PROJECT : PROPOSED ONE STOREY HOUSE

SUBJECT : BILL OF MATERIALS


OWNER : MR./MRS. MAGDALENA CORPUZ

SCOPE OF WORKS
ITEM PARTICULARS QTY UNIT TOTAL AMOUNT

GENERAL CONSTRUCTION WORKS

A EARTHWORKS 38,000.00
Site clearing and Excavations 1 lot 21,000.00
Ground Levelling and Backfills 50 m³ 15,000.00
Layout and Batten board Staking 2,000.00

B STEEL AND REINFORCEMENTS WORKS 351,755.00


Footings & Columns
12 mm. dia. 24 pcs. 175.00 4,200.00
10 mm. dia. 18 pcs. 115.00 2,070.00
100mm x 200mm I-Beam 13 pcs. 13,500.00 175,500.00

Beams and Roof Beams


12 mm. dia 48 pcs. 175.00 8,400.00
10 mm. dia. 30 pcs. 115.00 3,450.00
100mm x 200mm I-Beam 10 pcs. 13,500.00 135,500.00

Slabs and Dowels


12 mm. dia 95 pcs. 175.00 16,625.00
10 mm. dia. 46 pcs. 115.00 5,290.00
Tie Wires #16 18 kg. 40.00 720.00

C CONCRETE AND MASONRY WORKS 136,900.00


Cement 480 bags 175.00 84,000.00
Sand 26 m³ 500.00 13,000.00
3/4 Crushed Gravel 28 m³ 750.00 21,000.00
4" CHB 1350 pcs. 14.00 18,900.00

D FORMS AND FORMWORKS 158,200.00


2"x3" Coco Lumbers 31 pcs. 2500 77,500.00
2"x2" Coco Lumbers 33 pcs. 2500 77,500.00
Plywood Forms Panelling 5 pcs. 640 3,200.00

E ROOFING WORKS ( SLAB ROOF ) 68,107.00


12 mm. dia 95 pcs. 175.00 16,625.00
10 mm. dia. 46 pcs. 115.00 5,290.00
Tie Wires #16 18 kg. 40.00 720.00
WaterProofing 112 ltrs. 406.00 45,472.00

F. CEILING WORKS 28,083.00


Gypsum Board Ceiling Panels 27 pcs. 429.00 11,583.00
G.I. Metal furring Framing Studs and hangers 10,900.00
Gypsum Putty and Tape 5,600.00

G PLUMBING FIXTURES & INSTALLATION 52,930.00


Faucet 4 pcs. 150.00 600.00
Shower Valve 2 pc. 150.00 300.00
Floor Drain 3 pcs. 75.00 225.00
Shower Drain 2 pc. 75.00 145.00
Kitchen Sink 1 pc. 1,500.00 1,500.00
Water Line (Complete System) 2.4 Is. 8,500.00 20,400.00
Sewerage System 2.4 Is. 900.00 2,160.00
Storm Drainage System 2.4 Is. 9,000.00 21,600.00
Water Closet 2 pcs. 1,500.00 3,000.00
Lavatory 2 pcs. 1,500.00 3,000.00
PROJECT : PROPOSED TWO STOREY HOUSE
SUBJECT : BILL OF MATERIALS
OWNER : MR./MRS. MAGDALENA CORPUZ

SCOPE OF WORKS
ITEM PARTICULARS QTY UNIT TOTAL AMOUNT

H. ELECTRICAL WORKS 21,500.00


Outlet Complete 7 Sets 200.00 1,400.00
Lighting Outlet 19 Sets 200.00 3,800.00
Wires and Cables
2.5 mm THWN 7 Roll 750.00 5,250.00
3.5 mm.THWN 7 Roll 950.00 6,650.00
Switch 7 200.00 1,400.00
Circuit Breakers/Panel Board 2 1,500.00 3,000.00

I. DOORS AND WINDOWS 169,375.00

Main Door - Glass Sliding Door 1 set 15,000.00 15,000.00


Kitchen Door- Pocket Door 1 set 1,600.00 1,600.00
Bedroom Doors - Flush Type Door 2 sets 1,100.00 2,200.00
Toilet Door - PVC Door QDE Paint Finish 2 sets 800 1,600.00
Locksets/Doorknob 6 pcs. 150 900.00
All Windows - Steel Casement with Clear Glass Awning 4 sets 2,500.00 10,000.00
CURTAIN WALL 39.45 sqm 3,500.00 138,075.00

J. PAINTING WORKS 36,950.00


Exterior and Interior Walls (semi-gloss paint finish) 5 gal 3,500.00 17,500.00
Exterior and Interior Ceilings (flat paint finish) 3 gal 4,600.00 13,800.00
Doors Paint finish (QDE paint finish) 1 gal 4,600.00 4,600.00
Steel Casement Windows (QDE paint finish) 1 gal 1,050.00 1,050.00

K. TILE WORKS 37,943.00


Toilet Wall and Floors (Ceramic Tile Finish)
10 x 20cm. (4" x 8") Glazed Wall Tiles 77 pcs 19.00 1,463.00
20 x 20cm. Unglazed Floor Tiles 91 pcs. 25.00 2,275.00
Living, Dining, Bedroom (Vinyl Tile Finish) (0.60x0.60) 225 pcs 115.00 25,875.00
Kitchen Counters (Mosaic Tile Finish) 52 pcs. 65.00 3,380.00
Entrance Porch (Smooth Plain Cement Finish) 45 pcs. 110.00 4,950.00

CABINETRY 4,950.00
Kitchen Hanging Cabinet (paint Finish) 3 set 550.00 1,650.00
Kitchen Low Cabinet (paint Finish) 6 set 550.00 3,300.00

BUILDING COST 917,630.00


LABOR COST (30%) 275,289.00

TOTAL AMOUNT: 1,192,919.00 PHP