RENCANA ANGGARA BIAYA ( RAB )

PEKERJAAN : MENGHITUNG STRUKTUR BETON


LOKASI :-
TAHUN :-

HARGA SAT. JUMLAH HARGA


URAIAN PEKERJAAN VOLUME SAT.
(Rp.) (Rp.)
1 2 3 4 5 6
D PEKERJAAN STRUKTUR BETON
1 Pekerjaan Kolom 20/70
Beton K-225 (site mix) 0.56 m3 Rp 1,557,131.51 Rp 871,993.65
Besi beton 90.56 kg Rp 22,012.63 Rp 1,993,398.81
Bekisting 2 kali pakai 7.20 m2 Rp 183,239.16 Rp 1,319,321.95
2 Pekerjaan Balok 20/50 Rp -
Beton K-225 (site mix) 0.60 m3 Rp 1,557,131.51 Rp 934,278.91
Besi beton 120.05 kg Rp 22,012.63 Rp 2,642,664.87
Bekisting 2 kali pakai 7.20 m2 Rp 199,957.67 Rp 1,439,695.22
SUB JUMLAH Rp 9,201,353.41
TOTAL Rp 9,201,353.41
PPN 11% Rp 1,012,148.88
SUBTOTAL Rp 10,213,502.29
PEMBULATAN Rp 10,210,000.00
TERBILANG :
SEPULUH JUTA DUA RATUS SEPULUH RIBU RUPIAH
6.5 1 M³ MEMBUAT BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58
6.5.1 Bahan
371.000 Kg Semen @ Rp 1,440.00 Rp 469,440.00
0.698 m3 Pasir @ Rp 247,500.00 Rp 172,755.00
1.047 m3 Kerikil @ Rp 385,000.00 Rp 403,095.00
215.000 Liter Air @ Rp - Rp -
Jumlah (1) Rp 1,045,290.00
Tenaga - -
1.650 oh Pekerja @ Rp 143,200.00 Rp 236,280.00
0.275 oh Tukang Batu @ Rp 179,000.00 Rp 49,225.00
0.028 oh Kepala Tukang @ Rp 193,000.00 Rp 5,404.00
0.083 oh Mandor @ Rp 214,800.00 Rp 17,828.40
Jumlah (2) Rp 308,737.40
D. JUMLAH HARGA TENAGA DAN BAHAN Jumlah Rp 1,354,027.40
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10 % x D Rp 203,104.11
F. HARGA SATUAN PEKERJAAN PER- M³( D + E ) Rp 1,557,131.51

6.17 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


6.17.1 Bahan
10.500 Kg Besi Beton ( Polos / Ulir) @ Rp 15,500.00 162,750.00
0.150 Kg Kawat Beton @ Rp 26,000.00 Rp 3,900.00
Jumlah (1) Rp 166,650.00
Tenaga
0.070 oh Pekerja @ Rp 143,200.00 Rp 10,024.00
0.070 oh Tukang Batu @ Rp 179,000.00 Rp 12,530.00
0.007 oh Kepala Tukang @ Rp 193,000.00 Rp 1,351.00
0.004 oh Mandor @ Rp 214,800.00 Rp 859.20
Jumlah (2) Rp 24,764.20
D. JUMLAH HARGA TENAGA DAN BAHAN Jumlah Rp 191,414.20
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10 % x D Rp 28,712.13
F. HARGA SATUAN PEKERJAAN PER- KG( D + E ) Rp 220,126.33
Jadi 1 Kg Rp 22,012.63

6.22 1 M² MEMBUAT BEKESTING UNTUK KOLOM


6.22.1 Bahan
0.040 m³ Kayu Kelas III @ Rp 2,254,000.00 Rp 90,160.00
0.400 Kg Paku 5 Cm - 10 Cm @ Rp 23,400.00 Rp 9,360.00
0.200 Liter Minyak Bekesting @ Rp - Rp -
0.015 m³ Balok Kayu Kelas II @ Rp 3,150,000.00 Rp
0.350 Lbr Plywood Tebal 6 mm @ Rp 90,000.00 Rp 31,500.00
2.000 Btg Dolken Kayu Galamø (8 -10 Cm) @ Rp 4,400.00 Rp 8,800.00
Jumlah (1) Rp 187,070.00
Tenaga
0.520 oh Pekerja @ Rp 143,200.00 Rp 74,464.00
0.260 oh Tukang Batu @ Rp 179,000.00 Rp 46,540.00
0.026 oh Kepala Tukang @ Rp 193,000.00 Rp 5,018.00
0.026 oh Mandor @ Rp 214,800.00 Rp 5,584.80
Jumlah (2) Rp 131,606.80
D. JUMLAH HARGA TENAGA DAN BAHAN Jumlah Rp 318,676.80

E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10 % x D Rp 47,801.52


F. HARGA SATUAN PEKERJAAN PER- M²( D + E ) Rp 366,478.32
2x pakai Rp 183,239.16
Pekerjaan Kolom 20/70
Beton panjang LEBAR TINGGI VOLUME (M3)
4 0.2 0.7 0.56

Pekerjaan Kolom 20/70


Besi Tulangan Pokok panjang Jumlah besi diameter besi koefisien besi volume (kg)
4 4 14 1.208413614 19.33
4 12 12 0.887814084 42.62
Besi Begel 1.74 26.6666667 10 0.616537558 28.61

Total 90.56

Pekerjaan Kolom 20/70


BEKISTING panjang LEBAR TINGGI VOLUME (M2)
4 0.4 1.4 7.2

Pekerjaan Balok 20/50


Beton panjang LEBAR TINGGI VOLUME (M3)
6 0.2 0.5 0.6
Pekerjaan Balok 20/50
Besi Tulangan Pokok panjang Jumlah besi diameter besi koefisien besi volume (kg)
6 4 14 1.208413614 29.00
6 8 14 1.208413614 58.00
Besi Begel 1.34 40 10 0.616537558 33.05

Total 120.05

Pekerjaan Balok 20/50


BEKISTING panjang LEBAR TINGGI VOLUME (M2)
6 0.2 1 7.2