Qatar Integrated Railway Project (QIRP)

Qatar Railways in Future – Design and Build under Special Conditions

Project Presentation
February 11th, 2013, BTU Cottbus

DB International GmbH
J. Marienhagen
International Projects
Cottbus, 11.02.2013
Qatar Integrated Railway Project (QIRP)
Content

Introduction: Where is Qatar?

QRDP Project Overview

Important QRDP / QIRP Project Milestones

Role of DB International

Milestones in Project Management

Present Main Topic: Tender Documents

Time Schedule

Project Organisation

Management Approach

Technical Spotlights
1 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Content

Introduction: Where is Qatar?

2 DB International GmbH
Qatar Integrated Railway Project (QIRP)
World Map

Source: public domain 3 DB International GmbH


Qatar Integrated Railway Project (QIRP)
Map Qatar

Berlin

Doha

Source: public domain


4 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Doha, Map and Impressions

Map Source: public domain


Pictures: © J. Marienhagen 5 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Content

QRDP Project Overview

6 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Bauboom in Qatar – Middle East Economic Digest

1. Ein 4 Mrd. USD Stadion-Bauprogramm sieht den Bau von neun


umweltfreundlichen, innovativen Fußballstadien vor sowie den
Ausbau von drei existierenden Stadien.
2. Das umfassende Straßenausbau- und Verbesserungs-
programm von 20 Mrd. USD beinhaltet den Lusail Expressway,
Doha Expressway, Dukhan Freeway sowie die Doha Bay
Kreuzung.
3. Weitere 25 Mrd. USD decken den Bau einer Stadtbahn, einer
Hochgeschwindigkeitsstrecke zwischen NDIA, Stadtzentrum
Doha und dem vorgesehenem Qatar Causeway nach Bahrein
ab.
4. Zusätzlich soll eine Strecke für den Güterverkehr entstehen,
die an die GCC Staaten anknüpfen wird.

Die beiden Punkte 3. und 4. werden im


Qatar Rail Development Programme (QRDP) zusammengefasst.
Source logo: FIFA 7 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Qatar Railway Development Program

8 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Metro and Long Distance Network scheme

Long Distance Network Metro Network


Phase 1 (FIFA 2022)

9
Qatar Integrated Railway Project (QIRP)
Content

Important QRDP / QIRP Project Milestones

10 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Important QRDP Project Milestones

 Main technical
solutions
 Important, time- Inauguration Test Section
critical Tenders
 Organisational Inauguration First Line Section
basis

Metro Network Phase 1 (FIFA 2022) Metro Network Phase 2

Inauguration Freight Network


Long Distance Network
Phases 1, 2, 3 and 4 to be specified

2012 2014 2018 2020 2022 2025 2030

11
Qatar Integrated Railway Project (QIRP)
Content

Role of DB International

12 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Role of DBI Branch Qatar

The Role of the DBI within this phase of the project is the

„Lead Consultant“.

DBI Branch Qatar workforce consists of two different kinds of Employees:

 DB (I) staff contracted as „secondees“ for Qatar Railways


(approximately 40 employees)

 DBI staff located in the branch office


(approximately 30 employees) Branch Qatar

 Depending of the workload, all other DBI ressources as well as


many subconsultants are supporting this staff. In 2012, more than
approx. 150 engineers and technicians worked in parallel for the design works.
13
Qatar Integrated Railway Project (QIRP)
Content

Milestones in Project Management

14 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Typical Phasing of a Project

Concept Maintenance/
Operation

Definition Handover
Feasibility Study

Specification Preliminary Design Commissioning Validation

Integration Detailed Design/ Testing Verification


Shop Drawings

Construction and Installation

Implementation

Time
15
Qatar Integrated Railway Project (QIRP)
Sidestep: FIDIC

International Federation of Consulting Engineers FIDIC


Die Aufteilung der Vergabe ist ganz anders
geregelt als in Deutschland in der HOAI.

Für verschiedene Auftrags- (Vergabe-) arten


kommen verschiedene FIDIC- Rahmen-
verträge zur Anwendung. Diese sind in
jedem Einzelfall gesondert zu verhandeln
und präzisie auf den jeweiligen Vertrag
anzupassen.

Bezogen auf das aktuelle Projekt sind das


Yellow Book
(Plant and Design-Build, designed by the
Contractor) sowie das
Red Book
(Construction, designed by the Employer)
vergleichbar mit unseren bekannten
Vergabeverfahren.
16
Qatar Integrated Railway Project (QIRP)
Typical Tendering Procedures

Concept Maintenance/
Operation

Definition Handover
Feasibility Study

Specification Preliminary Design Commissioning Validation

Tender

Integration Detailed Design/ Testing Verification


Shop Drawings

Tender
Construction and Installation

Implementation

Time
17
Qatar Integrated Railway Project (QIRP)
Content

Present Main Topic: Tender Documents

18 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Scope of Work: DBI 2012

Scope of Work 2012: Tender Design / Tender Documents for different „Work Orders“

Qatar Rail RAMS Management

DBI RAMS Management


LEGEND:
WO#08 RAMS
Management
MEP scope
Third Party
(e.g. road Other Rail
Rolling Depots WO#01
authority, civil WO#04 WO#05 WO#07* projects (e.g.
DBI scope Stock ICC/ECC Civil
constructions, Civil @Grade Track Operation & WO#08 LRT and LD)
forTunnels
NDIA, ...) & Elevated Works Maintenance Railway
Systems
Scope to be
assigned MEP MEP

19 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Scope of Work: Work Order 8 „Railway Systems“

Qatar Rail RAMS Management

DBI RAMS Management


LEGEND:
WO#08 RAMS
Management
MEP scope
Third Party
(e.g. road Other Rail
Rolling Depots WO#01
authority, civil WO#04 WO#05 WO#07* projects (e.g.
DBI scope Stock ICC/ECC Civil
constructions, Civil @Grade Track Operation & WO#08 LRT and LD)
forTunnels
NDIA, ...) & Elevated Works Maintenance Railway
Systems
Scope to be
assigned MEP MEP

Interface Management

EMC Management

WO#08 RAMS Management

WP S: Signalling WP T: Telecom WP E: Energy WP V: Tunnel


Infra Radio SPS Ventilation
On-board Fixed TPS Study
SCADA BACS 3rd rail
SCADA PCSS

20 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Railway Systems: Subsystems Overview

Project Management

Interface Management

EMC Management

RAM and Safety Management

Energy Telecom Signalling Tunnel Ventilation

21
Qatar Integrated Railway Project (QIRP)
Content

Time Schedule

22 DB International GmbH
Qatar Integrated Railway Project (QIRP)
From Aquisition to Project Finalisation

Projektphasen: Zeitlicher Ablauf:

Angebotsvorbereitung / Akquise 10/2010 – 11/2011


Angebotsbearbeitung 11/2011 – 03/2012
Verhandlung 02/2012 – 05/2012
Angebotsüberarbeitung 03/2012 – 05/2012
Abschließende Verhandlung Ende 05/2012
Beauftragung durch ‚Notice to proceed‘ 01.06.2012
Beauftragung durch Vertrag 01.08.2012
Bearbeitung 03/2012 – 11/2012
Prüfung / Überarbeitung 11/2012 – 01/2013
Projektabschluss 31.01.2013

23 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Milestones within the design project

Tender Design +7 months

Conceptual Design +4 months

Inception Report +6 weeks


Reviewed Tender Design
+8 months
Project Execution Plan +2 weeks

Contract Award

24 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Milestones within the design project

Time schedule, milestones and deliverables due date


May Jun Jul Aug Sep Oct Nov Dez

 Project Execution Plan 20.06.12 

 Inception Report, Assumptions Register 12.07.12 

 Conceptual design 11.09.12 

 Tender Design 30.11.12 

 Reviewed Tender Design 31.12.12 

25
Qatar Integrated Railway Project (QIRP)
Content

Project Organisation

26 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Organisational Chart

Consultancy Services for Tender Design Railway Systems (WO #8)

Q ATA R R A I L CPO / SPM


Client: CTO Director Systems
D. Leckel M. Olschewski

Consultant: Quality Management Project Management


Document Management J. Marienhagen
Branch
Project Qatar
Controlling A. Winter / A. Linssen

Tunnel Ventilation Signalling Telecom Energy EMC


Dr. P. Reinke A. Heneka O. Matthäi R. Geisendorf H. Neumann

Lines of Communication:
 Official project communication will be between Director Systems and PM
 Technical communication will be initiated by PM

27 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Organisational Chart (detailled)

Q ATA R R A I L
Client: Chief Technical Officer Director Systems
D. Leckel M. Olschewski

contractual technical
Consultant:

Branch Project Management RAM & Safety


Management J. Marienhagen T. Ploeg+
M. Ahlgrimm A. Linssen / A. Winter P. Franck +

Quality Management
Dr. K. Hofmann
U. Kohlenberger
TVS Signalling Telecom Energy EMC
A. Heneka O. Matthäi R. Geisendorf H. Neumann
Dr. P. Reinke◦
K. Tahmassebi A. Winter p.u. J. von Lingen R. Kadhim
Document Management
T. Germann

WP S1: Metro Infrastr. WP T1: Radio Systems WP E2: SPS WP C1: EMC Managmt.
A. Heneka , M. Franke N. Vu Dr. A. Frenzel + Dr. R. Hietzke*
P. Czerkewski* B. Klingenberg R. Zillmer+ R. Arlt +
Project Management
Assistance
J. Drescher
WP E3: DC TPS
WP S2: Req. On-board WP T2: Fixed Systems WP C2: EMC Design
F. Helms, F. König
A. Tahmassebi V. Vaxevanakis H. Neumann*
T. Scherrans*,
M. Marschollek* O. Matthäi J. Thiemig+
M. Gumprecht*
Technical Service
Support / CAD
U. Engelhardt WP T3: SCADA BACS WP C3: Proof of EMC
S. Helms WP E4: Sys Rq. 3rd Rail Dr. K.-H. Kuypers
M. Kuhne
A. Souradny F. Helms, F. König Dr. S. Röhlig +
F. Hein
N.N.*
N.N.+

WP E5: SCADA-PCSS
Administrative Services F. König
Legal Advice
N. Henckel

* … Subcontractor IfB
Contract Management + ... Subcontractor KEMA/ELBAS
P. Bethge 28 ◦ … Subcontractor HBI
DB International GmbH
D. Golz
Qatar Integrated Railway Project (QIRP)
Technical Counterparts – tailored project organisation

29 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Staffing Concept (Plan)

Staffing Concept per Week


30

Germany
Average
Qatar
presence
25 rate
needed
in Doha
20

50%
Number of Personnel

15

10

0
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3
Calendar Week
30 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Content

Management Approach

31 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Management Approach (1): Thinking Ahead

Different design stages within a project require a different project management attention

Project Execution Plan

Tender Documentation
Project Initiaon Phase

Conceptual Design
Inception Report

Project Closure
Rework Phase
Aquisition

Project Phase
Project Management Technical Workforce

32 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Management Approach (2): Leading Documents

The project starts with creating a Project Execution Plan (PEP).


It can be updated and revised through whole the technical
processes phase. The PEP is based upon the definitions given
by the „System Engineering Process“ (ISO/IEC 15288).

33 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Management Approach (2): Leading Documents

After analysing the scope in very detail, the first ideas for
fulfilling the work has to compiled and discussed with the
Client.

Therefore, an Inception Report (IR) has to be issued.

Inception Report

34 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Management Approach (3): Conceptual Design as Presentation Event

Within the project progress, many detailed


technical discussions were held.

Presenting the Conceptual Design as one of


the most important milestones / results
within the technical progress has to be an
outstanding, memorable event. In order to
avoid a “normal” presentation, we decided to
organise this 2-day event as a splitted
performance.

Day 1: presentation event in a hotel, one


hour per technical discipline including short
discussion

Day 2: “After Show Parties” for discussion of


the technical issues in parallel and in the
needed degree of detail.

Result: concentrated project progress


involving all technical work packages 35 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Management Approach (4): Completion of Tender Documentation

After getting a “no objection” notice by the


Client to the technical approach and the
presented level of detail within the tender
documentation, the Conceptual Design was
transferred into a comprehensive technical
documentation.

These documents consist of technical


descriptions as well as some generic
drawings.

The resulting documents are intended to


form the “particular employers requirements”
according to FIDIC regulations.

A Review Phase, incorporating all the


comments of the Client as well of some
independent checking authorities, is the last
activity of the actual project.

36 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Content

Technical Spotlights
37 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Technical Spotlights: Grades of Automation

The performance of mass transit systems is largely dependent on the performance of the train control. With
increasing automation, the responsibility for operation management is passing from the driver to the system. A train
control system comprises functions for supervision, operation and control of the entire operational process. It can
feature different degrees of automation such as manual train operation, semi-automated train operation and
unattended operation.

These types of
operation are referred
to as Grade of
Automation

reference:

38
Qatar Integrated Railway Project (QIRP)
Technical Spotlights: Tunnel Ventilation System (TVS)

Objectives / Functional requirements


TVS integral element of metro system to ensure:
acceptable level of tunnel air temperature
limited air pressure and pressure transients in tunnels and inside trains
sufficient air exchange rates for sufficient air quality (smell, pollution, humidity)
smoke free areas during fire

Source: HBI Haerter AG 39


Qatar Integrated Railway Project (QIRP)
Technical Spotlights: Tunnel Ventilation System (TVS)

add. extreme value analysis

40 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Technical Spotlights: Tunnel Ventilation System (TVS)

Principle Illustration
Mode
Water drop/ Fog
curtain (wet
cooling)
Emergency
Congested

Cold air supply


(dry cooling)

Maintenance

41
Qatar Integrated Railway Project (QIRP)
Assumptions Register – verification process

 Each technical definition


requires an agreement from
different sides.
 In any case where this
agreement cannot reached
(due to a missing
counterpart or a missing
definition), an assumption
has to be made.
 These assumptions are
consolidated in a
“Assumptions Register”,
which is a living document .
 The aim is to solve all these
assumptions before
tendering.
42 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Hazard Analysis

 Hazard identification
This means hazards of the system itself
(track works) but also hazards in relation to
interfaces with other work orders will be
identified

 Qualitative Risk Assessment


Determining the likelihood of an event in
combination with the severity of the
outcome (Inherent Risk Ranking)

 Definition of risk mitigation


Determining for the risks which have an to
high inherent Risk Ranking what mitigating
measures could reduce the risk ranking.

43
Qatar Integrated Railway Project (QIRP)
Interface Management

44 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Interfaces to disciplines out of DBI scope

45 DB International GmbH
Qatar Integrated Railway Project (QIRP)
Quality Gate / EPLASS workflow

Levels of authorization
Prepared
by a competent Person who produces the design document, complying with
codes and standards governing that work.

Checked
by a competent person able to undertake a formal detailed check of design
methods, codes and standards used, deliverables, calculations, drawings,
and technical specifications produced by another member of the
Engineering Team. This role will be undertaken by a competent person of
the same discipline, not the Preparer, but can be a member of the same
team for a Category I check

Approved

Documents may only be approved for issue by the authorized person as


defined in the Engineering Standards.

Authorized for issue


Generally speaking this will be the Project Manager or formally advised
delegate.
46 DB International GmbH
Qatar Integrated Railway Project (QIRP)

Thank you for your attention!

Doha, Museum of Islamic Art / Skyline of West Bay __ © J. Marienhagen


47 DB International GmbH