29,150.00
Semen Portland Kg 10.400 1,400.00 14,560.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
JUMLAH HARGA BAHAN 49,650.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 76,462.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 76,462.50
4.4.3.4 Pemasangan 1 m2 Iantai ubin warna ukuran 40 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Batu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 24,832.50
B. BAHAN
Ubin warna 40 x 40 cm Bh 6.630 4,900.00 32,487.00
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.300 11,000.00 14,300.00
JUMLAH HARGA BAHAN 66,447.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 91,279.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 91,279.50
4.4.3.5 Pemasangan 1 m2 Iantai ubin warna ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.260 55,000.00 14,300.00
Tukang Batu L.02 OH 0.130 71,500.00 9,295.00
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Ubin warna 30 x 30 cm Bh 11.870 3,300.00 39,171.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 75,611.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 101,351.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 101,351.00
4.4.3.6 Pemasangan 1 m2 Iantai ubin warna ukuran 20 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.270 55,000.00 14,850.00
Tukang Batu L.02 OH 0.135 71,500.00 9,652.50
Kepala Tukang L.03 OH 0.014 77,000.00 1,078.00
Mandor L.04 OH 0.014 88,000.00 1,232.00
JUMLAH TENAGA KERJA 26,812.50
B. BAHAN
Ubin warna 20 x 20 cm Bh 26.500 2,700.00 71,550.00
Semen Portland Kg 10.400 1,400.00 14,560.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.620 11,000.00 17,820.00
JUMLAH HARGA BAHAN 109,870.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 136,682.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 136,682.50
4.4.3.7 Pemasangan 1 m2 Iantai ubin teraso ukuran 40 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Batu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 24,832.50
B. BAHAN
Ubin teraso 40 x 40 cm Bh 6.630 8,800.00 58,344.00
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.300 11,000.00 14,300.00
JUMLAH HARGA BAHAN 92,304.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 117,136.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 117,136.50
4.4.3.8 Pemasangan 1 m2 Iantai ubin teraso ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.260 55,000.00 14,300.00
Tukang Batu L.02 OH 0.130 71,500.00 9,295.00
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Ubin teraso 30 x 30 cm Bh 11.870 4,600.00 54,602.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 91,042.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 116,782.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 116,782.00
4.4.3.9 Pemasangan 1 m2 Iantai ubin granit ukuran 40 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Batu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 24,832.50
B. BAHAN
Ubin granit 40 x 40 cm Bh 6.630 45,600.00 302,328.00
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.300 11,000.00 14,300.00
JUMLAH HARGA BAHAN 336,288.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 361,120.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 361,120.50
4.4.3.10 Pemasangan 1 m2 Iantai ubin granit ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.260 55,000.00 14,300.00
Tukang Batu L.02 OH 0.130 71,500.00 9,295.00
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Ubin granit 30 x 30 cm Bh 11.870 22,500.00 267,075.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 303,515.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 329,255.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 329,255.00
4.4.3.11 Pemasangan 1 m2 Iantai ubin teralux kerang ukuran 40 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Batu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 24,832.50
B. BAHAN
Ubin teralux kerang 40 x 40 cm Bh 6.630 20,000.00 132,600.00
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.300 11,000.00 14,300.00
JUMLAH HARGA BAHAN 166,560.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 191,392.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 191,392.50
4.4.3.12 Pemasangan 1 m2 Iantai ubin teralux ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.260 55,000.00 14,300.00
Tukang Batu L.02 OH 0.130 71,500.00 9,295.00
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Ubin teralux kerang 30 x 30 cm Bh 11.870 13,500.00 160,245.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 196,685.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 222,425.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 222,425.00
4.4.3.13 Pemasangan 1 m2 Iantai ubin teralux marmer ukuran 60 x 60 cm
A. TENAGA
Pekerja L.01 OH 0.240 55,000.00 13,200.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.012 88,000.00 1,056.00
JUMLAH TENAGA KERJA 23,760.00
B. BAHAN
Ubin teralux marmer 60 x 60 cm Bh 3.100 - -
Semen Portland Kg 9.600 1,400.00 13,440.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 35,880.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 59,640.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 59,640.00
4.4.3.14 Pemasangan 1 m2 Iantai ubin teralux marmer ukuran 40 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Batu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 24,832.50
B. BAHAN
Ubin teralux marmer 40 x 40 cm Bh 6.630 - -
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.300 11,000.00 14,300.00
JUMLAH HARGA BAHAN 33,960.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 58,792.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 58,792.50
4.4.3.15 Pemasangan 1 m2 Iantai ubin teralux marmer ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.260 55,000.00 14,300.00
Tukang Batu L.02 OH 0.130 71,500.00 9,295.00
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 25,740.00
B. BAHAN
Ubin teralux marmer 30 x 30 cm Bh 11.870 - -
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 36,440.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 62,180.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 62,180.00
4.4.3.16 Pemasangan 1 m' Plint ubin PC abu-abu ukuran 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin PC abu-abu 10 x 20 cm Bh 5.300 - -
Semen Portland Kg 1.650 1,400.00 2,310.00
Pasir Pasang m3 0.004 132,000.00 528.00
JUMLAH HARGA BAHAN 2,838.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 15,356.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 15,356.00
4.4.3.17 Pemasangan 1 m' Plint ubin PC abu-abu ukuran 10 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin PC abu-abu 10 x 30 cm Bh 3.530 - -
Semen Portland Kg 1.240 1,400.00 1,736.00
Pasir Pasang m3 0.003 132,000.00 396.00
JUMLAH HARGA BAHAN 2,132.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,650.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 14,650.00
4.4.3.18 Pemasangan 1 m' Plint ubin PC abu-abu ukuran 10 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin PC abu-abu 10 x 40 cm Bh 2.650 - -
Semen Portland Kg 1.240 1,400.00 1,736.00
Pasir Pasang m3 0.003 132,000.00 396.00
JUMLAH HARGA BAHAN 2,132.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,650.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 14,650.00
4.4.3.19 Pemasangan 1 m' Plint ubin PC warna ukuran 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin PC warna 10 x 20 cm Bh 5.300 2,700.00 14,310.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 17,402.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 29,920.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 29,920.00
4.4.3.20 Pemasangan 1 m' Plint ubin PC warna ukuran 10 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin PC warna 10 x 30 cm Bh 3.530 3,000.00 10,590.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 13,682.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 26,200.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 26,200.00
4.4.3.21 Pemasangan 1 m' Plint ubin PC warna ukuran 10 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin PC warna 10 x 40 cm Bh 2.650 3,500.00 9,275.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 12,367.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 24,885.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 24,885.00
4.4.3.22 Pemasangan 1 m' Plint ubin teraso ukuran 10 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teraso 10 x 30 cm Bh 3.530 3,300.00 11,649.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 14,741.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 27,259.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 27,259.00
4.4.3.23 Pemasangan 1 m' Plint ubin teraso ukuran 10 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teraso 10 x 40 cm Bh 2.650 3,800.00 10,070.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 13,162.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 25,680.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 25,680.00
4.4.3.24 Pemasangan 1 m' Plint ubin granit ukuran 10 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin granit 10 x 40 cm Bh 2.650 7,500.00 19,875.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 22,967.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 35,485.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 35,485.00
4.4.3.25 Pemasangan 1 m' Plint ubin granit ukuran 10 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin granit 10 x 30 cm Bh 3.530 4,000.00 14,120.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 17,212.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 29,730.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 29,730.00
4.4.3.26 Pemasangan 1 m' Plint ubin teralux kerang ukuran 10 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teralux kerang 10 x 40 cm Bh 2.650 6,500.00 17,225.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 20,317.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 32,835.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 32,835.00
4.4.3.27 Pemasangan 1 m' Plint ubin teralux kerang ukuran 10 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teralux kerang 10 x 30 cm Bh 3.530 10,000.00 35,300.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 38,392.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 50,910.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 50,910.00
4.4.3.28 Pemasangan 1 m' Plint ubin teralux marmer ukuran 10 x 60 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teralux marmer 10 x 60 cm Bh 1.700 25,000.00 42,500.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 45,592.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 58,110.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 58,110.00
4.4.3.29 Pemasangan 1 m' Plint ubin teralux marmer ukuran 10 x 40 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teralux marmer 10 x 40 cm Bh 2.650 17,500.00 46,375.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 49,467.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 61,985.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 61,985.00
4.4.3.30 Pemasangan 1 m' Plint ubin teralux marmer ukuran 10 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 12,518.00
B. BAHAN
Plint ubin teralux marmer 10 x 30 cm Bh 3.530 13,700.00 48,361.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 51,453.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 63,971.00
E. Overhead & Profit (15%) 15% x D
F. Harga Satuan Pekerjaan (D+E) 63,971.00
4.4.3.31 Pemasangan 1 m2 lantai teraso cor di tempat, tebal 3 cm
A. TENAGA
Pekerja L.01 OH 0.360 55,000.00 19,800.00
Tukang Batu L.02 OH 0.180 71,500.00 12,870.00
Kepala Tukang L.03 OH 0.018 77,000.00 1,386.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 35,640.00
B. BAHAN
Teraso Cor m3 0.036 450,000.00 16,200.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 17,300.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 52,940.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 52,940.00
4.4.3.32 Pemasangan 1 m2 lantai keramik artistik 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
JUMLAH TENAGA KERJA 69,300.00
B. BAHAN
Ubin keramik artistik 10 x 20 cm Bh 53.000 1,100.00 58,300.00
Semen Portland Kg 8.190 1,400.00 11,466.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 2.750 11,000.00 30,250.00
JUMLAH HARGA BAHAN 105,956.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 175,256.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 175,256.00
4.4.3.33 Pemasangan 1 m2 lantai keramik artistik 10 x 10 cm atau 5 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Ubin artistik 10 x 10 cm atau 5 x 20 cm Bh 106.000 550.00 58,300.00
Semen Portland Kg 8.190 1,400.00 11,466.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 3.200 11,000.00 35,200.00
JUMLAH HARGA BAHAN 110,906.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 180,206.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 180,206.00
4.4.3.34 Pemasangan 1 m2 lantai keramik ukuran 33 x 33 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Ubin keramik 33 x 33 cm Bh 10.000 4,900.00 49,000.00
Semen Portland Kg 8.190 1,400.00 11,466.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.620 11,000.00 17,820.00
JUMLAH HARGA BAHAN 84,226.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,526.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 153,526.00
4.4.3.35 Pemasangan 1 m2 lantai keramik ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Ubin keramik 30 x 30 cm Bh 11.870 4,000.00 47,480.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 83,920.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,220.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 153,220.00
4.4.3.36 Pemasangan 1 m2 lantai keramik ukuran 20 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Ubin keramik 20 x 20 cm Bh 26.500 1,900.00 50,350.00
Semen Portland Kg 10.400 1,400.00 14,560.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 1.620 11,000.00 17,820.00
JUMLAH HARGA BAHAN 88,670.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 157,970.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 157,970.00
4.4.3.37 Pemasangan 1 m2 lantai keramik ukuran 10 x 30 cm untuk variasi/border
A. TENAGA
Pekerja L.01 OH 1.050 55,000.00 57,750.00
Tukang Batu L.02 OH 0.525 71,500.00 37,537.50
Kepala Tukang L.03 OH 0.053 77,000.00 4,081.00
Mandor L.04 OH 0.053 88,000.00 4,664.00
104,032.50
B. BAHAN
Ubin keramik 10 x 30 cm Bh 33.000 1,650.00 54,450.00
Semen Portland Kg 9.800 1,400.00 13,720.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 4.370 11,000.00 48,070.00
JUMLAH HARGA BAHAN 122,180.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 226,212.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 226,212.50
4.4.3.38 Pemasangan 1 m2 lantai keramik mozaik ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Ubin keramik mozaik 30 x 30 cm Bh 11.870 4,900.00 58,163.00
Semen Portland Kg 14.150 1,400.00 19,810.00
Pasir Pasang m3 0.039 132,000.00 5,148.00
Semen Warna Kg 2.000 11,000.00 22,000.00
JUMLAH HARGA BAHAN 105,121.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 174,421.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 174,421.00
4.4.3.39 Pemasangan 1 m' plint keramik ukuran 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
12,518.00
B. BAHAN
plint keramik ukuran 10 x 20 cm Bh 5.300 2,200.00 11,660.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.025 11,000.00 275.00
JUMLAH HARGA BAHAN 13,927.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 26,445.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 26,445.00
4.4.3.40 Pemasangan 1 m' plint keramik ukuran 10 x 10 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
12,518.00
B. BAHAN
plint keramik ukuran 10 x 10 cm Bh 10.600 1,100.00 11,660.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.050 11,000.00 550.00
JUMLAH HARGA BAHAN 14,202.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 26,720.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 26,720.00
4.4.3.41 Pemasangan 1 m' plint keramik ukuran 5 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.090 55,000.00 4,950.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.005 88,000.00 440.00
12,518.00
B. BAHAN
plint keramik ukuran 5 x 20 cm Bh 5.300 2,200.00 11,660.00
Semen Portland Kg 0.570 1,400.00 798.00
Pasir Pasang m3 0.0015 132,000.00 198.00
Semen Warna Kg 0.013 11,000.00 143.00
JUMLAH HARGA BAHAN 12,799.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 25,317.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 25,317.00
4.4.3.42 Pemasangan 1 m' plint internal cove artistik 5 x 5 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.750 55,000.00 41,250.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.038 88,000.00 3,344.00
103,994.00
B. BAHAN
plint internal cove artistik 5 x 5 x 20 cm Bh 5.300 6,700.00 35,510.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir Pasang m3 0.003 132,000.00 396.00
Semen Warna Kg 0.100 11,000.00 1,100.00
JUMLAH HARGA BAHAN 38,602.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 142,596.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 142,596.00
4.4.3.43 Pemasangan 1 m2 lantai marmer ukuran 100 x 100 cm
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Marmer 100 x 100 cm Bh 1.060 250,000.00 265,000.00
Semen Portland Kg 8.190 1,400.00 11,466.00
Pasir Pasang m3 0.045 132,000.00 5,940.00
Semen Warna Kg 0.650 11,000.00 7,150.00
JUMLAH HARGA BAHAN 289,556.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 358,856.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 358,856.00
4.4.3.44 Pemasangan 1 m2 lantai karpet
A. TENAGA
Pekerja L.01 OH 0.170 55,000.00 9,350.00
Tukang Kayu L.02 OH 0.170 71,500.00 12,155.00
Kepala Tukang L.03 OH 0.017 77,000.00 1,309.00
Mandor L.04 OH 0.009 88,000.00 792.00
23,606.00
B. BAHAN
Karpet m2 1.050 25,000.00 26,250.00
Lem Kg 0.350 18,000.00 6,300.00
JUMLAH HARGA BAHAN 32,550.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 56,156.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 56,156.00
4.4.3.45 Pemasangan 1 m2 underlayer (pelapis bawah karet)
A. TENAGA
Pekerja L.01 OH 0.120 55,000.00 6,600.00
Tukang Kayu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.006 88,000.00 528.00
16,632.00
B. BAHAN
Underlayer/ rubber corrugated m2 1.050 - -
Lem Kg 0.350 18,000.00 6,300.00
JUMLAH HARGA BAHAN 6,300.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 22,932.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 22,932.00
4.4.3.46 Pemasangan 1 m2 lantai parquet kayu
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Kayu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Parquet m2 1.050 320,000.00 336,000.00
Lem Kg 0.600 18,000.00 10,800.00
JUMLAH HARGA BAHAN 346,800.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 416,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 416,100.00
4.4.3.47 Pemasangan 1 m2 lantai kayu gymfloor
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Kayu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Gymfloor m2 1.050 125,000.00 131,250.00
Lem Kg 0.600 18,000.00 10,800.00
JUMLAH HARGA BAHAN 142,050.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 211,350.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 211,350.00
4.4.3.48 Pemasangan 1 m2 dinding porselen 11 x 11 cm
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Batu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
99,000.00
B. BAHAN
Porselen 11 x 11 cm Bh 86.000 700.00 60,200.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 1.500 11,000.00 16,500.00
JUMLAH HARGA BAHAN 92,096.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 191,096.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 191,096.00
4.4.3.49 Pemasangan 1 m2 dinding porselen 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Porselen 10 x 20 cm Bh 53.000 1,100.00 58,300.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 2.750 11,000.00 30,250.00
JUMLAH HARGA BAHAN 103,946.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 193,046.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 193,046.00
4.4.3.50 Pemasangan 1 m2 dinding porselen 20 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Porselen 20 x 20 cm Bh 26.000 1,900.00 49,400.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 1.940 11,000.00 21,340.00
JUMLAH HARGA BAHAN 86,136.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 175,236.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 175,236.00
4.4.3.51 Pemasangan 1 m2 dinding keramik artistik 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Keramik artistik 10 x 20 cm Bh 53.000 1,100.00 58,300.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 2.750 11,000.00 30,250.00
JUMLAH HARGA BAHAN 103,946.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 193,046.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 193,046.00
4.4.3.52 Pemasangan 1 m2 dinding keramik artistik 5 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Keramik artistik 5 x 20 cm Bh 106.000 550.00 58,300.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 2.900 11,000.00 31,900.00
JUMLAH HARGA BAHAN 105,596.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 194,696.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 194,696.00
4.4.3.53 Pemasangan 1 m2 dinding keramik 10 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Keramik 5 x 20 cm Bh 53.000 - -
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 2.750 11,000.00 30,250.00
JUMLAH HARGA BAHAN 45,646.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 134,746.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 134,746.00
4.4.3.54 Pemasangan 1 m2 dinding keramik 20 x 20 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Keramik 20 x 20 cm Bh 26.500 - -
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir Pasang m3 0.018 132,000.00 2,376.00
Semen Warna Kg 1.940 11,000.00 21,340.00
JUMLAH HARGA BAHAN 36,736.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 125,836.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 125,836.00
4.4.3.55 Pemasangan 1 m2 dinding marmer 100 x 100 cm
A. TENAGA
Pekerja L.01 OH 0.900 55,000.00 49,500.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.045 88,000.00 3,960.00
89,100.00
B. BAHAN
Marmer 100 x 100 cm Bh 1.060 250,000.00 265,000.00
Semen Portland Kg 12.440 1,400.00 17,416.00
Pasir Pasang m3 0.025 132,000.00 3,300.00
Semen Warna Kg 0.650 11,000.00 7,150.00
Paku 12 cm Kg 3.030 22,000.00 66,660.00
JUMLAH HARGA BAHAN 359,526.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 448,626.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 448,626.00
4.4.3.56 Pemasangan 1 m2 dinding bata pelapis 3 x 7 x 24 cm
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Batu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
99,000.00
B. BAHAN
Bata pelapis Bh 63.000 - -
Semen Portland Kg 12.440 1,400.00 17,416.00
Pasir Pasang m3 0.025 132,000.00 3,300.00
Semen Warna Kg 2.750 11,000.00 30,250.00
JUMLAH HARGA BAHAN 50,966.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 149,966.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 149,966.00
4.4.3.57 Pemasangan 1 m2 dinding batu paras
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Batu paras Bh 1.100 65,000.00 71,500.00
Semen Portland Kg 11.750 1,400.00 16,450.00
Pasir Pasang m3 0.035 132,000.00 4,620.00
JUMLAH HARGA BAHAN 92,570.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 161,870.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 161,870.00
4.4.3.58 Pemasangan 1 m2 dinding batu tempel hitam
A. TENAGA
Pekerja L.01 OH 0.700 55,000.00 38,500.00
Tukang Batu L.02 OH 0.350 71,500.00 25,025.00
Kepala Tukang L.03 OH 0.035 77,000.00 2,695.00
Mandor L.04 OH 0.035 88,000.00 3,080.00
69,300.00
B. BAHAN
Batu tempel hitam Bh 1.100 - -
Semen Portland Kg 11.750 1,400.00 16,450.00
Pasir Pasang m3 0.035 132,000.00 4,620.00
JUMLAH HARGA BAHAN 21,070.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 90,370.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 90,370.00
4.4.3.59 Pemasangan 1 m2 lantai vinyl ukuran 30 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Batu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.008 88,000.00 704.00
20,834.00
B. BAHAN
Vinyl Bh 11.870 34,600.00 410,702.00
Lem Vinyl Kg 0.350 18,000.00 6,300.00
JUMLAH HARGA BAHAN 417,002.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 437,836.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 437,836.00
4.4.3.60 Pemasangan 1 m2 wallpaper lebar 50 cm
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang Batu L.02 OH 0.175 71,500.00 12,512.50
Kepala Tukang L.03 OH 0.017 77,000.00 1,309.00
Mandor L.04 OH 0.002 88,000.00 176.00
33,247.50
B. BAHAN
Wallpaper m' 2.200 53,000.00 116,600.00
Lem Kg 0.250 18,000.00 4,500.00
JUMLAH HARGA BAHAN 121,100.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 154,347.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 154,347.50
4.4.3.61 Pemasangan 1 m2 floor hardener
A. TENAGA
Pekerja L.01 OH 0.120 55,000.00 6,600.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.006 88,000.00 528.00
16,632.00
B. BAHAN
Floor Hardener Kg 5.000 30,800.00 154,000.00
JUMLAH HARGA BAHAN 154,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 170,632.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 170,632.00
4.4.3.62 Pemasangan 1 m' plint vinyl 15 x 30 cm
A. TENAGA
Pekerja L.01 OH 0.080 55,000.00 4,400.00
Tukang Batu L.02 OH 0.080 71,500.00 5,720.00
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.004 88,000.00 352.00
11,088.00
B. BAHAN
Plint Vinyl Bh 1.760 - -
Lem Vinyl Kg 0.080 18,000.00 1,440.00
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 11,088.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 11,088.00
4.4.3.63 Pemasangan 1 m' plint kayu tebal 2 cm lebar 10 cm
A. TENAGA
Pekerja L.01 OH 0.120 55,000.00 6,600.00
Tukang Batu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.006 88,000.00 528.00
16,632.00
B. BAHAN
Papan kayu kelas I m3 0.003 18,000,000.00 54,000.00
Paku /skrup 5 cm Kg 0.050 - -
JUMLAH HARGA BAHAN 54,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 70,632.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 70,632.00

4.5.1 HARGA SATUAN PEKERJAAN LANGIT - LANGIT (PLAFOND)

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.5.1.1 Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
A. TENAGA
Pekerja L.01 OH 0.030 55,000.00 1,650.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 7,546.00
B. BAHAN
Asbes semen m2 1.100 79,700.00 87,670.00
Paku tripleks Kg 0.010 20,000.00 200.00
JUMLAH HARGA BAHAN 87,870.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 95,416.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 95,416.00
4.5.1.2 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm
A. TENAGA
Pekerja L.01 OH 0.120 55,000.00 6,600.00
Tukang Kayu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 16,632.00
B. BAHAN
Akustik 30 x 30 cm Lbr 12.000 19,200.00 230,400.00
Paku tripleks Kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 231,400.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 248,032.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 248,032.00
4.5.1.3 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Akustik 30 x 60 cm Lbr 5.800 38,500.00 223,300.00
Paku tripleks Kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 224,300.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 238,160.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 238,160.00
4.5.1.4 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Akustik 60 x 120 cm Lbr 1.500 46,700.00 70,050.00
Paku tripleks Kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 71,050.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 84,910.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 84,910.00
4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Tripleks Lbr 0.375 - -
Paku tripleks Kg 0.030 20,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,460.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 14,460.00
4.5.1.6 Pemasangan 1 m2 langit-langit lambriziring kayu, tebal 9 mm
A. TENAGA
Pekerja L.01 OH 0.800 55,000.00 44,000.00
Tukang Kayu L.02 OH 0.800 71,500.00 57,200.00
Kepala Tukang L.03 OH 0.080 77,000.00 6,160.00
Mandor L.04 OH 0.040 88,000.00 3,520.00
JUMLAH TENAGA KERJA 110,880.00
B. BAHAN
Kayu Papan m3 0.015 135,000.00 2,025.00
Paku tripleks Kg 0.010 20,000.00 200.00
JUMLAH HARGA BAHAN 2,225.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 113,105.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 113,105.00
4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (1200 x 2400 x 9) mm
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.050 71,500.00 3,575.00
Kepala Tukang L.03 OH 0.005 77,000.00 385.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 9,900.00
B. BAHAN
Gypsum Board Lbr 0.364 63,800.00 23,223.20
Paku Sekrup Kg 0.110 - -
JUMLAH HARGA BAHAN 23,223.20
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 33,123.20
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 33,123.20
4.5.1.8 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium
A. TENAGA
Pekerja L.01 OH 0.500 55,000.00 27,500.00
Tukang Kayu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.025 88,000.00 2,200.00
JUMLAH TENAGA KERJA 69,300.00
B. BAHAN
Profil Alluminium "T" m' 3.600 22,000.00 79,200.00
Kawat diameter 4 mm Kg 0.150 17,000.00 2,550.00
Ramset Bh 1.050 550.00 577.50
Akustik 60 cm x 120 cm Lbr 1.500 46,700.00 70,050.00
JUMLAH HARGA BAHAN 81,750.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 151,050.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 151,050.00
4.5.1.9 Pemasangan 1 m' list langit-langit kayu profil
A. TENAGA
Pekerja L.01 OH 0.050 55,000.00 2,750.00
Tukang Kayu L.02 OH 0.050 71,500.00 3,575.00
Kepala Tukang L.03 OH 0.005 77,000.00 385.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 6,974.00
B. BAHAN
List kayu profil m' 1.050 8,500.00 8,925.00
Paku Kg 0.010 20,000.00 200.00
JUMLAH HARGA BAHAN 9,125.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 16,099.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 16,099.00

4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.5.2.1 Pemasangan 1 m2 atap genteng palentong kecil
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 14,932.50
B. BAHAN
Genteng Palentong Bh 25.000 2,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 64,932.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 64,932.50
4.5.2.2 Pemasangan 1 m2 atap genteng kodok glazur
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 14,932.50
B. BAHAN
Genteng Kodok Glazur Bh 25.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,932.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 14,932.50
4.5.2.3 Pemasangan 1 m2 atap genteng palentong besar/super
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 13,706.00
B. BAHAN
Genteng Palentong besar Bh 12.000 3,300.00 39,600.00
JUMLAH HARGA BAHAN 39,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 53,306.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 53,306.00
4.5.2.4 Pemasangan 1 m' bubung genteng palentong
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 38,016.00
B. BAHAN
Genteng bubung palentong Bh 5.000 6,700.00 33,500.00
Semen Portland Kg 8.000 1,400.00 11,200.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
JUMLAH HARGA BAHAN 48,924.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 86,940.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 86,940.00
4.5.2.5 Pemasangan 1 m' bubung genteng kodok glazur
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 38,016.00
B. BAHAN
Genteng bubung kodok Bh 5.000 21,000.00 105,000.00
Semen Portland Kg 8.000 1,400.00 11,200.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
JUMLAH HARGA BAHAN 120,424.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 158,440.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 158,440.00
4.5.2.6 Pemasangan 1 m' bubung genteng palentong besar
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 38,016.00
B. BAHAN
Genteng bubung palentong Bh 4.000 - -
Semen Portland Kg 8.000 1,400.00 11,200.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
JUMLAH HARGA BAHAN 15,424.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 53,440.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 53,440.00
4.5.2.7 Pemasangan 1 m2 roof light fiberglass 90 x 180
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.067 71,500.00 4,790.50
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,645.50
B. BAHAN
Roof light fiberglass Lbr 0.600 75,300.00 45,180.00
Paku biasa 1/2" - 1" Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 45,905.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 59,550.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 59,550.50
4.5.2.8 Pemasangan 1 m2 atap asbes gelombang 0.92m x 2.5m x 5mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 14,382.50
B. BAHAN
Asbes gelombang 92 x 250 Lbr 0.500 93,500.00 46,750.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 46,750.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 61,132.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 61,132.50
4.5.2.9 Pemasangan 1 m2 atap asbes gelombang 0.92m x 2.25m x 5mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 14,382.50
B. BAHAN
Asbes gelombang 92 x 225 Lbr 0.600 85,800.00 51,480.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 51,480.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,862.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 65,862.50
4.5.2.10 Pemasangan 1 m2 atap asbes gelombang 0.92m x 2.00m x 5mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 92 x 200 Lbr 0.600 79,200.00 47,520.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 47,520.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 61,380.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 61,380.00
4.5.2.11 Pemasangan 1 m2 atap asbes gelombang 0.92m x 1.80m x 5mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 92 x 180 Lbr 0.750 69,300.00 51,975.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 51,975.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,835.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 65,835.00
4.5.2.12 Pemasangan 1 m2 atap asbes gelombang 1.05m x 3.00m x 4mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 105 x 300 Lbr 0.350 86,300.00 30,205.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 30,205.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 44,065.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 44,065.00
4.5.2.13 Pemasangan 1 m2 atap asbes gelombang 1.05m x 2.70m x 4mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 105 x 270 Lbr 0.420 78,600.00 33,012.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 33,012.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 46,872.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 46,872.00
4.5.2.14 Pemasangan 1 m2 atap asbes gelombang 1.05m x 2.40m x 4mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 105 x 240 Lbr 0.440 69,800.00 30,712.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 30,712.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 44,572.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 44,572.00
4.5.2.15 Pemasangan 1 m2 atap asbes gelombang 1.05m x 2.10m x 4mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 105 x 210 Lbr 0.510 57,700.00 29,427.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 29,427.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 43,287.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 43,287.00
4.5.2.16 Pemasangan 1 m2 atap asbes gelombang 1.05m x 1.50m x 4mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 105 x 150 Lbr 0.800 38,500.00 30,800.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 30,800.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 44,660.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 44,660.00
4.5.2.17 Pemasangan 1 m2 atap asbes gelombang 1.08m x 3.00m x 6mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 108 x 300 Lbr 0.370 105,300.00 38,961.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 38,961.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 52,821.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 52,821.00
4.5.2.18 Pemasangan 1 m2 atap asbes gelombang 1.08m x 2.70m x 6mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 108 x 270 Lbr 0.380 96,100.00 36,518.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 36,518.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 50,378.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 50,378.00
4.5.2.19 Pemasangan 1 m2 atap asbes gelombang 1.08m x 2.40m x 6mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 108 x 240 Lbr 0.460 82,700.00 38,042.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 38,042.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 51,902.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 51,902.00
4.5.2.20 Pemasangan 1 m2 atap asbes gelombang 1.08m x 2.10m x 6mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 108 x 210 Lbr 0.490 69,900.00 34,251.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 34,251.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 48,111.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 48,111.00
4.5.2.21 Pemasangan 1 m2 atap asbes gelombang 1.08m x 1.80m x 6mm
A. TENAGA
Pekerja L.01 OH 0.140 55,000.00 7,700.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Asbes gelombang 108 x 180 Lbr 0.570 58,200.00 33,174.00
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN 33,174.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 47,034.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 47,034.00
4.5.2.22 Pemasangan 1 m' bubung stel gelombang 0.92m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Bubung stel gelombang 92 Lbr 2.400 21,500.00 51,600.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 51,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 66,510.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 66,510.50
4.5.2.23 Pemasangan 1 m' bubung stel gelombang 1.05m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Bubung stel gelombang 105 Lbr 2.100 28,600.00 60,060.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 60,060.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 74,970.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 74,970.50
4.5.2.24 Pemasangan 1 m' bubung stel gelombang 1.08m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Bubung stel gelombang 108 Lbr 2.050 31,300.00 64,165.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 64,165.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 79,075.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 79,075.50
4.5.2.25 Pemasangan 1 m' nok paten 0.92m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Nok Paten 92 Lbr 1.200 33,000.00 39,600.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 39,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 54,510.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 54,510.50
4.5.2.26 Pemasangan 1 m' nok paten 1.05m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Nok Paten 105 Lbr 1.200 37,500.00 45,000.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 45,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 59,910.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 59,910.50
4.5.2.27 Pemasangan 1 m' nok paten 1.08m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Nok Paten 108 Lbr 1.200 42,200.00 50,640.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 50,640.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,550.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 65,550.50
4.5.2.28 Pemasangan 1 m' nok stel rata 0.92m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Nok Stel Rata 92 Lbr 1.100 27,600.00 30,360.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 30,360.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 45,270.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 45,270.50
4.5.2.29 Pemasangan 1 m' nok stel rata 1.05m
A. TENAGA
Pekerja L.01 OH 0.084 55,000.00 4,620.00
Tukang Kayu L.02 OH 0.125 71,500.00 8,937.50
Kepala Tukang L.03 OH 0.013 77,000.00 1,001.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 14,910.50
B. BAHAN
Nok Stel Rata 105 Lbr 1.100 36,000.00 39,600.00
paku sekrup 3,5" Bh 6.000 - -
JUMLAH HARGA BAHAN 39,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 54,510.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 54,510.50
4.5.2.30 Pemasangan 1 m2 genteng beton
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 19,800.00
B. BAHAN
Genteng beton Bh 11.000 3,800.00 41,800.00
Paku biasa 2" - 5" Kg 0.030 14,500.00 435.00
JUMLAH HARGA BAHAN 42,235.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 62,035.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 62,035.00
4.5.2.31 Pemasangan 1 m2 genteng aspal
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.003 77,000.00 231.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 33,561.00
B. BAHAN
Genteng aspal Bh 6.900 18,300.00 126,270.00
Plywood 6 mm Lbr 0.350 71,000.00 24,850.00
Paku biasa 1/2" - 1" Kg 0.030 14,500.00 435.00
Plastik Aerator Bh 0.500 15,000.00 7,500.00
JUMLAH HARGA BAHAN 159,055.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 192,616.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 192,616.00
4.5.2.32 Pemasangan 1 m2 genteng metal
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.001 88,000.00 88.00
JUMLAH TENAGA KERJA 19,008.00
B. BAHAN
Genteng metal Bh 1.020 96,800.00 98,736.00
Paku biasa 1/2" - 1" Lbr 0.200 14,500.00 2,900.00
JUMLAH HARGA BAHAN 101,636.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 120,644.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 120,644.00
4.5.2.33 Pemasangan 1 m2 atap sirap kayu
A. TENAGA
Pekerja L.01 OH 0.166 55,000.00 9,130.00
Tukang Kayu L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 29,634.00
B. BAHAN
Sirap Kayu Bh 30.000 1,900.00 57,000.00
Paku biasa 1/2" - 1" Lbr 0.200 14,500.00 2,900.00
JUMLAH HARGA BAHAN 59,900.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 89,534.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 89,534.00
4.5.2.34 Pemasangan 1 m' nok genteng beton
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.020 88,000.00 1,760.00
JUMLAH TENAGA KERJA 39,600.00
B. BAHAN
Nok Genteng Beton Bh 3.500 11,500.00 40,250.00
Paku biasa 1/2" - 1" Kg 0.050 14,500.00 725.00
Semen Portland Kg 10.800 1,400.00 15,120.00
Pasir Pasang m3 0.032 132,000.00 4,224.00
Semen warna Kg 1.000 11,000.00 11,000.00
JUMLAH HARGA BAHAN 71,319.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 110,919.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 110,919.00
4.5.2.35 Pemasangan 1 m' nok genteng aspal
A. TENAGA
Pekerja L.01 OH 0.125 55,000.00 6,875.00
Tukang Kayu L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 27,203.00
B. BAHAN
Nok Genteng Aspal Bh 2.000 32,200.00 64,400.00
Paku biasa 1/2" - 1" Kg 0.050 14,500.00 725.00
Kayu Balok Borneo m3 0.0035 7,750,000.00 27,125.00
JUMLAH HARGA BAHAN 92,250.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 119,453.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 119,453.00
4.5.2.36 Pemasangan 1 m' nok genteng metal
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.013 88,000.00 1,144.00
JUMLAH TENAGA KERJA 26,774.00
B. BAHAN
Nok Genteng Metal (Genteng Decrabond) Bh 1.100 93,500.00 102,850.00
Paku biasa 1/2" - 1" Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 103,575.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 130,349.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 130,349.00
4.5.2.37 Pemasangan 1 m' nok sirap
A. TENAGA
Pekerja L.01 OH 0.125 55,000.00 6,875.00
Tukang Kayu L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 27,203.00
B. BAHAN
Seng plat 3" x 6" bjls 28 Lbr 0.400 47,800.00 19,120.00
paku biasa 1/2" - 1" Kg 0.060 14,500.00 870.00
paku biasa 2" - 5" Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 19,990.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 47,193.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 47,193.00
4.5.2.38 Pemasangan 1 m2 atap seng gelombang
A. TENAGA
Pekerja L.01 OH 0.120 55,000.00 6,600.00
Tukang Kayu L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 11,880.00
B. BAHAN
Seng gelombang 3" x 6" bjls 28 Lbr 0.700 58,500.00 40,950.00
paku biasa 1/2" - 1" Kg 0.020 14,500.00 290.00
JUMLAH HARGA BAHAN 41,240.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 53,120.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 53,120.00
4.5.2.39 Pemasangan 1 m' nok atap seng
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.070 71,500.00 5,005.00
Kepala Tukang L.03 OH 0.007 77,000.00 539.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 14,322.00
B. BAHAN
Seng plat 3" x 6" bjls 28 Lbr 0.300 47,800.00 14,340.00
paku biasa 1/2" - 1" Kg 0.040 14,500.00 580.00
JUMLAH HARGA BAHAN 14,920.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 29,242.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 29,242.00
4.5.2.40 Pemasangan 1 m2 atap alumunium
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 63,019.00
B. BAHAN
Alumunium gelombang 0.55 Lbr 1.050 98,200.00 103,110.00
Paku hak panjang 15 cm Kg 0.020 - -
JUMLAH HARGA BAHAN 103,110.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 166,129.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 166,129.00
4.5.2.41 Pemasangan 1 m' nok alumunium
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 1.000 71,500.00 71,500.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 82,170.00
B. BAHAN
Nok standar 40 x 18, swg 22 Bh 1.200 36,300.00 43,560.00
Paku hak panjang 15 cm Kg 0.040 - -
JUMLAH HARGA BAHAN 43,560.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 125,730.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 125,730.00
4.5.2.42 Pemasangan 1 m2 alumunium foil/sisalation
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.050 71,500.00 3,575.00
Kepala Tukang L.03 OH 0.005 77,000.00 385.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 12,914.00
B. BAHAN
alumunium foil/sisalation m2 1.050 20,300.00 21,315.00
JUMLAH HARGA BAHAN 21,315.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 34,229.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 34,229.00

4.6.1 HARGA SATUAN PEKERJAAN KAYU

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.6.1.1 Pembuatan dan pemasangan 1 m2 kusen pintu dan kusen jendela, kayu kelas I
A. TENAGA
Pekerja L.01 OH 7.000 55,000.00 385,000.00
Tukang Kayu L.02 OH 21.000 71,500.00 1,501,500.00
Kepala Tukang L.03 OH 2.100 77,000.00 161,700.00
Mandor L.04 OH 0.350 88,000.00 30,800.00
JUMLAH TENAGA KERJA 2,079,000.00
B. BAHAN
Balok kayu kelas I m3 1.100 15,800,000.00 17,380,000.00
Paku 10 cm Kg 1.250 14,500.00 18,125.00
Lem kayu Kg 1.000 27,200.00 27,200.00
JUMLAH HARGA BAHAN 17,425,325.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 19,504,325.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 19,504,325.00
4.6.1.2 Pembuatan dan pemasangan 1 m2 kusen pintu dan kusen jendela, kayu kelas II dan III
A. TENAGA
Pekerja L.01 OH 6.000 55,000.00 330,000.00
Tukang Kayu L.02 OH 18.000 71,500.00 1,287,000.00
Kepala Tukang L.03 OH 1.800 77,000.00 138,600.00
Mandor L.04 OH 0.300 88,000.00 26,400.00
JUMLAH TENAGA KERJA 1,782,000.00
B. BAHAN
Balok kayu kelas II atau III m3 1.200 - -
Paku 10 cm Kg 1.250 14,500.00 18,125.00
Lem kayu Kg 1.000 27,200.00 27,200.00
JUMLAH HARGA BAHAN 45,325.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,827,325.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,827,325.00
4.6.1.3 Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang Kayu L.02 OH 1.050 71,500.00 75,075.00
Kepala Tukang L.03 OH 0.105 77,000.00 8,085.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 103,994.00
B. BAHAN
Papan kayu kelas II m3 0.040 9,000,000.00 360,000.00
Paku 5 - 7 cm Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 360,725.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 464,719.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 464,719.00
4.6.1.4 Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III
A. TENAGA
Pekerja L.01 OH 0.350 55,000.00 19,250.00
Tukang Kayu L.02 OH 1.050 71,500.00 75,075.00
Kepala Tukang L.03 OH 0.105 77,000.00 8,085.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 103,994.00
B. BAHAN
Papan kayu kelas III m3 0.040 6,250,000.00 250,000.00
Paku 5 - 7 cm Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 250,725.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 354,719.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 354,719.00
4.6.1.5 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 3.000 71,500.00 214,500.00
Kepala Tukang L.03 OH 0.300 77,000.00 23,100.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 297,000.00
B. BAHAN
Papan kayu kelas I atau II m3 0.040 - -
Lem Kayu Kg 0.500 27,200.00 13,600.00
JUMLAH HARGA BAHAN 13,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 310,600.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 310,600.00
4.6.1.6 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 0.800 55,000.00 44,000.00
Tukang Kayu L.02 OH 2.400 71,500.00 171,600.00
Kepala Tukang L.03 OH 0.240 77,000.00 18,480.00
Mandor L.04 OH 0.040 88,000.00 3,520.00
JUMLAH TENAGA KERJA 237,600.00
B. BAHAN
Papan kayu kelas I atau II m3 0.024 - -
Lem Kayu Kg 0.300 27,200.00 8,160.00
JUMLAH HARGA BAHAN 8,160.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 245,760.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 245,760.00
4.6.1.7 Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi, kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 3.000 71,500.00 214,500.00
Kepala Tukang L.03 OH 0.300 77,000.00 23,100.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 297,000.00
B. BAHAN
Papan kayu kelas I atau II m3 0.064 - -
Lem Kayu Kg 0.500 27,200.00 13,600.00
JUMLAH HARGA BAHAN 13,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 310,600.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 310,600.00
4.6.1.8 Pembuatan 1 m2 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II tertutup (lebar sampai 90 cm)
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Kayu L.02 OH 3.000 71,500.00 214,500.00
Kepala Tukang L.03 OH 0.300 77,000.00 23,100.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 297,000.00
B. BAHAN
Papan kayu kelas II m3 0.025 9,000,000.00 225,000.00
Paku 1 - 2.5 cm Kg 0.030 14,500.00 435.00
Lem kayu Kg 0.500 27,200.00 13,600.00
Plywood tebal 4 mm Ukuran (90 x 220) cm Lbr 1.000 95,000.00 95,000.00
JUMLAH HARGA BAHAN 334,035.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 631,035.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 631,035.00
4.6.1.9 Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 0.800 55,000.00 44,000.00
Tukang Kayu L.02 OH 2.400 71,500.00 171,600.00
Kepala Tukang L.03 OH 0.240 77,000.00 18,480.00
Mandor L.04 OH 0.040 88,000.00 3,520.00
JUMLAH TENAGA KERJA 237,600.00
B. BAHAN
Papan kayu kelas I atau II m3 0.0256 - -
Paku 1 - 2.5 cm Kg 0.030 14,500.00 435.00
Lem kayu Kg 0.500 27,200.00 13,600.00
Plywood tebal 4 mm Ukuran (90 x 220) cm Lbr 1.000 95,000.00 95,000.00
JUMLAH HARGA BAHAN 109,035.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 346,635.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 346,635.00
4.6.1.10 Pembuatan 1 m2 jalusi kusen, kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 0.800 55,000.00 44,000.00
Tukang Kayu L.02 OH 2.400 71,500.00 171,600.00
Kepala Tukang L.03 OH 0.240 77,000.00 18,480.00
Mandor L.04 OH 0.040 88,000.00 3,520.00
JUMLAH TENAGA KERJA 237,600.00
B. BAHAN
Papan kayu kelas I atau II m3 0.060 - -
Paku 1 - 2.5 cm Kg 0.150 14,500.00 2,175.00
JUMLAH HARGA BAHAN 2,175.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 239,775.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 239,775.00
4.6.1.11 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I
A. TENAGA
Pekerja L.01 OH 0.800 55,000.00 44,000.00
Tukang Kayu L.02 OH 2.400 71,500.00 171,600.00
Kepala Tukang L.03 OH 0.240 77,000.00 18,480.00
Mandor L.04 OH 0.040 88,000.00 3,520.00
JUMLAH TENAGA KERJA 237,600.00
B. BAHAN
Papan kayu kelas I m3 0.025 18,000,000.00 450,000.00
Paku 1 - 2.5 cm Kg 0.030 14,500.00 435.00
Lem kayu Kg 0.300 27,200.00 8,160.00
Plywood tebal 4 mm Ukuran (90 x 220) cm Lbr 1.000 95,000.00 95,000.00
JUMLAH HARGA BAHAN 553,595.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 791,195.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 791,195.00
4.6.1.12 Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas III
A. TENAGA
Pekerja L.01 OH 0.850 55,000.00 46,750.00
Tukang Kayu L.02 OH 2.550 71,500.00 182,325.00
Kepala Tukang L.03 OH 0.255 77,000.00 19,635.00
Mandor L.04 OH 0.043 88,000.00 3,784.00
JUMLAH TENAGA KERJA 252,494.00
B. BAHAN
Papan kayu kelas III m3 0.025 6,250,000.00 156,250.00
Paku 1 - 2.5 cm Kg 0.030 14,500.00 435.00
Lem kayu Kg 0.800 27,200.00 21,760.00
Plywood tebal 4 mm Ukuran (90 x 220) cm Lbr 1.000 95,000.00 95,000.00
Formika Lbr 0.500 82,500.00 41,250.00
JUMLAH HARGA BAHAN 314,695.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 567,189.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 567,189.00
4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 m
A. TENAGA
Pekerja L.01 OH 4.000 55,000.00 220,000.00
Tukang Kayu L.02 OH 12.000 71,500.00 858,000.00
Kepala Tukang L.03 OH 1.200 77,000.00 92,400.00
Mandor L.04 OH 0.200 88,000.00 17,600.00
JUMLAH TENAGA KERJA 1,188,000.00
B. BAHAN
Balok kayu m3 1.100 - -
Besi strip tebal 5 mm Kg 15.000 15,000.00 225,000.00
Paku 12 cm Kg 5.600 14,500.00 81,200.00
JUMLAH HARGA BAHAN 306,200.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,494,200.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,494,200.00
4.6.1.14 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I
A. TENAGA
Pekerja L.01 OH 6.700 55,000.00 368,500.00
Tukang Kayu L.02 OH 20.100 71,500.00 1,437,150.00
Kepala Tukang L.03 OH 2.010 77,000.00 154,770.00
Mandor L.04 OH 0.335 88,000.00 29,480.00
JUMLAH TENAGA KERJA 1,989,900.00
B. BAHAN
Balok kayu kelas I m3 1.200 15,800,000.00 18,960,000.00
Besi strip tebal 5 mm Kg 15.000 15,000.00 225,000.00
Paku 12 cm Kg 5.600 14,500.00 81,200.00
JUMLAH HARGA BAHAN 19,266,200.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 21,256,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 21,256,100.00
4.6.1.15 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II
A. TENAGA
Pekerja L.01 OH 6.700 55,000.00 368,500.00
Tukang Kayu L.02 OH 20.100 71,500.00 1,437,150.00
Kepala Tukang L.03 OH 2.010 77,000.00 154,770.00
Mandor L.04 OH 0.335 88,000.00 29,480.00
JUMLAH TENAGA KERJA 1,989,900.00
B. BAHAN
Balok kayu kelas II m3 1.100 8,000,000.00 8,800,000.00
Besi strip tebal 5 mm Kg 15.000 15,000.00 225,000.00
Paku 12 cm Kg 3.000 14,500.00 43,500.00
JUMLAH HARGA BAHAN 9,068,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 11,058,400.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 11,058,400.00
4.6.1.16 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Kaso-kaso 5 x 7 cm m3 0.014 7,000,000.00 98,000.00
Reng 2 x 3 cm m3 0.036 6,500,000.00 234,000.00
Paku 5 dan 10 cm Kg 0.250 14,500.00 3,625.00
JUMLAH HARGA BAHAN 335,625.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 349,485.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 349,485.00
4.6.1.17 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Kaso-kaso 5 x 7 cm m3 0.014 7,000,000.00 98,000.00
Reng 3 x 4 cm m3 0.057 6,500,000.00 370,500.00
Paku 5 dan 10 cm Kg 0.250 14,500.00 3,625.00
JUMLAH HARGA BAHAN 472,125.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 485,985.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 485,985.00
4.6.1.-- Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 13,860.00
B. BAHAN
Kaso-kaso 5 x 7 cm m3 0.008 7,000,000.00 56,000.00
Reng 3 x 4 cm m3 0.004 6,500,000.00 26,000.00
Paku 5 dan 10 cm Kg 0.150 14,500.00 2,175.00
JUMLAH HARGA BAHAN 84,175.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 98,035.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 98,035.00
4.6.1.18 Pemasangan 1 m2 rangka atap sirap, kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.120 55,000.00 6,600.00
Tukang Kayu L.02 OH 0.120 71,500.00 8,580.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 16,632.00
B. BAHAN
Kayu Kelas II m3 0.165 6,500,000.00 1,072,500.00
Paku 5 dan 10 cm Kg 0.200 14,500.00 2,900.00
JUMLAH HARGA BAHAN 1,075,400.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,092,032.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,092,032.00
4.6.1.19 Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.030 77,000.00 2,310.00
Mandor L.04 OH 0.075 88,000.00 6,600.00
JUMLAH TENAGA KERJA 38,610.00
B. BAHAN
Kaso-kaso 5 x 7 cm m3 0.0154 - -
Paku 7 - 10 cm Kg 0.200 14,500.00 2,900.00
JUMLAH HARGA BAHAN 2,900.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 41,510.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 41,510.00
4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.030 77,000.00 2,310.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 35,640.00
B. BAHAN
Kaso-kaso 5 x 7 cm m3 0.0163 - -
Paku 7 - 10 cm Kg 0.250 14,500.00 3,625.00
JUMLAH HARGA BAHAN 3,625.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,265.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 39,265.00
4.6.1.21 Pemasangan 1 m' lisplank ukuran (3 x 20) cm, kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 21,780.00
B. BAHAN
Papan Kayu m3 0.0108 - -
Paku 5 - 7cm Kg 0.100 14,500.00 1,450.00
JUMLAH HARGA BAHAN 1,450.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 23,230.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 23,230.00
4.6.1.22 Pemasangan 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I atau II
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 21,780.00
B. BAHAN
Papan Kayu m3 0.011 - -
Paku 5 - 7 cm Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 725.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 22,505.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 22,505.00
4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 44,594.00
B. BAHAN
Balok Kayu m3 0.028 8,000,000.00 224,000.00
Paku 5 - 7 cm Kg 0.150 14,500.00 2,175.00
JUMLAH HARGA BAHAN 226,175.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 270,769.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 270,769.00
4.6.1.24 Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Kayu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 44,594.00
B. BAHAN
Balok kayu 6 x 12 cm m3 0.028 8,000,000.00 224,000.00
Paku 5 dan 10 cm Kg 0.150 14,500.00 2,175.00
Teakwood tebal 4 mm ukuran (120 x 240) cm Lbr 0.860 124,700.00 107,242.00
Lem kayu Kg 0.560 27,200.00 15,232.00
JUMLAH HARGA BAHAN 348,649.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 393,243.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 393,243.00
4.6.1.25 Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
A. TENAGA
Pekerja L.01 OH 0.200 55,000.00 11,000.00
Tukang Kayu L.02 OH 0.600 71,500.00 42,900.00
Kepala Tukang L.03 OH 0.060 77,000.00 4,620.00
Mandor L.04 OH 0.010 88,000.00 880.00
JUMLAH TENAGA KERJA 59,400.00
B. BAHAN
Balok kayu 6 x 12 cm m3 0.028 8,000,000.00 224,000.00
Paku 5 dan 10 cm Kg 0.150 14,500.00 2,175.00
Plywood tebal 4 mm ukuran (120 x 240) cm Lbr 0.860 95,000.00 81,700.00
Lem kayu Kg 0.560 27,200.00 15,232.00
JUMLAH HARGA BAHAN 323,107.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 382,507.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 382,507.00
4.6.1.26 Pemasangan 1 m2 dinding lambriziring dari papan kayu kelas I
A. TENAGA
Pekerja L.01 OH 0.600 55,000.00 33,000.00
Tukang Kayu L.02 OH 1.800 71,500.00 128,700.00
Kepala Tukang L.03 OH 0.180 77,000.00 13,860.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 178,200.00
B. BAHAN
Papan kayu kelas I m3 0.007 18,000,000.00 126,000.00
Paku 5 dan 10 cm Kg 0.100 14,500.00 1,450.00
Paku skrup 10 cm Kg 0.150 - -
JUMLAH HARGA BAHAN 127,450.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 305,650.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 305,650.00
4.6.1.27 Pemasangan 1 m2 dinding lambriziring dari plywood ukuran (120 x 240) cm
A. TENAGA
Pekerja L.01 OH 0.025 55,000.00 1,375.00
Tukang Kayu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.001 88,000.00 88.00
JUMLAH TENAGA KERJA 7,441.50
B. BAHAN
Plywood tebal 4 mm Lbr 0.400 95,000.00 38,000.00
Paku 1 dan 2.5 cm Kg 0.050 14,500.00 725.00
JUMLAH HARGA BAHAN 38,725.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 46,166.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 46,166.50
4.6.1.28 Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV
A. TENAGA
Pekerja L.01 OH 0.025 55,000.00 1,375.00
Tukang Kayu L.02 OH 0.075 71,500.00 5,362.50
Kepala Tukang L.03 OH 0.008 77,000.00 616.00
Mandor L.04 OH 0.001 88,000.00 88.00
JUMLAH TENAGA KERJA 7,441.50
B. BAHAN
Bilik bambu m2 1.500 9,300.00 13,950.00
Kaso-kaso (5 x 7) cm m3 0.014 - -
Paku Kg 0.012 14,500.00 174.00
List kayu 2/4 m3 0.003 5,000.00 15.00
JUMLAH HARGA BAHAN 13,950.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 21,391.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 21,391.50

4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.6.2.1 Pemasangan 1 buah kunci tanam antik
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Kayu L.02 OH 0.600 71,500.00 42,900.00
Kepala Tukang L.03 OH 0.060 77,000.00 4,620.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 51,084.00
B. BAHAN
Kunci Tanam Antik Bh 1.000 157,500.00 157,500.00
JUMLAH HARGA BAHAN 157,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 208,584.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 208,584.00
4.6.2.2 Pemasangan 1 buah kunci tanam biasa
A. TENAGA
Pekerja L.01 OH 0.010 55,000.00 550.00
Tukang Kayu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 40,590.00
B. BAHAN
Kunci Tanam Biasa Bh 1.000 47,500.00 47,500.00
JUMLAH HARGA BAHAN 47,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 88,090.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 88,090.00
4.6.2.3 Pemasangan 1 buah kunci kamar mandi
A. TENAGA
Pekerja L.01 OH 0.005 55,000.00 275.00
Tukang Kayu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 40,139.00
B. BAHAN
Kunci Tanam Kamar Mandi Bh 1.000 29,700.00 29,700.00
JUMLAH HARGA BAHAN 29,700.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 69,839.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 69,839.00
4.6.2.4 Pemasangan 1 buah kunci kamar silinder
A. TENAGA
Pekerja L.01 OH 0.005 55,000.00 275.00
Tukang Kayu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 40,139.00
B. BAHAN
Kunci Silinder Bh 1.000 82,500.00 82,500.00
JUMLAH HARGA BAHAN 82,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 122,639.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 122,639.00
4.6.2.5 Pemasangan 1 buah engsel pintu
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Engsel Pintu Bh 1.000 16,500.00 16,500.00
JUMLAH HARGA BAHAN 16,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 29,275.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 29,275.40
4.6.2.6 Pemasangan 1 buah engsel jendela kupu - kupu
A. TENAGA
Pekerja L.01 OH 0.010 55,000.00 550.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.0005 88,000.00 44.00
JUMLAH TENAGA KERJA 8,514.00
B. BAHAN
Engsel Kupu - Kupu Bh 1.000 18,850.00 18,850.00
JUMLAH HARGA BAHAN 18,850.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 27,364.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 27,364.00
4.6.2.7 Pemasangan 1 buah engsel angin
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.0005 88,000.00 44.00
JUMLAH TENAGA KERJA 21,384.00
B. BAHAN
Engsel Angin Bh 1.000 18,000.00 18,000.00
JUMLAH HARGA BAHAN 18,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,384.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 39,384.00
4.6.2.8 Pemasangan 1 buah spring knip
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Spring knip Bh 1.000 26,100.00 26,100.00
JUMLAH HARGA BAHAN 26,100.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 38,875.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 38,875.40
4.6.2.9 Pemasangan 1 buah kait angin
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Kait Angin Bh 1.000 12,600.00 12,600.00
JUMLAH HARGA BAHAN 12,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 25,375.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 25,375.40
4.6.2.10 Pemasangan 1 buah door closer
A. TENAGA
Pekerja L.01 OH 0.050 55,000.00 2,750.00
Tukang Kayu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 42,614.00
B. BAHAN
Door Closer Set 1.000 203,500.00 203,500.00
JUMLAH HARGA BAHAN 203,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 246,114.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 246,114.00
4.6.2.11 Pemasangan 1 buah kunci selot
A. TENAGA
Pekerja L.01 OH 0.020 55,000.00 1,100.00
Tukang Kayu L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.001 88,000.00 88.00
JUMLAH TENAGA KERJA 17,028.00
B. BAHAN
Kunci Selot Bh 1.000 57,000.00 57,000.00
JUMLAH HARGA BAHAN 57,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 74,028.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 74,028.00
4.6.2.12 Pemasangan 1 buah door holder
A. TENAGA
Pekerja L.01 OH 0.050 55,000.00 2,750.00
Tukang Kayu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 42,614.00
B. BAHAN
Door Holder Bh 1.000 70,000.00 70,000.00
JUMLAH HARGA BAHAN 70,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 112,614.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 112,614.00
4.6.2.13 Pemasangan 1 buah door stop
A. TENAGA
Pekerja L.01 OH 0.010 55,000.00 550.00
Tukang Kayu L.02 OH 0.100 71,500.00 7,150.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 8,910.00
B. BAHAN
Door Stop Bh 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 33,910.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 33,910.00
4.6.2.14 Pemasangan 1 buah rel pintu dorong
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Kayu L.02 OH 0.600 71,500.00 42,900.00
Kepala Tukang L.03 OH 0.060 77,000.00 4,620.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 51,084.00
B. BAHAN
Rel Pintu Dorong Bh 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 75,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 126,084.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 126,084.00
4.6.2.15 Pemasangan 1 buah kunci lemari
A. TENAGA
Pekerja L.01 OH 0.025 55,000.00 1,375.00
Tukang Kayu L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.0013 88,000.00 114.40
JUMLAH TENAGA KERJA 21,289.40
B. BAHAN
Kunci Lemari Bh 1.000 10,000.00 10,000.00
JUMLAH HARGA BAHAN 10,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 31,289.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 31,289.40
4.6.2.16 Pemasangan 1 m2 kaca tebal 3 mm
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Kaca tebal 3 mm m2 1.100 75,000.00 82,500.00
Sealant Kg 0.050 28,000.00 1,400.00
JUMLAH HARGA BAHAN 83,900.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 96,675.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 96,675.40
4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Kaca tebal 5 mm m2 1.100 93,500.00 102,850.00
Sealant Kg 0.050 28,000.00 1,400.00
JUMLAH HARGA BAHAN 104,250.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 117,025.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 117,025.40
4.6.2.18 Pemasangan 1 m2 kaca tebal 8 mm
A. TENAGA
Pekerja L.01 OH 0.017 55,000.00 935.00
Tukang Kayu L.02 OH 0.170 71,500.00 12,155.00
Kepala Tukang L.03 OH 0.017 77,000.00 1,309.00
Mandor L.04 OH 0.0009 88,000.00 79.20
JUMLAH TENAGA KERJA 14,478.20
B. BAHAN
Kaca tebal 8 mm m2 1.100 220,000.00 242,000.00
Sealant Kg 0.070 28,000.00 1,960.00
JUMLAH HARGA BAHAN 243,960.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 258,438.20
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 258,438.20
4.6.2.19 Pemasangan 1 m2 kaca buram tebal 12 mm
A. TENAGA
Pekerja L.01 OH 0.025 55,000.00 1,375.00
Tukang Kayu L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.0013 88,000.00 114.40
JUMLAH TENAGA KERJA 21,289.40
B. BAHAN
Kaca Buram 12 mm m2 1.100 150,000.00 165,000.00
Sealant Kg 0.070 28,000.00 1,960.00
JUMLAH HARGA BAHAN 166,960.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 188,249.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 188,249.40
4.6.2.20 Pemasangan 1 m2 kaca cermin tebal 5 mm
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Kaca Cermin 5 mm m2 1.100 137,500.00 151,250.00
JUMLAH HARGA BAHAN 151,250.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 164,025.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 164,025.40
4.6.2.21 Pemasangan 1 m2 kaca cermin tebal 8 mm
A. TENAGA
Pekerja L.01 OH 0.017 55,000.00 935.00
Tukang Kayu L.02 OH 0.170 71,500.00 12,155.00
Kepala Tukang L.03 OH 0.017 77,000.00 1,309.00
Mandor L.04 OH 0.0009 88,000.00 79.20
JUMLAH TENAGA KERJA 14,478.20
B. BAHAN
Kaca Cermin 8 mm m2 1.100 214,500.00 235,950.00
JUMLAH HARGA BAHAN 235,950.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 250,428.20
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 250,428.20
4.6.2.22 Pemasangan 1 m2 kaca wireglassed tebal 5 mm
A. TENAGA
Pekerja L.01 OH 0.015 55,000.00 825.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.0008 88,000.00 70.40
JUMLAH TENAGA KERJA 12,775.40
B. BAHAN
Kaca wireglassed tebal 5 mm m2 1.100 605,000.00 665,500.00
JUMLAH HARGA BAHAN 665,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 678,275.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 678,275.40
4.6.2.23 Pemasangan 1 m2 kaca patri tebal 5 mm
A. TENAGA
Pekerja L.01 OH 0.075 55,000.00 4,125.00
Tukang Kayu L.02 OH 0.150 71,500.00 10,725.00
Kepala Tukang L.03 OH 0.015 77,000.00 1,155.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 16,357.00
B. BAHAN
Kaca patri tebal 5 mm m2 1.100 1,100,000.00 1,210,000.00
Sealant Kg 0.050 28,000.00 1,400.00
JUMLAH HARGA BAHAN 1,210,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,226,357.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,226,357.00

4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
4.7.1.1 Pengikisan/pengerokan 1 m2 permukaan cat lama
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 8,514.00
B. BAHAN
Soda Api Kg 0.050 18,700.00 935.00
JUMLAH HARGA BAHAN 935.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 9,449.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 9,449.00
4.7.1.2 Pencucian1 m2 bidang permukaan tembok yang pernah dicat
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 8,514.00
B. BAHAN
Sabun Kg 0.050 13,700.00 685.00
JUMLAH HARGA BAHAN 685.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 9,199.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 9,199.00
4.7.1.3 Pengerokan 1 m2 karat lama permukaan baja dengan cara manual
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Mandor L.04 OH 0.008 88,000.00 704.00
JUMLAH TENAGA KERJA 8,954.00
B. BAHAN
Sabun Kg 0.050 13,700.00 685.00
JUMLAH HARGA BAHAN 685.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 9,639.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 9,639.00
4.7.1.4 Pengecatan 1 m2 bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
Pekerja L.01 OH 0.070 55,000.00 3,850.00
Tukang Cat L.02 OH 0.009 71,500.00 643.50
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 5,219.50
B. BAHAN
Cat meni Kg 0.200 28,000.00 5,600.00
Plamir Kg 0.150 19,800.00 2,970.00
Cat dasar Kg 0.170 45,000.00 7,650.00
Cat penutup Kg 0.260 45,000.00 11,700.00
Kuas Bh 0.010 11,200.00 112.00
Pengencer Kg 0.030 11,500.00 345.00
Ampelas Lbr 0.200 3,200.00 640.00
JUMLAH HARGA BAHAN 29,017.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 34,236.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 34,236.50
4.7.1.5 Pengecatan 1 m2 bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup)
A. TENAGA
Pekerja L.01 OH 0.070 55,000.00 3,850.00
Tukang Cat L.02 OH 0.105 71,500.00 7,507.50
Kepala Tukang L.03 OH 0.004 77,000.00 308.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 11,929.50
B. BAHAN
Cat meni Kg 0.200 28,000.00 5,600.00
Plamir Kg 0.150 19,800.00 2,970.00
Cat dasar Kg 0.170 45,000.00 7,650.00
Cat penutup Kg 0.350 45,000.00 15,750.00
Kuas Bh 0.010 11,200.00 112.00
Pengencer Kg 0.030 11,500.00 345.00
Ampelas Lbr 0.200 3,200.00 640.00
JUMLAH HARGA BAHAN 33,067.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 44,996.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 44,996.50
4.7.1.6 Pelaburan 1 m2 bidang kayu dengan teak oil
A. TENAGA
Pekerja L.01 OH 0.040 55,000.00 2,200.00
Tukang Cat L.02 OH 0.063 71,500.00 4,504.50
Kepala Tukang L.03 OH 0.063 77,000.00 4,851.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 11,819.50
B. BAHAN
Teak Oil Ltr 0.360 60,000.00 21,600.00
JUMLAH HARGA BAHAN 21,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 33,419.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 33,419.50
4.7.1.7 Pelaburan 1 m2 bidang kayu dengan politur
A. TENAGA
Pekerja L.01 OH 0.040 55,000.00 2,200.00
Tukang Cat L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.016 77,000.00 1,232.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 7,986.00
B. BAHAN
Politur Ltr 0.150 26,600.00 3,990.00
Politur Jadi Ltr 0.372 39,000.00 14,508.00
Ampelas Lbr 2.000 3,200.00 6,400.00
JUMLAH HARGA BAHAN 24,898.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 32,884.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 32,884.00
4.7.1.8 Pelaburan 1 m2 bidang kayu dengan cat residu dan ter
A. TENAGA
Pekerja L.01 OH 0.100 55,000.00 5,500.00
Mandor L.04 OH 0.006 88,000.00 528.00
JUMLAH TENAGA KERJA 6,028.00
B. BAHAN
Residu atau Ter Ltr 0.350 18,000.00 6,300.00
JUMLAH HARGA BAHAN 6,300.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 12,328.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 12,328.00
4.7.1.9 Pelaburan 1 m2 bidang kayu dengan vernis
A. TENAGA
Pekerja L.01 OH 0.160 55,000.00 8,800.00
Tukang Cat L.02 OH 0.160 71,500.00 11,440.00
Kepala Tukang L.03 OH 0.016 77,000.00 1,232.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 21,736.00
B. BAHAN
Vernis Ltr 0.150 35,000.00 5,250.00
Dempul Kg 0.050 19,300.00 965.00
Ampelas Lbr 0.100 3,200.00 320.00
JUMLAH HARGA BAHAN 6,535.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 28,271.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 28,271.00
4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
Pekerja L.01 OH 0.020 55,000.00 1,100.00
Tukang Cat L.02 OH 0.063 71,500.00 4,504.50
Kepala Tukang L.03 OH 0.0063 77,000.00 485.10
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 6,353.60
B. BAHAN
Plamir Kg 0.100 19,800.00 1,980.00
Cat Dasar Kg 0.100 27,500.00 2,750.00
Cat Penutup Kg 0.260 27,500.00 7,150.00
JUMLAH HARGA BAHAN 11,880.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 18,233.60
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 18,233.60
4.7.1.11 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
Pekerja L.01 OH 0.028 55,000.00 1,540.00
Tukang Cat L.02 OH 0.042 71,500.00 3,003.00
Kepala Tukang L.03 OH 0.0042 77,000.00 323.40
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 5,130.40
B. BAHAN
Cat Dasar Kg 0.120 27,500.00 3,300.00
Cat Penutup Kg 0.180 27,500.00 4,950.00
JUMLAH HARGA BAHAN 8,250.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 13,380.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 13,380.40
4.7.1.12 Pelaburan 1 m2 tembok dengan kalkarium
A. TENAGA
Pekerja L.01 OH 0.028 55,000.00 1,540.00
Tukang Cat L.02 OH 0.042 71,500.00 3,003.00
Kepala Tukang L.03 OH 0.0042 77,000.00 323.40
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 5,130.40
B. BAHAN
Kalkarium Kg 0.100 17,000.00 1,700.00
JUMLAH HARGA BAHAN 1,700.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 6,830.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 6,830.40
4.7.1.13 Pelaburan 1 m2 tembok dengan kapur sirih
A. TENAGA
Pekerja L.01 OH 0.150 55,000.00 8,250.00
Tukang Cat L.02 OH 0.001 71,500.00 71.50
Kepala Tukang L.03 OH 0.0001 77,000.00 7.70
Mandor L.04 OH 0.0025 88,000.00 220.00
JUMLAH TENAGA KERJA 8,549.20
B. BAHAN
Kapur sirih Kg 0.150 3,500.00 525.00
Ampelas Kg 0.100 3,200.00 320.00
Alang-alang Kg 0.250 5,500.00 1,375.00
JUMLAH HARGA BAHAN 2,220.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 10,769.20
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 10,769.20
4.7.1.14 Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan)
A. TENAGA
Pekerja L.01 OH 0.040 55,000.00 2,200.00
Tukang Cat L.02 OH 0.005 71,500.00 357.50
Kepala Tukang L.03 OH 0.0005 77,000.00 38.50
Mandor L.04 OH 0.0025 88,000.00 220.00
JUMLAH TENAGA KERJA 2,816.00
B. BAHAN
Kapur sirih Kg 0.300 3,500.00 1,050.00
Ampelas Kg 0.200 3,200.00 640.00
Alang-alang Kg 0.250 5,500.00 1,375.00
JUMLAH HARGA BAHAN 3,065.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,881.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 5,881.00
4.7.1.15 Pemasangan 1 m2 wallpaper
A. TENAGA
Pekerja L.01 OH 0.020 55,000.00 1,100.00
Tukang Cat L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.0025 88,000.00 220.00
JUMLAH TENAGA KERJA 17,160.00
B. BAHAN
Wallpaper m2 1.200 115,000.00 138,000.00
Lem Kg 0.200 27,500.00 5,500.00
JUMLAH HARGA BAHAN 143,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 160,660.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 160,660.00
4.7.1.16 Pengecatan 1 m2 permukaan baja dengan meni besi
A. TENAGA
Pekerja L.01 OH 0.020 55,000.00 1,100.00
Tukang Cat L.02 OH 0.200 71,500.00 14,300.00
Kepala Tukang L.03 OH 0.020 77,000.00 1,540.00
Mandor L.04 OH 0.0025 88,000.00 220.00
JUMLAH TENAGA KERJA 17,160.00
B. BAHAN
Meni Besi Kg 0.100 28,000.00 2,800.00
Kuas Bh 0.010 11,200.00 112.00
JUMLAH HARGA BAHAN 2,912.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 20,072.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 20,072.00
4.7.1.17 Pengecatan 1 m2 permukaan baja dengan meni besi dengan perancah
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Cat L.02 OH 0.225 71,500.00 16,087.50
Kepala Tukang L.03 OH 0.0225 77,000.00 1,732.50
Mandor L.04 OH 0.0075 88,000.00 660.00
JUMLAH TENAGA KERJA 32,230.00
B. BAHAN
Meni Besi Kg 0.100 28,000.00 2,800.00
Pengencer Ltr 0.010 11,500.00 115.00
Kuas Bh 0.010 11,200.00 112.00
Perancah Kayu m3 0.002 5,000,000.00 10,000.00
JUMLAH HARGA BAHAN 2,915.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 35,145.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 35,145.00
4.7.1.18 Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis
A. TENAGA
Pekerja L.01 OH 0.250 55,000.00 13,750.00
Tukang Cat L.02 OH 0.250 71,500.00 17,875.00
Kepala Tukang L.03 OH 0.025 77,000.00 1,925.00
Mandor L.04 OH 0.0013 88,000.00 114.40
JUMLAH TENAGA KERJA 33,664.40
B. BAHAN
Meni A Kg 0.100 18,500.00 1,850.00
Meni B Kg 0.010 15,000.00 150.00
Cat Kg 0.080 47,800.00 3,824.00
Kuas Bh 0.010 11,200.00 112.00
Pengencer Ltr 0.010 11,500.00 115.00
JUMLAH HARGA BAHAN 6,051.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,715.40
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 39,715.40
4.7.1.19 Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Cat L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.012 77,000.00 924.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 8,778.00
B. BAHAN
Cat Kg 0.300 47,800.00 14,340.00
Kuas Bh 0.010 11,200.00 112.00
Pengencer Ltr 0.010 11,500.00 115.00
JUMLAH HARGA BAHAN 14,567.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 23,345.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 23,345.00
4.7.1.20 Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Cat L.02 OH 0.800 71,500.00 57,200.00
Kepala Tukang L.03 OH 0.080 77,000.00 6,160.00
Mandor L.04 OH 0.020 88,000.00 1,760.00
JUMLAH TENAGA KERJA 87,120.00
B. BAHAN
Cat Dasar Kg 0.110 47,800.00 5,258.00
Cat Antara Kg 0.170 47,800.00 8,126.00
Cat Penutup Kg 0.080 47,800.00 3,824.00
Kuas Bh 0.010 11,200.00 112.00
Pengencer Ltr 0.010 11,500.00 115.00
JUMLAH HARGA BAHAN 17,435.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 104,555.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 104,555.00
4.7.1.21 Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
A. TENAGA
Pekerja L.01 OH 0.400 55,000.00 22,000.00
Tukang Cat L.02 OH 0.700 71,500.00 50,050.00
Kepala Tukang L.03 OH 0.070 77,000.00 5,390.00
Mandor L.04 OH 0.020 88,000.00 1,760.00
JUMLAH TENAGA KERJA 79,200.00
B. BAHAN
Cat Dasar Kg 0.300 47,800.00 14,340.00
Pengencer Ltr 0.010 11,500.00 115.00
JUMLAH HARGA BAHAN 14,455.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 93,655.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 93,655.00

5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
( Rp ) ( Rp )
5.1.1.1 Pemasangan 1 buah closet duduk/monoblock
A. TENAGA
Pekerja L.01 OH 3.300 55,000.00 181,500.00
Tukang Batu L.02 OH 1.100 71,500.00 78,650.00
Kepala Tukang L.03 OH 0.010 77,000.00 770.00
Mandor L.04 OH 0.160 88,000.00 14,080.00
JUMLAH TENAGA KERJA 275,000.00
B. BAHAN
Closet Duduk Unit 1.000 1,850,000.00 1,850,000.00
Perlengkapan Ls 0.060 1,850,000.00 111,000.00
JUMLAH HARGA BAHAN 1,961,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 2,236,000.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 2,236,000.00
5.1.1.2 Pemasangan 1 buah closet jongkok porselen
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Batu L.02 OH 1.500 71,500.00 107,250.00
Kepala Tukang L.03 OH 0.150 77,000.00 11,550.00
Mandor L.04 OH 0.160 88,000.00 14,080.00
JUMLAH TENAGA KERJA 187,880.00
B. BAHAN
Closet Jongkok porselen Unit 1.000 203,500.00 203,500.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir Pasang m3 0.010 132,000.00 1,320.00
JUMLAH HARGA BAHAN 213,220.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 401,100.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 401,100.00
5.1.1.3 Pemasangan 1 buah closet jongkok teraso
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Batu L.02 OH 1.500 71,500.00 107,250.00
Kepala Tukang L.03 OH 0.150 77,000.00 11,550.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 178,200.00
B. BAHAN
Closet Jongkok teraso Unit 1.000 88,000.00 88,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir Pasang m3 0.010 132,000.00 1,320.00
Bata Merah Bh 7.000 750.00 5,250.00
JUMLAH HARGA BAHAN 102,970.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 281,170.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 281,170.00
5.1.1.4 Pemasangan 1 buah urinoir
A. TENAGA
Pekerja L.01 OH 1.000 55,000.00 55,000.00
Tukang Batu L.02 OH 1.000 71,500.00 71,500.00
Kepala Tukang L.03 OH 0.100 77,000.00 7,700.00
Mandor L.04 OH 0.050 88,000.00 4,400.00
JUMLAH TENAGA KERJA 138,600.00
B. BAHAN
Urinoir Unit 1.000 2,000,000.00 2,000,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir Pasang m3 0.010 132,000.00 1,320.00
Perlengkapan % 0.300 2,000,000.00 600,000.00
JUMLAH HARGA BAHAN 2,609,720.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 2,748,320.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 2,748,320.00
5.1.1.5 Pemasangan 1 buah wastafel
A. TENAGA
Pekerja L.01 OH 1.200 55,000.00 66,000.00
Tukang Batu L.02 OH 1.450 71,500.00 103,675.00
Kepala Tukang L.03 OH 0.150 77,000.00 11,550.00
Mandor L.04 OH 0.060 88,000.00 5,280.00
JUMLAH TENAGA KERJA 186,505.00
B. BAHAN
Wastafel Unit 1.200 522,500.00 627,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir Pasang m3 0.010 132,000.00 1,320.00
Perlengkapan % 0.120 627,000.00 75,240.00
JUMLAH HARGA BAHAN 711,960.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 898,465.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 898,465.00
5.1.1.6 Pemasangan 1 buah bathcuip porselen
A. TENAGA
Pekerja L.01 OH 0.075 55,000.00 4,125.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.075 77,000.00 5,775.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 63,789.00
B. BAHAN
Bathcuip Unit 1.000 26,400.00 26,400.00
Perlengkapan % 0.200 26,400.00 5,280.00
JUMLAH HARGA BAHAN 31,680.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 95,469.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 95,469.00
5.1.1.7 Pemasangan 1 buah bak fiberglass vol 1 m3
A. TENAGA
Pekerja L.01 OH 3.000 55,000.00 165,000.00
Tukang Batu L.02 OH 4.500 71,500.00 321,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.900 88,000.00 79,200.00
JUMLAH TENAGA KERJA 569,800.00
B. BAHAN
Bak Fiberglass Unit 1.000 275,000.00 275,000.00
Perlengkapan Ls 0.120 275,000.00 33,000.00
JUMLAH HARGA BAHAN 308,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 877,800.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 877,800.00
5.1.1.8 Pemasangan 1 buah bak mandi batu bata vol 0,30 m3
A. TENAGA
Pekerja L.01 OH 6.000 55,000.00 330,000.00
Tukang Batu L.02 OH 3.000 71,500.00 214,500.00
Kepala Tukang L.03 OH 0.300 77,000.00 23,100.00
Mandor L.04 OH 0.030 88,000.00 2,640.00
JUMLAH TENAGA KERJA 570,240.00
B. BAHAN
Bata Merah Bh 150.000 750.00 112,500.00
Semen Portland Kg 120.000 1,400.00 168,000.00
Pasir Pasang m3 0.300 132,000.00 39,600.00
Porselen 11 x 11 Bh 360.000 700.00 252,000.00
Semen Warna Kg 6.000 11,000.00 66,000.00
JUMLAH HARGA BAHAN 638,100.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,208,340.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 1,208,340.00
5.1.1.9 Pemasangan 1 buah bak mandi teraso vol 0,30 m3
A. TENAGA
Pekerja L.01 OH 2.100 55,000.00 115,500.00
Tukang Batu L.02 OH 0.750 71,500.00 53,625.00
Kepala Tukang L.03 OH 0.070 77,000.00 5,390.00
Mandor L.04 OH 0.110 88,000.00 9,680.00
JUMLAH TENAGA KERJA 184,195.00
B. BAHAN
Bak teraso Bh 1.000 85,000.00 85,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir Pasang m3 0.010 132,000.00 1,320.00
JUMLAH HARGA BAHAN 94,720.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 278,915.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 278,915.00
5.1.1.10 Pemasangan 1 buah bak air fiberglass vol 1 m3
A. TENAGA
Pekerja L.01 OH 3.000 55,000.00 165,000.00
Tukang Batu L.02 OH 0.450 71,500.00 32,175.00
Kepala Tukang L.03 OH 0.045 77,000.00 3,465.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 201,960.00
B. BAHAN
Bak air fiberglass Unit 1.000 225,000.00 225,000.00
Perlengkapan Ls 0.120 225,000.00 27,000.00
JUMLAH HARGA BAHAN 252,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 453,960.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 453,960.00
5.1.1.11 Pemasangan 1 buah bak beton vol 1 m3
A. TENAGA
Pekerja L.01 OH 3.500 55,000.00 192,500.00
Tukang Batu L.02 OH 4.500 71,500.00 321,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.018 88,000.00 1,584.00
JUMLAH TENAGA KERJA 519,684.00
B. BAHAN
Beton 1 : 2 : 3 m3 0.900 899,897.23 809,907.51
Baja Tulangan Kg 180.000 12,014.60 2,162,628.00
Kayu Begisting m2 8.000 - -
Ubin Porselen Bh 5.000 1,100.00 5,500.00
Perlengkapan % 0.100 913,011.83 91,301.18
JUMLAH HARGA BAHAN 3,069,336.69
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 3,589,020.69
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 3,589,020.69
5.1.1.12 Pemasangan 1 buah bak cuci piring stainlessteel
A. TENAGA
Pekerja L.01 OH 0.030 55,000.00 1,650.00
Tukang Batu L.02 OH 0.300 71,500.00 21,450.00
Kepala Tukang L.03 OH 0.030 77,000.00 2,310.00
Mandor L.04 OH 0.015 88,000.00 1,320.00
JUMLAH TENAGA KERJA 26,730.00
B. BAHAN
Bak cuci stainless steel Unit 1.000 250,000.00 250,000.00
Water drain Bh 1.000 85,000.00 85,000.00
JUMLAH HARGA BAHAN 335,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 361,730.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 361,730.00
5.1.1.13 Pemasangan 1 buah bak cuci piring teraso
A. TENAGA
Pekerja L.01 OH 0.050 55,000.00 2,750.00
Tukang Batu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.025 88,000.00 2,200.00
JUMLAH TENAGA KERJA 44,550.00
B. BAHAN
Bak cuci teraso Unit 1.000 150,000.00 150,000.00
Water drain Bh 1.000 85,000.00 85,000.00
Semen Portland Kg 20.000 1,400.00 28,000.00
Pasir Pasang m3 0.050 132,000.00 6,600.00
JUMLAH HARGA BAHAN 269,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 314,150.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 314,150.00
5.1.1.14 Pemasangan 1 buah floor drain
A. TENAGA
Pekerja L.01 OH 0.050 55,000.00 2,750.00
Tukang Batu L.02 OH 0.500 71,500.00 35,750.00
Kepala Tukang L.03 OH 0.050 77,000.00 3,850.00
Mandor L.04 OH 0.025 88,000.00 2,200.00
JUMLAH TENAGA KERJA 44,550.00
B. BAHAN
Floor drain Bh 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 69,550.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 69,550.00
5.1.1.15 Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 cm tinggi 35 cm
A. TENAGA
Pekerja L.01 OH 2.160 55,000.00 118,800.00
Tukang Batu L.02 OH 0.720 71,500.00 51,480.00
Kepala Tukang L.03 OH 0.072 77,000.00 5,544.00
Mandor L.04 OH 0.011 88,000.00 968.00
JUMLAH TENAGA KERJA 176,792.00
B. BAHAN
Bata Merah Bh 40.000 750.00 30,000.00
Semen Portland Kg 44.000 1,400.00 61,600.00
Pasir Pasang m3 0.070 132,000.00 9,240.00
Pasir Beton m3 0.060 200,000.00 12,000.00
Kerikil m3 0.070 185,300.00 12,971.00
Baja Tulangan Kg 1.600 12,014.60 19,223.36
JUMLAH HARGA BAHAN 145,034.36
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 321,826.36
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 321,826.36
5.1.1.16 Pemasangan 1 buah bak kontrol pasangan bata 45 x 45 cm tinggi 50 cm
A. TENAGA
Pekerja L.01 OH 3.200 55,000.00 176,000.00
Tukang Batu L.02 OH 1.150 71,500.00 82,225.00
Kepala Tukang L.03 OH 0.011 77,000.00 847.00
Mandor L.04 OH 0.016 88,000.00 1,408.00
JUMLAH TENAGA KERJA 260,480.00
B. BAHAN
Bata Merah Bh 70.000 750.00 52,500.00
Semen Portland Kg 77.000 1,400.00 107,800.00
Pasir Pasang m3 0.130 132,000.00 17,160.00
Pasir Beton m3 0.090 200,000.00 18,000.00
Kerikil m3 0.020 185,300.00 3,706.00
Baja Tulangan Kg 2.600 12,014.60 31,237.96
JUMLAH HARGA BAHAN 230,403.96
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 490,883.96
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 490,883.96
5.1.1.17 Pemasangan 1 buah bak kontrol pasangan bata 60 x 60 cm tinggi 65 cm
A. TENAGA
Pekerja L.01 OH 3.200 55,000.00 176,000.00
Tukang Batu L.02 OH 1.150 71,500.00 82,225.00
Kepala Tukang L.03 OH 0.011 77,000.00 847.00
Mandor L.04 OH 0.016 88,000.00 1,408.00
JUMLAH TENAGA KERJA 260,480.00
B. BAHAN
Bata Merah Bh 123.000 750.00 92,250.00
Semen Portland Kg 114.000 1,400.00 159,600.00
Pasir Pasang m3 0.184 132,000.00 24,288.00
Pasir Beton m3 0.120 200,000.00 24,000.00
Kerikil m3 0.033 185,300.00 6,114.90
Baja Tulangan Kg 4.850 12,014.60 58,270.81
JUMLAH HARGA BAHAN 364,523.71
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 625,003.71
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 625,003.71
5.1.1.18 Pemasangan 1 m' pipa galvanis diameter 1/2"
A. TENAGA
Pekerja L.01 OH 0.054 55,000.00 2,970.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.027 88,000.00 2,376.00
JUMLAH TENAGA KERJA 12,474.00
B. BAHAN
Pipa galvanis 1/2" m 1.200 19,166.67 23,000.00
Perlengkapan Ls 0.350 19,166.67 6,708.33
JUMLAH HARGA BAHAN 29,708.33
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 42,182.33
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 42,182.33
5.1.1.19 Pemasangan 1 buah kran diameter 1/2" atau 3/4"
A. TENAGA
Pekerja L.01 OH 0.010 55,000.00 550.00
Tukang Batu L.02 OH 0.400 71,500.00 28,600.00
Kepala Tukang L.03 OH 0.040 77,000.00 3,080.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 32,670.00
B. BAHAN
Kran Air m 1.000 23,600.00 23,600.00
Sealtape Bh 0.025 3,500.00 87.50
JUMLAH HARGA BAHAN 23,687.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 56,357.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 56,357.50
5.1.1.20 Pemasangan 1 m' pipa galvanis diameter 3/4"
A. TENAGA
Pekerja L.01 OH 0.054 55,000.00 2,970.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.027 88,000.00 2,376.00
JUMLAH TENAGA KERJA 12,474.00
B. BAHAN
Pipa galvanis 3/4" m 1.200 24,750.00 29,700.00
Perlengkapan % 0.350 24,750.00 8,662.50
JUMLAH HARGA BAHAN 38,362.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 50,836.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 50,836.50
5.1.1.21 Pemasangan 1 m' pipa galvanis diameter 1"
A. TENAGA
Pekerja L.01 OH 0.054 55,000.00 2,970.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.027 88,000.00 2,376.00
JUMLAH TENAGA KERJA 12,474.00
B. BAHAN
Pipa galvanis 1" m 1.200 40,000.00 48,000.00
Perlengkapan % 0.350 40,000.00 14,000.00
JUMLAH HARGA BAHAN 62,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 74,474.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 74,474.00
5.1.1.22 Pemasangan 1 m' pipa galvanis diameter 1 1/2"
A. TENAGA
Pekerja L.01 OH 0.108 55,000.00 5,940.00
Tukang Batu L.02 OH 0.180 71,500.00 12,870.00
Kepala Tukang L.03 OH 0.018 77,000.00 1,386.00
Mandor L.04 OH 0.005 88,000.00 440.00
JUMLAH TENAGA KERJA 20,636.00
B. BAHAN
Pipa galvanis 1 1/2" m 1.200 48,116.67 57,740.00
Perlengkapan % 0.350 48,116.67 16,840.83
JUMLAH HARGA BAHAN 74,580.83
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 95,216.83
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 95,216.83
5.1.1.23 Pemasangan 1 m' pipa galvanis diameter 3"
A. TENAGA
Pekerja L.01 OH 0.135 55,000.00 7,425.00
Tukang Batu L.02 OH 0.225 71,500.00 16,087.50
Kepala Tukang L.03 OH 0.023 77,000.00 1,771.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 25,899.50
B. BAHAN
Pipa galvanis 3" m 1.200 92,650.00 111,180.00
Perlengkapan % 0.350 92,650.00 32,427.50
JUMLAH HARGA BAHAN 143,607.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 169,507.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 169,507.00
5.1.1.24 Pemasangan 1 m' pipa galvanis diameter 4"
A. TENAGA
Pekerja L.01 OH 0.135 55,000.00 7,425.00
Tukang Batu L.02 OH 0.225 71,500.00 16,087.50
Kepala Tukang L.03 OH 0.023 77,000.00 1,771.00
Mandor L.04 OH 0.007 88,000.00 616.00
JUMLAH TENAGA KERJA 25,899.50
B. BAHAN
Pipa galvanis 4" m 1.200 131,750.00 158,100.00
Perlengkapan % 0.350 131,750.00 46,112.50
JUMLAH HARGA BAHAN 204,212.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 230,112.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 230,112.00
5.1.1.25 Pemasangan 1 m' pipa PVC type AW diameter 1/2"
A. TENAGA
Pekerja L.01 OH 0.036 55,000.00 1,980.00
Tukang Batu L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 6,908.00
B. BAHAN
Pipa PVC 1/2" m 1.200 3,500.00 4,200.00
Perlengkapan % 0.350 3,500.00 1,225.00
JUMLAH HARGA BAHAN 5,425.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 12,333.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 12,333.00
5.1.1.26 Pemasangan 1 m' pipa PVC type AW diameter 3/4"
A. TENAGA
Pekerja L.01 OH 0.036 55,000.00 1,980.00
Tukang Batu L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 6,908.00
B. BAHAN
Pipa PVC 3/4" m 1.200 4,583.33 5,500.00
Perlengkapan % 0.350 4,583.33 1,604.17
JUMLAH HARGA BAHAN 7,104.17
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,012.17
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 14,012.17
5.1.1.27 Pemasangan 1 m' pipa PVC type AW diameter 1"
A. TENAGA
Pekerja L.01 OH 0.036 55,000.00 1,980.00
Tukang Batu L.02 OH 0.060 71,500.00 4,290.00
Kepala Tukang L.03 OH 0.006 77,000.00 462.00
Mandor L.04 OH 0.002 88,000.00 176.00
JUMLAH TENAGA KERJA 6,908.00
B. BAHAN
Pipa PVC 1" m 1.200 6,416.67 7,700.00
Perlengkapan % 0.350 6,416.67 2,245.83
JUMLAH HARGA BAHAN 9,945.83
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 16,853.83
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 16,853.83
5.1.1.28 Pemasangan 1 m' pipa PVC type AW diameter 1 1/2"
A. TENAGA
Pekerja L.01 OH 0.054 55,000.00 2,970.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 10,362.00
B. BAHAN
Pipa PVC 1 1/2" m 1.200 10,283.33 12,340.00
Perlengkapan % 0.350 10,283.33 3,599.17
JUMLAH HARGA BAHAN 15,939.17
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 26,301.17
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 26,301.17
5.1.1.29 Pemasangan 1 m' pipa PVC type AW diameter 2"
A. TENAGA
Pekerja L.01 OH 0.054 55,000.00 2,970.00
Tukang Batu L.02 OH 0.090 71,500.00 6,435.00
Kepala Tukang L.03 OH 0.009 77,000.00 693.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 10,362.00
B. BAHAN
Pipa PVC 2" m 1.200 12,750.00 15,300.00
Perlengkapan % 0.350 12,750.00 4,462.50
JUMLAH HARGA BAHAN 19,762.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 30,124.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 30,124.50
5.1.1.30 Pemasangan 1 m' pipa PVC type AW diameter 2 1/2"
A. TENAGA
Pekerja L.01 OH 0.081 55,000.00 4,455.00
Tukang Batu L.02 OH 0.135 71,500.00 9,652.50
Kepala Tukang L.03 OH 0.0135 77,000.00 1,039.50
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 15,499.00
B. BAHAN
Pipa PVC 2 1/2" m 1.200 19,200.00 23,040.00
Perlengkapan % 0.350 19,200.00 6,720.00
JUMLAH HARGA BAHAN 29,760.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 45,259.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 45,259.00
5.1.1.31 Pemasangan 1 m' pipa PVC type AW diameter 3"
A. TENAGA
Pekerja L.01 OH 0.081 55,000.00 4,455.00
Tukang Batu L.02 OH 0.135 71,500.00 9,652.50
Kepala Tukang L.03 OH 0.0135 77,000.00 1,039.50
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 15,499.00
B. BAHAN
Pipa PVC 3" m 1.200 25,900.00 31,080.00
Perlengkapan % 0.350 25,900.00 9,065.00
JUMLAH HARGA BAHAN 40,145.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 55,644.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 55,644.00
5.1.1.32 Pemasangan 1 m' pipa PVC type AW diameter 4"
A. TENAGA
Pekerja L.01 OH 0.081 55,000.00 4,455.00
Tukang Batu L.02 OH 0.135 71,500.00 9,652.50
Kepala Tukang L.03 OH 0.0135 77,000.00 1,039.50
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 15,499.00
B. BAHAN
Pipa PVC 4" m 1.200 42,950.00 51,540.00
Perlengkapan % 0.350 42,950.00 15,032.50
JUMLAH HARGA BAHAN 66,572.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 82,071.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 82,071.50
5.1.1.33 Pemasangan 1 m' pipa air limbah jenis pipa tanah Ø 20 cm
A. TENAGA
Pekerja L.01 OH 0.080 55,000.00 4,400.00
Tukang Batu L.02 OH 0.040 71,500.00 2,860.00
Kepala Tukang L.03 OH 0.004 77,000.00 308.00
Mandor L.04 OH 0.004 88,000.00 352.00
JUMLAH TENAGA KERJA 7,920.00
B. BAHAN
Pipa Tanah Ø 20 cm Bh 1.600 - -
Semen Portland Kg 0.870 1,400.00 1,218.00
Pasir Pasang m3 0.014 132,000.00 1,848.00
Pasir Urug m3 0.014 70,000.00 980.00
JUMLAH HARGA BAHAN 4,046.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 11,966.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 11,966.00
5.1.1.34 Pemasangan 1 m' pipa air limbah jenis pipa tanah Ø 15 cm
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Batu L.02 OH 0.030 71,500.00 2,145.00
Kepala Tukang L.03 OH 0.003 77,000.00 231.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 5,940.00
B. BAHAN
Pipa Tanah Ø 15 cm Bh 1.600 - -
Semen Portland Kg 0.680 1,400.00 952.00
Pasir Pasang m3 0.013 132,000.00 1,716.00
Pasir Urug m3 0.011 70,000.00 770.00
JUMLAH HARGA BAHAN 3,438.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 9,378.00
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 9,378.00
5.1.1.35 Pemasangan 1 m' pipa beton Ø 15 - 20 cm
A. TENAGA
Pekerja L.01 OH 0.060 55,000.00 3,300.00
Tukang Batu L.02 OH 0.030 71,500.00 2,145.00
Kepala Tukang L.03 OH 0.003 77,000.00 231.00
Mandor L.04 OH 0.003 88,000.00 264.00
JUMLAH TENAGA KERJA 5,940.00
B. BAHAN
Pipa Beton Bh 1.100 - -
Bata Merah m3 0.027 750.00 20.25
Semen Portland Kg 3.920 1,400.00 5,488.00
Pasir Pasang m3 0.056 132,000.00 7,392.00
Pasir Urug m3 0.024 70,000.00 1,680.00
JUMLAH HARGA BAHAN 14,580.25
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 20,520.25
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 20,520.25
5.1.1.36 Pemasangan 1 m' pipa beton Ø 30 - 100 cm
A. TENAGA
Pekerja L.01 OH 0.380 55,000.00 20,900.00
Tukang Batu L.02 OH 0.190 71,500.00 13,585.00
Kepala Tukang L.03 OH 0.019 77,000.00 1,463.00
Mandor L.04 OH 0.019 88,000.00 1,672.00
JUMLAH TENAGA KERJA 37,620.00
B. BAHAN
Pipa Beton Bh 1.100 - -
Bata Merah m3 0.550 750.00 412.50
Semen Portland Kg 10.300 1,400.00 14,420.00
Pasir Pasang m3 0.061 132,000.00 8,052.00
Pasir Urug m3 0.069 70,000.00 4,830.00
JUMLAH HARGA BAHAN 27,714.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,334.50
E. Overhead & Profit (15%) 15% x D -
F. Harga Satuan Pekerjaan (D+E) 65,334.50
PERHITUNGAN BERAT BESI DAN BEGESTING TIAP 1 M3 BETON

DAFTAR BERAT BJTP PER METER :


Diameter Besi Berat Besi
(mm) (kg)
6 0.22160
8 0.39396
10 0.61556
12 0.88640
16 1.57582

BENTUK STRUKTUR TULANGAN


LEBAR TINGGI PANJANG PANJANG BERAT TOTAL BEGESTING
NO. SKET POTONGAN DIAMETER JUMLAH
(B) (H) (L) POTONGAN BESI/meter BESI 2x PAKAI
(mm) (mm) (mm) (mm) (mm) (kg) (kg) (m2)

1 BALOK INDUK 20/35


200 350 14286 Tul. Pokok Atas 12 4 57624 0.88640 51.078
Tul. Extra 10 2 28772 0.61556 17.711
Tul. Pokok Bawah 12 2 28572 0.88640 25.326
Beugel - 150 8 96 105600 0.39396 41.602
135.72 5.01

2 BALOK ANAK 15/30


150 300 22223 Tul. Pokok Atas 12 3 67029 0.88640 59.415
Tul. Extra 10 2 44646 0.61556 27.482
Tul. Pokok Bawah 12 2 44446 0.88640 39.397
Beugel - 150 8 149 134100 0.39396 52.829
179.12 6.67

3 BALOK SLOOF 20/30


200 200 25000 Tul. Pokok Atas 12 3 75360 0.88640 66.799
Tul. Extra 10 2 50200 0.61556 30.901
Tul. Pokok Bawah 12 2 50000 0.88640 44.320
Beugel - 150 8 167 133600 0.39396 52.632
194.65 5.00

4 BALOK 15/20
150 200 33334 Tul. Pokok Atas 12 3 100362 0.88640 88.961
Tul. Extra
Tul. Pokok Bawah 12 2 66668 0.88640 59.095
Beugel - 150 8 223 156100 0.39396 61.496
209.55 6.67

5 BALOK RING 15/15


150 150 44445 Tul. Pokok Atas 12 3 133695 0.88640 118.507
Tul. Extra
Tul. Pokok Bawah 12 2 88890 0.88640 78.792
Beugel - 150 8 297 178200 0.39396 70.203
267.50 6.67

6 KOLOM 20/20
200 200 25000 Tul. Pokok 12 4 100480 0.88640 89.065
Tul. Extra 10 4 100400 0.61556 61.802
Beugel - 200 8 125 100000 0.39396 39.396
190.26 5.00

7 KOLOM 15/15
150 150 44445 Tul. Pokok 12 4 178260 0.88640 158.010
Tul. Extra
Beugel - 200 8 223 133800 0.39396 52.711
210.72 6.67

8 STRAUSS PILE D.25


- 250 20383 Tul. Pokok Atas 12 4 82012 0.88640 72.695
Tul. Extra
Tul. Pokok Bawah 12 4 82012 0.88640 72.695
Beugel - 150 8 136 117640 0.39396 46.345
191.74 -

9 POOR 20.80.80
200 800 6250 Tul. Pokok Atas 12 6 95625 0.61556 58.863
Tul. Extra
Tul. Pokok Bawah 12 6 95625 0.61556 58.863
Beugel - 150
117.73 -

10 PELAT t. 12 cm. (1 layer)


1000 120 8334 Tul. Y - 150 8 7 58898 0.39396 23.203
Tul. X - 150 8 56 60480 0.39396 23.826
1 layer 47.03 5.29
2 layer 94.06

11 PELAT t. 7 cm.
1000 70 14286 Tul. Y - 150 8 7 100562 0.39396 39.617
Tul. X - 150 8 96 103680 0.39396 40.845
1 layer 80.46 8.22
2 layer 160.92
BACK UP VOLUME

NO. PEKERJAAN URAIAN


I PEK. TANAH

1 GALIAN TANAH PONDASI ST = 0.05 x 3.00 x 17.00 = 2.50


POND. UTUH = 1.00 x 1.00 x 82.38 = 82.38
SET. POND = 0.90 x 1.00 x 59.50 = 53.55
= 138.43

2 URUGAN PASIR BAWAH PONDASI = 0.90 x 0.10 x 82.38 = 7.41


= 0.80 x 0.10 x 59.50 = 4.76
= 12.17

3 URUGAN SIRTU BAWAH LANTAI = 1.50 x 3.50 x 0.20 = 1.05


= 3.00 x 4.50 x 0.20 = 2.70
= 3.50 x 5.00 x 0.20 = 3.50
= 1.50 x 1.50 x 0.20 = 0.45
= 6.50 x 4.50 x 0.20 = 5.61
= 3.00 x 4.50 x 0.20 = 2.70
= 3.00 x 2.00 x 0.20 = 1.20
= 3.00 x 3.00 x 0.20 = 1.80
= 2.00 x 5.00 x 0.20 = 2.00
= 5.00 x 4.20 x 0.20 = 2.73
= 1.50 x 1.50 x 0.20 = 0.45
= 1.50 x 1.20 x 0.20 = 0.36
= 2.20 x 1.18 x 0.20 = 0.52
= 8.00 x 3.50 x 0.20 = 3.26
= 1.50 x 1.10 x 0.20 = (2.01)
= 26.32

4 URUGAN TANAH KEMBALI = 0.3 + 0.80


82.38 - x 0.80
2.00

= 0.3 + 0.80
59.50 - x 0.80
2.00

II PASANGAN DAN PLESTERAN

1 AANSTAMPENG = 1.00 x 0.20 x 82.38 = 16.48


= 0.90 x 0.20 x 59.50 = 10.71
= 27.19

2 PAS. BATU KALI 1 : 3 : 8 = 0.30 + 0.80


x 0.80 x 82.38
2.00

= 0.30 + 0.80
x 0.80 x 59.50
2.00

3 PAS. BATU BATA 1 : 3 = 0.30 x 122.38


= 0.30 x 16.50
5 PAS. BATU BATA 1 : 6 TEMBOK = 53.25 x 3.60
TEMBOK = 18.05 x 4.00
TEMBOK LT.2 = 42.75 x 3.90
TEMBOK PAGAR = 9.00 x 2.00
TEMBOK = 6.25 x 2.00
GEWEL 1 0.50 x 11.29 x 4.13 x 2.00
GEWEL 2 0.50 x 4.50 x 2.03 x 1.00
GEWEL 3 0.50 x 6.65 x 2.75 x 1.00
GEWEL 4 8.45 + 5.10
2.00
GEWEL 5 = 6.65 x 1.85 x 1.00
GEWEL 6 = 3.83 x 1.85 x 1.00

LUAS KUSEN
PAS. BATA 1:3

6 PLESTERAN Plesteran 1 : 6 = 463.16 x 2.00


plesteran 1:3

Plesteran 1 : 3 = 122.38 x 0.30 x 2.00


= 16.50 x 0.30 x 2.00

Plesteran beton BL 15/15 = 0.30 x 6.50


BL 15/20 = 0.40 x 99.13
BL 15/30 = 0.60 x 6.50
BL 20/35 = 0.70 x 59.50
GWL 15/15 = 0.30 x 81.59
KLM 20/20 = 0.40 x 3.60 x 17.00
KLM 15/15 = 0.30 x 4.00 x 24.00
KLM 15/15 = 0.30 x 3.90 x 14.00
KLM PAGAR 15/15 = 0.30 x 2.00 x 7.00

7 BENANGAN KLM = 3.60 x 17.00


= 4.00 x 24.00
= 3.60 x 14.00
= 2.00 x 7.00
BL = 0.30 x 6.50
= 0.40 x 99.13
= 0.60 x 6.50
= 0.70 x 59.50
= 0.30 x 81.59

III PEKERJAAN BETON

1 STROUSE d.30 = 0.79 x 0.06 x 3.00 x 17.00

2 POOR 20.80.80 = 0.20 x 0.80 x 0.80 x 17.00

3 SLOOF 20/30 = 0.20 x 0.30 x 59.00 x 1.00

4 SLOOF 15/20 = 0.20 x 0.30 x 99.13 x 1.00

5 BALOK LATEI 15/20 = 0.15 x 0.20 x 114.05 x 1.00

6 BALOK RING 15/15 = 0.15 x 0.15 x 11.80 x 1.00

7 BALOK INDUK 20/35 = 0.20 x 0.35 x 59.50 x 1.00

8 BALOK ANAK 15/30 = 0.15 x 0.30 x 6.50 x 1.00

9 BALOK GEWEL 15/15 = 0.15 x 0.15 x 81.59 x 1.00

10 KOLOM 15/15 = 0.15 x 0.15 x 3.60 x 5.00


= 0.15 x 0.15 x 4.00 x 24.00
= 0.15 x 0.15 x 3.90 x 14.00
= 0.15 x 0.15 x 2.00 x 7.00
= 0.15 x 0.15 x 7.50 x 3.00

11 KOLOM 20/20 = 0.20 x 0.20 x 3.60 x 17.00

12 PLAT BETON 12 CM = 0.12 x 3.50 x 6.00 x 1.00


= 0.12 x 3.00 x 4.50 x 1.00
= 0.12 x 3.00 x 8.00 x 1.00

13 PLAT BETON 7 CM = 0.70 x 3.40 x 0.70 x 1.00


= 0.70 x 1.50 x 0.70 x 1.00
= 0.70 x 1.80 x 0.70 x 1.00
13 PLAT TANGGA 12cm = 0.12 x 7.35 x 0.90 x 1.00

IV PEKERJAAN KUSEN, PINTU, JENDELA

1 KUSEN P1 1.52
2.06
2.06
5.64 x 1.00 = 5.64 m'

P2 1.12
2.06
2.06
5.24 x 6.00 = 31.44 m'

P3 1.12
2.06
2.06
5.24 x 2.00 = 10.48 m'

P5 1.12
2.06
2.06
5.24 x 1.00 = 5.24 m'

P6 3.32
2.06
2.06
7.44 x 1.00 = 7.44 m'

PJ 1.78
0.82
2.06
2.06
1.32
8.04 x 2.00 = 16.08 m'

J1 1.38
1.38
1.32
1.32
1.32
6.72 x 1.00 = 6.72 m'

J2 0.82
0.82
1.62
1.62
4.88 x 4.00 = 19.52 m'

J3 0.92
0.92
1.72
1.72
5.28 x 2.00 = 10.56 m'

J4 0.92
0.92
1.32
1.32
4.48 x 2.00 = 8.96 m'

J5 1.58
1.58
0.74
0.74
1.44
1.44
7.52 x 1.00 = 7.52 m'

J6 0.72
0.72
0.52
0.52
1.44
1.44
5.36 x 1.00 = 5.36 m'

BV 0.72
0.72
0.42
0.42
2.28 x 3.00 = 6.84 m'

JUMLAH TOTAL = 141.80 m' x

2 DAUN PINTU P1 = 1.21 x 2.01 x 1.00 =


P2 = 0.81 x 2.01 x 6.00 =
P3 = 0.81 x 2.01 x 2.00 =
P5 = 0.81 x 2.01 x 1.00 =
P6 = 3.02 x 2.01 x 1.00 =

PJ = 0.81 x 2.01 x 2.00 =


0.61 x 1.21 x 2.00 =
=

3 DAUN JENDELA J1 = 0.51 x 1.21 x 2.00 =


J2 = 0.51 x 1.51 x 4.00 =
J3 = 0.61 x 1.61 x 2.00 =
J4 = 0.61 x 1.21 x 2.00 =
J5 = 0.61 x 0.41 x 1.00 =

4 KACA BENING 5 MM P1 = 0.15 x 1.50 x 1.00 =


P3 = 0.15 x 1.50 x 2.00 =
PJ = 0.42 x 1.02 x 2.00 =
J1 = 0.32 x 1.02 x 4.00 =
J2 = 0.34 x 1.34 x 4.00 =
J3 = 0.42 x 1.42 x 2.00 =
J4 = 0.42 x 1.02 x 2.00 =
J5 = 0.60 x 1.32 x 1.00 =
= 0.44 x 0.22 x 1.00 =
BV = 4.00 x 0.25 x 3.00 =
=

V PEKERJAAN ATAP

1 NOK 8/12 = 0.08 x 0.12 x 23.90 x 1.00

2 GORDING 8/12 = 0.08 x 0.12 x 49.00 x 1.00

3 BALOK TEMBOK 8/12 = 0.08 x 0.12 x 47.00 x 1.00

4 KONSOL 6/10 = 0.80 x 0.12 x 9.00 x 1.00

5 KUDA-KUDA 8/12 = 0.80 x 0.12 x 17.20 x 3.00

6 JURAI = 0.80 x 0.12 x 4.47 x 4.00


= 0.80 x 0.12 x 3.70 x 2.00

7 PASANG USUK DAN RENG L1 = 104.16 m2


L2 = 91.37 m2
= 195.53 m2

8 LISPLANK = 0.02 x 0.30 x =

9 TALANG SENG - =

10 PLAFOND ETERNIT = 1.50 x 3.50 x 1.00 =


= 3.00 x 4.50 x 1.00 =
= 3.50 x 5.00 x 1.00 =
= 1.50 x 1.50 x 1.00 =
= 6.50 x 4.50 x 1.00 =
= 3.00 x 4.50 x 1.00 =
= 3.00 x 2.00 x 1.00 =
= 3.00 x 3.00 x 1.00 =
= 2.00 x 5.00 x 1.00 =
= 5.00 x 4.20 x 1.00 =
= 1.50 x 1.50 x 1.00 =
= 1.50 x 1.20 x 1.00 =
= 2.20 x 1.18 x 1.00 =
= 8.00 x 3.50 x 1.00 =
= 1.50 x 1.10 x 1.00 =
= 1.50 x 3.50 x 1.00 =
= 3.50 x 4.50 x 1.00 =
= 3.00 x 4.00 x 1.00 =
= 4.50 x 3.00 x 1.00 =
= 46.90 x 0.70 x 1.00 =
=

11 LIST ETERNIT = 2.00 x 1.50 + 3.50 =


= 2.00 x 3.00 + 4.50 =
= 2.00 x 3.50 + 5.00 =
= 2.00 x 1.50 + 1.50 =
= 2.00 x 6.50 + 4.50 =
= 2.00 x 3.00 + 4.50 =
= 2.00 x 3.00 + 2.00 =
= 2.00 x 3.00 + 3.00 =
= 2.00 x 2.00 + 5.00 =
= 2.00 x 5.00 + 4.20 =
= 2.00 x 1.50 + 1.50 =
= 2.00 x 1.50 + 1.20 =
= 2.00 x 2.20 + 1.18 =
= 2.00 x 8.00 + 3.50 =
= 2.00 x 1.50 + 1.10 =
= 2.00 x 1.50 + 3.50 =
= 2.00 x 3.50 + 4.50 =
= 2.00 x 3.00 + 4.00 =
= 2.00 x 4.50 + 3.00 =
= 2.00 x 46.90 + 0.70 =
=

VI PEKERJAAN LANTAI

1 RABAT BETON = 1.50 x 3.50 x 1.00 =


= 3.00 x 4.50 x 1.00 =
= 3.50 x 5.00 x 1.00 =
= 1.50 x 1.50 x 1.00 =
= 6.50 x 4.50 x 1.00 =
= 3.00 x 4.50 x 1.00 =
= 3.00 x 2.00 x 1.00 =
= 3.00 x 3.00 x 1.00 =
= 2.00 x 5.00 x 1.00 =
= 5.00 x 4.20 x 1.00 =
= 1.50 x 1.50 x 1.00 =
= 1.50 x 1.20 x 1.00 =
= 2.20 x 1.18 x 1.00 =
= 8.00 x 3.50 x 1.00 =
= 1.50 x 1.10 x 1.00 =
=

2 LANTAI KERAMIK 40x40 = 1.50 x 3.50 x 1.00 =


= 3.00 x 4.50 x 1.00 =
= 3.50 x 5.00 x 1.00 =
= 6.50 x 4.50 x 1.00 =
= 3.00 x 4.50 x 1.00 =
= 3.00 x 2.00 x 1.00 =
= 3.00 x 3.00 x 1.00 =
= 2.00 x 5.00 x 1.00 =
= 5.00 x 4.20 x 1.00 =
= 1.50 x 1.20 x 1.00 =
= 2.20 x 1.18 x 1.00 =
= 8.00 x 3.50 x 1.00 =
= 1.50 x 1.10 x 1.00 =
= 1.50 x 3.50 x 1.00 =
= 3.50 x 4.50 x 1.00 =
= 3.00 x 4.00 x 1.00 =
keramik tangga = 0.90 x 0.18 x 19.00 =
= 0.90 x 0.28 x 19.00 =
=

3 LANTAI KERAMIK 20 X 20 = 1.50 x 1.50 x 1.00 =


= 1.50 x 1.50 x 1.00 =
= 2.00 x 3.00 x 1.00 =
=

4 KERAMIK DINDING 20X20 = 1.50 x 1.50 x 1.00 =


= 1.50 x 1.50 x 1.00 =
=
VII PEKERJAAN CAT-CATAN

1 MENGECAT TEMBOK Plesteran 1 : 6 = 803.32


Plesteran 1 : 3 = 79.30
Plestertan Beton = 185.49
= 882.62 m2

2 MENGECAT PLAFOND = 210.92 m2

3 MENGECAT KAYU Cat kusen = 141.80 x 0.27 = 38.29


Cat lisplank = 0.36 x 0.64 = 0.23
JUMLAH TOTAL = 38.52

Plituran daun pintu & jendela = 49.33 m2

VIII PEKERJAAN INSTALASI AIR


1 SEPTIKTANK
Galian tanah 3.00 x 1.00 x 1.80 =
2.00 x 1.60 x 0.95 =
=

Pasangan bata 1 : 3 2.00 x 1.40 x 1.00 =


2.00 x 1.40 x 1.00 =
2.00 x 0.74 x 2.40 =
1.08 x 1.00 =
2.00 x 0.40 x 1.08 =
2.00 x 0.85 x 1.00 =
=

Balok 15/15 0.15 x 0.15 x 1.00 x 2.00 =

Plat tebal 7 cm 0.70 x 3.04 x 1.30 =

Plesteran 1 : 3 =
2 RESAPAN
Galian tanah 3.14 x 1.13 x 1.13 x 3.60

Pas. bata kosong 3.14 x 0.63 x 0.63 x 3.60

Pasangan bata 1 : 3 3.14 x 0.63 x 0.63 x 3.00

Tanah Urug 3.14 x 0.93 x 0.93 x 0.20 x

Kerikil 3.14 x 0.93 x 0.93 x 0.10

Ijuk 3.14 x 1.03 x 1.03 x 0.10 x

Plat tebal 7 cm 3.14 x 0.78 x 0.78 x 0.70

Plesteran 1 : 3
URAIAN

m3
m3
m3
m3

m3
m3
m3

m3
m3
m3
m3
m3
m3
m2
m3
m3
m3
m3
m3
m3
m3
m3
m3

= 38.38 m3

= 15.50 m3

= 53.88 m3

m3
m3
m3

= 36.25 m3

= 26.18 m3

= 62.43 m3

= 36.71 m2
= 4.95 m2
= 41.66 m2
= 191.70 m2
= 72.20 m2
= 166.73 m2
= 18.00 m2
= 12.50 m2
= 46.65 m2
= 4.58 m2
= 9.14 m2
= 6.78 m2

= 12.32 m2
= 7.09 m2
= 512.35 m2
= 49.19 m2
= 41.66 m2
= 463.16 m2

= 882.62 m2
= 79.30 m2
= 803.32 m2

= 69.40 m2
= 9.90 m2
= 79.30 m2

= 1.95
= 39.65
= 3.90
= 41.65
= 24.48
= 24.48
= 28.80
= 16.38
= 4.20
= 185.49 m2

= 61.20
= 96.00
= 50.40
= 14.00
= 1.95
= 39.65
= 3.90
= 41.65
= 24.48
= 333.23 m1

= 2.50 m3

= 2.18 m3

= 3.54 m3

= 5.95 m3

= 3.42 m3

= 0.27 m3

= 4.17 m3

= 0.29 m3

= 1.84 m3

= 0.41 m3
= 2.16 m3
= 1.23 m3
= 0.32 m3
= 0.51 m3
= 4.61 m3

= 2.45 m3

= 2.52 m3
= 1.62 m3
= 2.88 m3
= 7.02 m3

x 2.00 = 3.33 m3
x 4.00 = 2.94 m3
x 2.00 = 1.76 m3
= 8.04 m3

x 1.00 = 0.79 m3
0.06 x 0.15 = 1.28 m3

KACA
2.43 - 0.45 = 1.98 m2
9.77 = 9.77 m2
3.26 - 0.45 = 2.81 m2
1.63 - = 1.63 m2
6.07 = 6.07 m2
= 22.26 m2

3.26
1.48
4.73 - 0.86 = 3.88 m2
= 26.13 m2

1.23 - 2.61 = (1.38) m2


3.08 - 1.82 = 1.26 m2
1.96 - 1.19 = 0.77 m2
1.48 - 0.86 = 0.62 m2
0.75 - 1.08 = (0.33) m2
= 0.94 m2

0.45 m2
0.45 m2
0.86 m2
2.61 m2
1.82 m2
1.19 m2
0.86 m2
0.79 m2
0.29 m2
3.00 m2
12.32 m2

= 0.23 m3

= 0.47 m3

= 0.45 m3

= 0.86 m3

= 4.95 m3

= 1.72 m3
= 0.71 m3
= 2.43 m3

59.75 m2

2.43 m1

5.25
13.50
17.50
2.25
28.05
13.50
6.00
9.00
10.00
13.65
2.25
1.80
2.59
16.30
(10.05)
5.25
15.75
12.00
13.50
32.83
210.92 m2

10.00
15.00
17.00
6.00
22.00
15.00
10.00
12.00
14.00
18.40
6.00
5.40
6.75
23.00
5.20
10.00
16.00
14.00
15.00
95.20
335.95 m1

5.25
13.50
17.50
2.25
28.05
13.50
6.00
9.00
10.00
13.65
2.25
1.80
2.59
16.30
(10.05)
131.59 m2

5.25
13.50
17.50
28.05
13.50
6.00
9.00
10.00
13.65
1.80
2.59
16.30
(10.05)
5.25
15.75
12.00
3.08
4.79
167.95 m2

2.25
2.25
6.00
10.50 m2

2.25 m2
2.25 m2
4.50 m2
m2

5.40 m3
3.04 m3
8.44 m3

2.80 m2
2.80 m2
3.55 m2
1.08 m2
0.86 m2
1.70 m2
12.79 m2

0.05 m3

2.77 m3

12.79 m2
= 14.31 m3

= 4.42 m2

= 3.68 m2

0.60 = 0.54 m3

= 0.27 m2

3.00 = 0.99 m3

= 1.32 m3

= 3.00 m2
RENCANA ANGGARAN BIAYA ( RAB ) - SNI 2014

Pekerjaan : Final Project Drawing Technical


Lokasi : Ds. Jatirejo Kec. Wonoasri Kab . Madiun

NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SAT. (Rp) JUMLAH (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan dan perataan m2 210.00 - -
2 Pasang bowplank m' 62.00 81,860.00 5,075,320.00
5,075,320.00
II PEKERJAAN TANAH
1 Galian tanah pondasi m3 138.43 - -
2 Urugan bawah pondasi m3 12.17 - -
3 Urugan tanah kembali m3 53.88 - -
4 Urugan sirtu bawah lantai m3 26.32 - -
-
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Aanstamping m3 27.19 - -
2 Pasangan batu kali 1:3:8 m3 62.43 - -
3 Pasangan bata 1 : 3 m2 41.66 - -
4 Pasangan bata 1 : 6 m2 463.16 - -
5 Plesteran 1 : 3 m2 79.30 - -
6 Plesteran 1 : 6 m2 882.62 - -
7 Benangan m' 333.23 7,970.00 2,655,809.63
8 Tangga besi spiral ls 1.00 3,000,000.00 3,000,000.00
9 Besi Hollow 2x2 Railling m' 13.44 240,000.00 3,225,600.00
8,881,409.63
IV PEKERJAAN BETON BERTULANG
1 Beton strauss pile dia. 25 cm.
a Mengecor beton campuran K-175 m3 2.50 - -
b Pembesian kg 479.76 12,014.60 5,764,111.70
c Begesting m2 - - -
2 Beton poor 20.80.80
a Mengecor beton campuran K-175 m3 2.18 - -
b Pembesian kg 256.17 12,014.60 3,077,775.28
c Begesting m2 - - -
3 Beton kolom 15/15
a Mengecor beton campuran K-175 m3 4.61 - -
b Pembesian kg 972.42 12,014.60 11,683,289.63
c Begesting m2 30.78 212,456.00 6,539,476.94
4 Beton kolom 20/20
a Mengecor beton campuran K-175 m3 2.45 - -
b Pembesian kg 465.76 12,014.60 5,595,960.31
c Begesting m2 12.24 212,456.00 2,600,461.44
5 Beton sloof 15/20
a Mengecor beton campuran K-175 m3 5.95 - -
b Pembesian kg 1,246.31 12,014.60 14,973,911.96
c Begesting m2 39.67 217,175.00 8,615,294.24
6 Beton latei 15/20
a Mengecor beton campuran K-175 m3 3.42 - -
b Pembesian kg 716.98 12,014.60 8,614,247.96
c Begesting m2 22.82 451,100.00 10,294,735.80
7 Beton ring 15/15
a Mengecor beton campuran K-175 m3 0.27 - -
b Pembesian kg 71.02 12,014.60 853,299.00
c Begesting m2 1.77 451,100.00 798,846.22
8 Balok induk 20/35
a Mengecor beton campuran K-175 m3 4.17 - -
b Pembesian kg 565.26 12,014.60 6,791,368.73
c Begesting m2 20.87 451,100.00 9,412,945.82
9 Balok anak 15/30
a Mengecor beton campuran K-175 m3 0.29 - -
b Pembesian kg 1.95 12,014.60 23,440.18
c Begesting m2 1.95 451,100.00 880,084.82
10 Balok Gewel 15/15
a Mengecor beton campuran K-175 m3 1.84 - -
b Pembesian kg 491.05 12,014.60 5,899,767.17
c Begesting m2 12.24 451,100.00 5,523,276.95
11 Plat 12
a Mengecor beton campuran K-175 m3 7.02 - -
b Pembesian kg 660.30 12,014.60 7,933,191.76
c Begesting m2 37.14 515,100.00 19,128,650.58
12 Pelat beton tebal 7 cm.
a Mengecor beton campuran K-175 m3 8.04 - -
b Pembesian kg 646.59 12,014.60 7,768,577.96
c Begesting m2 66.06 515,100.00 34,025,404.39
13 Pelat tangga tebal 12 cm.
a Mengecor beton campuran K-175 m3 0.79 - -
b Pembesian kg 74.63 12,014.60 896,694.77
c Begesting m2 4.20 515,100.00 2,162,126.09
179,856,939.72
V PEKERJAAN KUSEN, PINTU & JENDELA
1 Pasang kusen kayu jati 6/15 m3 1.28 - -
2 Pasang daun pintu panil jati m2 48.39 - -
3 Pasang daun pintu PVC ( pengunci lengkap ) unit 2.00 858,000.00 1,716,000.00
4 Pasang daun jendela kayu jati m2 0.94 - -
5 Pasang kaca polos tebal 5 mm m2 12.32 - -
1,716,000.00
VI PEKERJAAN ALAT PENGGANTUNG & PENGUNCI
1 Pasang engsel pintu bh 26.00 26,400.00 686,400.00
2 Pasang grendel pintu bh 16.00 16,200.00 259,200.00
3 Pasang kunci tanam bh 13.00 62,100.00 807,300.00
4 Pasang engsel jendela bh 12.00 21,000.00 252,000.00
5 Pasang grendel jendela bh 13.00 11,000.00 143,000.00
6 Pasang hak angin bh 13.00 30,200.00 392,600.00
7 Pasang handle jendela bh 13.00 85,000.00 1,105,000.00
3,645,500.00
VII PEKERJAAN ATAP
1 Pasang gording 8/12 m3 0.47 - -
2 Pasang balok tembok 8/12 m3 0.45 - -
3 Pasang Kuda-kuda konsol 8/12 m3 0.86 - -
4 Pasang Kuda-kuda 8/12 m3 4.95 - -
5 Pasang Jurai 8/12 m3 0.36 - -
6 Pasang nok 8/12 m3 0.23 - -
7 Pasang usuk 5/7 dan reng 2/3 m2 195.53 98,035.00 19,168,293.38
8 Pasang papan bubungan 2/20 m' 23.90 - -
9 Pasang genteng palentong m2 195.53 - -
10 Pasang genteng bubungan m' 23.90 53,440.00 1,277,216.00
11 Pasang plafond eternit baru m2 210.92 95,416.00 20,124,665.64
12 Pasang list plafond m' 335.95 16,099.00 5,408,459.05
13 Pasang lisplank 2/30 m' 59.75 - -
45,978,634.07
VIII PEKERJAAN LANTAI
1 Pasang lantai keramik 40x40 landasan rabat beton 1:3:5 t. 7 cm. m2 167.95 361,120.50 60,650,549.10
2 Pasang lantai keramik 20x20 m2 10.50 136,682.50 1,435,166.25
3 Pasang keramik dinding 20x20 m2 4.50 175,236.00 788,562.00
4 Paving m2 26.95 37,500.00 1,010,625.00
63,884,902.35
IX PEKERJAAN INSTALASI LISTRIK
1 Kabel NYA m' - 5,500.00 -
2 Pasang lampu gantung bh 8.00 500,000.00 4,000,000.00
3 Pasang lampu SL 15 W + fitting ( Ex. Philips ) bh 7.00 35,000.00 245,000.00
4 Pasang lampu SL 18 W + fitting ( Ex. Philips ) bh 39.00 36,000.00 1,404,000.00
5 Pasang stopkontak ( Ex. Broco ) ttk 11.00 16,000.00 176,000.00
6 Pasang saklar tunggal ( Ex. Broco ) bh 16.00 18,000.00 288,000.00
7 Pasang saklar ganda ( Ex. Broco ) bh 6.00 15,000.00 90,000.00
8 Pasang MCB 4 group bh 1.00 440,000.00 440,000.00
9 Pasang Listrik 1200 watt ls 1.00 2,000,000.00 2,000,000.00
8,643,000.00
X PEKERJAAN CAT - CATAN
1 Mengecat tembok m2 882.62 - -
2 Mengecat plafond m2 210.92 - -
3 Mengecat kayu m2 38.52 - -
4 Plituran m2 49.33 - -
-
XI PEKERJAAN INSTALASI AIR (SANITASI)
1 Instalasi air bersih pipa PVC 3/4" m' 54.30 14,012.17 760,860.65
2 Instalasi air kotor pipa PVC 2" m' 33.50 - -
3 Instalasi air kotor pipa PVC 3" m' 11.70 - -
4 Pasang kitchen sink bh 1.00 - -
5 Pasang klosed duduk bh 2.00 - -
6 Pasang kran air bh 7.00 24,700.00 172,900.00
7 Pasang floordrain bh 3.00 - -
8 Pasang bak kontrol unit 2.00 - -
10 Tandon air Pinguin 500liter bh 1.00 700,000.00 700,000.00
11 Tower tandon air ls 1.00 2,500,000.00 2,500,000.00
9 SEPTIKTANK
Galian tanah m3 8.44 - -
Pasangan bata 1 : 3 m2 12.79 - -
Balok 15/15 m3 0.05 463,114.60 20,840.16
Plat tebal 7 cm m3 2.77 527,114.60 1,458,209.83
Plesteran 1 : 3 m2 12.79 - -
10 RESAPAN
Galian tanah m3 14.31 - -
Pas. bata kosong m3 4.42 285,660.00 1,261,367.44
Pasangan bata 1 : 3 m3 3.68 - -
Tanah Urug m3 0.54 - -
Kerikil m3 0.27 193,700.00 52,040.65
Ijuk kg 0.99 7,150.00 7,076.27
Plat tebal 7 cm m3 1.32 527,114.60 695,882.86
7,629,177.86
REKAPITULASI RENCANA ANGGARAN BIAYA ( RAB )

Pekerjaan Final Project Drawing Technical


Lokasi Ds. Jatirejo Kec. Wonoasri Kab . Madiun
Luas 280 m2
NO. URAIAN PEKERJAAN JUMLAH (Rp.)

I PEKERJAAN PERSIAPAN 5,075,320.00


II PEKERJAAN TANAH -
III PEKERJAAN PASANGAN DAN PLESTERAN 8,881,409.63
IV PEKERJAAN BETON BERTULANG 179,856,939.72
V PEKERJAAN KUSEN, PINTU & JENDELA 1,716,000.00
VI PEKERJAAN ALAT PENGGANTUNG & PENGUNCI 3,645,500.00
VII PEKERJAAN ATAP 45,978,634.07
VIII PEKERJAAN LANTAI 63,884,902.35
IX PEKERJAAN INSTALASI LISTRIK 8,643,000.00
X PEKERJAAN CAT - CATAN -
XI PEKERJAAN INSTALASI AIR (SANITASI) 7,629,177.86

JUMLAH Rp. 325,310,883.62


DIBULATKAN Rp. 325,310,000.00

Terbilang : " Tujuh Ratus Sembilan Puluh Sembilan Juta Enam Ratus Empat Belas Ribu Rupiah".

Madiun, 22 Januari 2015


,Menyetujui ,Estimator

Drs. AGOES WIDIJANTO .MUHAMMAD AKRIM M


TIME SCHEDULE
Pembangunan Rumah Dinas Pejabat Kabupaten Madiun
Jl. Basuki rahmat , Wonoasri Madiun

JANGKA WAKTU PELAKSANAAN


NO URAIAN PEKERJAAN BOBOT (%) BULAN KE - I BULAN KE - II
1 2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN 0.80 0.40 0.40


II PEKERJAAN TANAH 2.22 0.56 0.56 0.56 0.56
III PEKERJAAN PASANGAN DAN PLESTERAN 25.27 5.05 5.05 5.05 5.05 5.05
IV PEKERJAAN BETON BERTULANG 41.10 10.27 10.27 10.27 10.27
V PEKERJAAN KUSEN, PINTU & JENDELA 3.78 1.26 1.26 1.26
VI PEKERJAAN LANGIT-LANGIT 2.38 1.19
VII PEKERJAAN ATAP 7.62 1.91 1.91 1.91
VIII PEKERJAAN LANTAI 8.06
IX PEKERJAAN INSTALASI LISTRIK 1.48 0.74
X PEKERJAAN CAT - CATAN 0.90
XI PEKERJAAN INSTALASI AIR (SANITASI) 6.38 2.13 2.13

JUMLAH 100.00
Minggu 0.40 0.96 5.61 9.00 15.88 22.55 18.49 12.18
RENCANA
Komulatif ### 0.40 1.36 6.97 15.97 31.85 54.40 72.90 85.07
ANAAN
BULAN KE - III PROSENTASE
9 10 11 12

100

1.19 50
1.91
2.69 2.69 2.69
0.74
0.30 0.30 0.30
2.13 0

Grs Normal
5.78 5.12 3.73 0.30
Grs Rencana
90.86 95.97 99.70 100

Ponorogo, 19 Januari 2019

RIZKY WAHYU AGUNG


Direktur

Das könnte Ihnen auch gefallen

  • Mein Übungsheft Rechnen - 3. Klasse
    Mein Übungsheft Rechnen - 3. Klasse
    Von Everand
    Mein Übungsheft Rechnen - 3. Klasse
    Noch keine Bewertungen
  • Resolucion 14712 1984
    Resolucion 14712 1984
    Dokument24 Seiten
    Resolucion 14712 1984
    AlejoRSolano
    Noch keine Bewertungen
  • Simulación Ácido Base
    Simulación Ácido Base
    Dokument7 Seiten
    Simulación Ácido Base
    gloriamarvi
    Noch keine Bewertungen
  • Matched RSN8168
    Matched RSN8168
    Dokument135 Seiten
    Matched RSN8168
    n1046
    Noch keine Bewertungen
  • Concrete Material Tutorial
    Concrete Material Tutorial
    Dokument3 Seiten
    Concrete Material Tutorial
    alvaro
    Noch keine Bewertungen
  • Analytical Result
    Analytical Result
    Dokument7 Seiten
    Analytical Result
    sunil.raiyani
    Noch keine Bewertungen
  • Ma N455
    Ma N455
    Dokument102 Seiten
    Ma N455
    n1046
    Noch keine Bewertungen
  • Jawaban Gempa No. 2
    Jawaban Gempa No. 2
    Dokument3 Seiten
    Jawaban Gempa No. 2
    Artya Aurelia Pramesthi
    Noch keine Bewertungen
  • Bessel Function Table
    Bessel Function Table
    Dokument2 Seiten
    Bessel Function Table
    simossimo893
    Noch keine Bewertungen
  • Bessel Function Table
    Bessel Function Table
    Dokument2 Seiten
    Bessel Function Table
    Think Diag
    Noch keine Bewertungen
  • Tensile Test2
    Tensile Test2
    Dokument32 Seiten
    Tensile Test2
    MAGED MOHMMED AHMED QASEM
    Noch keine Bewertungen
  • Tabuas IBA
    Tabuas IBA
    Dokument36 Seiten
    Tabuas IBA
    fabaorcarvalho
    Noch keine Bewertungen
  • Leyes de Oro-Diego
    Leyes de Oro-Diego
    Dokument4 Seiten
    Leyes de Oro-Diego
    Valentin Velasquez
    Noch keine Bewertungen
  • Proyecto Desagües Pluviales
    Proyecto Desagües Pluviales
    Dokument13 Seiten
    Proyecto Desagües Pluviales
    pali
    Noch keine Bewertungen
  • Exp 3
    Exp 3
    Dokument5 Seiten
    Exp 3
    Anirudh dixit 01
    Noch keine Bewertungen
  • Accn 5
    Accn 5
    Dokument37 Seiten
    Accn 5
    MISBAH UL HAQUE
    Noch keine Bewertungen
  • Tabla Z
    Tabla Z
    Dokument2 Seiten
    Tabla Z
    lord_bafford526
    Noch keine Bewertungen
  • Simulasi Bot Andros New-1
    Simulasi Bot Andros New-1
    Dokument104 Seiten
    Simulasi Bot Andros New-1
    Classic Hot
    Noch keine Bewertungen
  • Tabla General PVC 50 A 160
    Tabla General PVC 50 A 160
    Dokument1 Seite
    Tabla General PVC 50 A 160
    Jose Luis Llaure
    Noch keine Bewertungen
  • Horwitz
    Horwitz
    Dokument2 Seiten
    Horwitz
    Diky Subhanuddin
    Noch keine Bewertungen
  • Matched Kobe - Da
    Matched Kobe - Da
    Dokument70 Seiten
    Matched Kobe - Da
    Ramesh Prajapati
    Noch keine Bewertungen
  • Accn 3
    Accn 3
    Dokument37 Seiten
    Accn 3
    MISBAH UL HAQUE
    Noch keine Bewertungen
  • Accn 2
    Accn 2
    Dokument37 Seiten
    Accn 2
    MISBAH UL HAQUE
    Noch keine Bewertungen
  • Accn 1
    Accn 1
    Dokument47 Seiten
    Accn 1
    BUSH RC
    Noch keine Bewertungen
  • 2 GR
    2 GR
    Dokument19 Seiten
    2 GR
    Ghinea Relu
    Noch keine Bewertungen
  • PDM
    PDM
    Dokument23 Seiten
    PDM
    Sourav Sutradhar
    Noch keine Bewertungen
  • PDM
    PDM
    Dokument23 Seiten
    PDM
    Joselle
    Noch keine Bewertungen
  • PDM
    PDM
    Dokument23 Seiten
    PDM
    Russel Fuller
    Noch keine Bewertungen
  • Accn 4
    Accn 4
    Dokument37 Seiten
    Accn 4
    MISBAH UL HAQUE
    Noch keine Bewertungen
  • 02 Tablas de Ahlvin y Ulery
    02 Tablas de Ahlvin y Ulery
    Dokument32 Seiten
    02 Tablas de Ahlvin y Ulery
    Deyvi Ninahuaman Sovero
    Noch keine Bewertungen
  • Current Rose
    Current Rose
    Dokument3 Seiten
    Current Rose
    Sandy Maolana
    Noch keine Bewertungen
  • BETAAA
    BETAAA
    Dokument2 Seiten
    BETAAA
    Feldiansyah 12
    Noch keine Bewertungen
  • Metodos
    Metodos
    Dokument20 Seiten
    Metodos
    Sebastián Badilla
    Noch keine Bewertungen
  • BusinessStatistics - Probability Temmplate Final
    BusinessStatistics - Probability Temmplate Final
    Dokument14 Seiten
    BusinessStatistics - Probability Temmplate Final
    Janarthanan Vt
    Noch keine Bewertungen
  • Archivo Tablas de Mortalidad
    Archivo Tablas de Mortalidad
    Dokument3 Seiten
    Archivo Tablas de Mortalidad
    2021 Act MARTINEZ OCAMPO HUGO
    Noch keine Bewertungen
  • Produksi Tanaman Biofarmaka (Obat)
    Produksi Tanaman Biofarmaka (Obat)
    Dokument8 Seiten
    Produksi Tanaman Biofarmaka (Obat)
    hazhemi rafsanjani
    Noch keine Bewertungen
  • Prad 1001 B Resu PP M
    Prad 1001 B Resu PP M
    Dokument945 Seiten
    Prad 1001 B Resu PP M
    Ridha Abdallah
    Noch keine Bewertungen
  • Frequência (HZ) Aceleração (m/s2)
    Frequência (HZ) Aceleração (m/s2)
    Dokument5 Seiten
    Frequência (HZ) Aceleração (m/s2)
    stuff stuff
    Noch keine Bewertungen
  • Untitled
    Untitled
    Dokument10 Seiten
    Untitled
    Javier Quinde
    Noch keine Bewertungen
  • Retno Uas
    Retno Uas
    Dokument4 Seiten
    Retno Uas
    Retno Dwianti
    Noch keine Bewertungen
  • Accn 1
    Accn 1
    Dokument37 Seiten
    Accn 1
    MISBAH UL HAQUE
    Noch keine Bewertungen
  • Tensile Test Excel
    Tensile Test Excel
    Dokument12 Seiten
    Tensile Test Excel
    Motasem Mrwan
    Noch keine Bewertungen
  • Modelo Hognestad
    Modelo Hognestad
    Dokument68 Seiten
    Modelo Hognestad
    ALAN
    Noch keine Bewertungen
  • Z Table
    Z Table
    Dokument2 Seiten
    Z Table
    Thành Nhân
    Noch keine Bewertungen
  • Book1 (Version 1)
    Book1 (Version 1)
    Dokument3 Seiten
    Book1 (Version 1)
    dec
    Noch keine Bewertungen
  • Dampfdrucktabelle Wasser - Fix
    Dampfdrucktabelle Wasser - Fix
    Dokument5 Seiten
    Dampfdrucktabelle Wasser - Fix
    6zx2pgr2cs
    Noch keine Bewertungen
  • Tabla Z - Ucedo V2
    Tabla Z - Ucedo V2
    Dokument3 Seiten
    Tabla Z - Ucedo V2
    steven
    Noch keine Bewertungen
  • Ilide - Info Tabel Poisson PR
    Ilide - Info Tabel Poisson PR
    Dokument6 Seiten
    Ilide - Info Tabel Poisson PR
    sislexx52
    Noch keine Bewertungen
  • RG15
    RG15
    Dokument2 Seiten
    RG15
    Lorenz Hofmann
    Noch keine Bewertungen
  • Z Table 109
    Z Table 109
    Dokument2 Seiten
    Z Table 109
    Govind kumar
    Noch keine Bewertungen
  • Tugas Sumur Theis
    Tugas Sumur Theis
    Dokument2 Seiten
    Tugas Sumur Theis
    Le7da
    Noch keine Bewertungen
  • Nodo
    Nodo
    Dokument2 Seiten
    Nodo
    Ana Hernández Dorado
    Noch keine Bewertungen
  • Clotoideunitaria
    Clotoideunitaria
    Dokument20 Seiten
    Clotoideunitaria
    emily la porta
    Noch keine Bewertungen
  • Domio 4
    Domio 4
    Dokument1 Seite
    Domio 4
    Ever Condori
    Noch keine Bewertungen
  • Datos Ensayo de Tensiã N
    Datos Ensayo de Tensiã N
    Dokument237 Seiten
    Datos Ensayo de Tensiã N
    julio
    Noch keine Bewertungen
  • Tablas Estadistica
    Tablas Estadistica
    Dokument16 Seiten
    Tablas Estadistica
    David Holguin Jaramillo
    Noch keine Bewertungen
  • Reaktor 2
    Reaktor 2
    Dokument57 Seiten
    Reaktor 2
    hartatiprasetyo
    Noch keine Bewertungen
  • Modelo de Hognestad
    Modelo de Hognestad
    Dokument7 Seiten
    Modelo de Hognestad
    Glenda Linaja García
    Noch keine Bewertungen
  • Lamda Max
    Lamda Max
    Dokument4 Seiten
    Lamda Max
    Ulin Nikmatus
    Noch keine Bewertungen