MONTHLY PLAN
Oct-19
Halaman : 2 dari 10
Hauller OB
1 HINO 260 dt 8 30 85% BRCM
2 HINO 260 dt 8 30 85% BRCM
3 HINO 260 dt 8 30 85% BRCM
4 HINO 260 dt 8 30 85% BRCM
5 NISSAN dt 8 30 85% BRCM
6 NISSAN dt 8 30 85% BRCM
7 NISSAN dt 8 30 85% BRCM
8 NISSAN dt 8 30 85% BRCM
Hauller COAL
Support
1 Dozer dz 90% BRCM
No : DPB/BRCM/MRP-MPD/I/2019
Tgl Terbit : 3 Oktober 2019
STANDARD PARAMETER OPERATION Revisi :0
Halaman : 4 dari 10
Oktober
Nov Des Total
Description Dimension Rate W40 (tgl 1-5) W45 (tgl 6-12) W46 (tgl 13-19) W47 (tgl 20-26) W48 (tgl 27-31) Total
Calendar Days Days 5.00 7.00 7.00 7.00 5.00 31.00 28.00 31.00 90.00
Holiday Days - - - - - - - 1.50 1.50
Overshift Days Day/week - 0.50 0.50 0.50 0.50 2.00 - - 2.00
Working Days Days 5.00 6.50 6.50 6.50 4.50 29.00 28.00 29.50 86.50
Day hours Hours 24 Hr/day 120.00 156.00 156.00 156.00 108.00 696.00 672.00 708.00 2,076.00
Shift number Shift 2 /day 10.00 13.00 13.00 13.00 9.00 58.00 56.00 59.00 173.00
Change Shift Hours 0.75 Hr/shift 7.50 9.75 9.75 9.75 6.75 43.50 42.00 44.25 129.75
Schedule Working hours Hours 112.50 146.25 146.25 146.25 101.25 652.50 630.00 663.75 1,946.25
PA % = PM 70% 11.81 15.36 15.36 15.36 10.63 68.51 66.15 69.69 204.36
85% UM 30% 5.06 6.58 6.58 6.58 4.56 29.36 28.35 29.87 87.58
Down Time Hours 15% 16.88 21.94 21.94 21.94 15.19 97.88 94.50 99.56 291.94
Available Hours Hours 95.63 124.31 124.31 124.31 86.06 554.63 522.00 564.19 1,640.81
Delay Time :
Rain + Clean Up Hours 2.0 Hr/shift 20.00 26.00 26.00 26.00 18.00 116.00 112.00 118.00 346.00
Safety talk Hours 0.5 hr/week 0.50 0.50 0.50 0.50 0.50 2.50 1.50 2.50 6.50
Unefficiency schedule Hours 0.33 Hr/shift 3.30 4.29 4.29 4.29 2.97 19.14 18.48 19.47 57.09
Friday Prayer Hours 1 hr/week 1.00 1.00 1.00 1.00 - 4.00 4.00 4.00 12.00
Fasting Month hours 0 hr/day - - - -
Pre-start Check hours 0.08 Hr/shift 0.83 1.08 1.08 1.08 0.75 4.83 4.67 4.92 14.42
Meals hours 1.00 Hr/shift 10.00 13.00 13.00 13.00 9.00 58.00 56.00 59.00 173.00
Refueling hours 0.08 Hr/shift 0.80 1.04 1.04 1.04 0.72 4.64 4.48 4.72 13.84
Job Area Maintenance hours 0.33 Hr/shift 3.30 4.29 4.29 4.29 2.97 19.14 18.48 19.47 57.09
Total Standby hours 39.73 51.20 51.20 51.20 34.91 228.25 219.61 232.08 679.94
- -
Eff. Working Hours hours 55.89 73.11 73.11 73.11 51.15 326.37 302.39 332.11 960.88
Use of Availability % 58.45% 58.81% 58.81% 58.81% 59.44% 58.85% 57.93% 58.87% 58.56%
3
No : DPB/BRCM/MRP-MPD/I/2019
Tgl Terbit : 3 Oktober 2019
EQUIPMENT SUMMARY Revisi :0
Halaman : 5 dari 10
Fleet 1 PC 400 PIT 50 200 11,178 14,622 14,622 14,622 10,231 45,692 60,479 66,422 172,593
Fleet 2 SK-480 PIT 50 200 11,178 14,622 14,622 14,622 10,231 45,692 60,479 66,422 172,593
Fleet 3 ZX-330 PIT 50 150 8,384 10,966 10,966 10,966 7,673 48,956 45,359 49,817 144,131
- - -
- - -
- - -
Total 550 30,740 40,210 40,210 40,210 28,134 140,340 166,316 182,661 489,317
Oktober
Description Unit Nov Des Total
W40 (tgl 1-5) W45 (tgl 6-12) W46 (tgl 13-19) W47 (tgl 20-26) W48 (tgl 27-31) Total
SUPER PIT
Waste Removal BCM 30,740.42 40,210.04 40,210.04 40,210.04 28,133.88 140,339.82 166,316.33 182,660.96 489,317.11
Coal Expose MT 4,000.00 4,000.00 4,000.00 4,000.00 4,000.00 20,000.00 45,359.00 49,816.62 115,175.63
Coal Getting MT 3,353.50 4,386.55 4,386.55 4,386.55 3,069.15 19,582.30 - - 19,582.30
SR Expose 7.69 10.05 10.05 10.05 7.03 7.02 3.67 3.67 4.25
SR Getting 9.17 9.17 9.17 9.17 9.17 7.17 - - 24.99
No : DPB/BRCM/MRP-MPD/I/2019
Tgl Terbit : 3 Oktober 2019
Issue Revisi :0
Halaman : 7 dari 10
1 Opening Project
No : DPB/BRCM/MRP-MPD/I/2019
Tgl Terbit : 3 Oktober 2019
Volume Remaint Revisi :0
Halaman : 8 dari 10
No : DPB/BRCM/MRP-MPD/I/2019
Tgl Terbit : 3 Oktober 2019
Sequence Oktober 2019 Revisi :0
Halaman : 9 dari 10
No : DPB/BRCM/MRP-MPD/I/2019
Tgl Terbit : 3 Oktober 2019
Volume Remaint Revisi :0
Halaman : 10 dari 10