DAFTAR MATA PEMBAYARAN UTAMA

NAMA PAKET : Rehabilitasi Jalan Sp. Sumberkembar - Sp. Panggungrejo II (E.B.086)


Jenis Barang/Jasa Satuan Volume Harga Satuan Pajak (%) Total %
Mobilisasi Ls 1.00 2,155,000.00 11 2,392,050.00 0.62%
Pembuatan dokumen RKK, RKPPL, RMLLP, RMPK Set 1.00 100,000.00 11 111,000.00 0.03%
Penyusunan pelaporan penerapan SMKK Set 1.00 100,000.00 11 111,000.00 0.03%
Spanduk (Banner) Lb 2.00 75,000.00 11 166,500.00 0.04%
Pembatas area (Restricted Area) Roll 2.00 100,000.00 11 222,000.00 0.06%
Topi pelindung (Safety Helmet) Bh 20.00 30,000.00 11 666,000.00 0.17%
Pelindung pernafasan dan mulut (masker, masker respirator) Bh 20.00 5,000.00 11 111,000.00 0.03%
Sarung tangan (Safety Gloves) Psg 20.00 15,000.00 11 333,000.00 0.09%
Sepatu keselamatan (Safety Shoes, rubber safety shoes and toe cap) Psg 20.00 60,000.00 11 1,332,000.00 0.35%
Rompi keselamatan (Safety Vest) Bh 20.00 25,000.00 11 555,000.00 0.14%
Petugas Keselamatan Konstruksi, Petugas K3 Konstruksi Org 4.00 2,125,000.00 11 9,435,000.00 2.46%
Peralatan P3K Set 1.00 75,000.00 11 83,250.00 0.02%
Biaya protokol kesehatan wabah menular (misal tempat cuci tangan, Termometer, swab, vitamin di masa pandemi covid-19) Ls 1.00 650,000.00 11 721,500.00 0.19%
Rambu larangan Bh 2.00 75,000.00 11 166,500.00 0.04%
Rambu peringatan Bh 2.00 75,000.00 11 166,500.00 0.04%
Alat Pemadam Api Ringan (APAR) Bh 1.00 175,000.00 11 194,250.00 0.05%
Galian Biasa m3 6.00 32,330.74 11 215,322.73 0.06%
Timbunan Biasa Dari Sumber Galian m3 20.00 257,634.25 11 5,719,480.35 1.49%
Galian Perkerasan Beraspal tanpa Cold Milling m3 1.69 478,259.96 11 897,167.86 0.23%
Lapis fondasi Agregat Kelas A m3 7.88 350,621.71 11 3,066,817.97 0.80%
Lapis fondasi Agregat Kelas S m3 9.75 300,486.30 11 3,252,012.98 0.85%
Lapis Pondasi Bawah Beton Kurus m3 10.40 1,227,574.88 11 14,171,124.41 3.69%
Pembongkaran Beton m3 10.00 431,662.82 11 4,791,457.30 1.25%
Pembongkaran Pasangan Batu m3 3.00 294,404.08 11 980,365.59 0.26%
Beton struktur fc30 Mpa (jalan beton) m3 115.50 1,860,542.18 11 238,530,810.19 62.18%
Beton fc15 MPa (tanpa begisting) m3 21.00 1,157,274.77 11 26,976,074.89 7.03%
Baja Tulangan Polos BjTP-280 Kg 2,089.40 15,840.43 11 36,737,663.83 9.58%
Baja Tulangan Sirip BjTS-280 Kg 110.48 16,110.22 11 1,975,641.39 0.51%
Pasangan Batu m3 22.23 757,058.53 11 18,680,646.35 4.87%
Pasang bekisting dinding beton biasa dengan m2 80.00 70,049.00 11 6,220,351.20 1.62%
Plesteran 1 pc 3 pp (Tebal 15 mm) m2 25.00 57,950.00 11 1,608,112.50 0.42%
Pekerjaan Siaran dng Mortar (1 PC 2 PP) m2 30.00 65,440.00 11 2,179,152.00 0.57%
Mengecat Trotoar / Leneng plonto (exterior) m2 28.00 27,520.00 11 855,321.60 0.22%
TOTAL 383,624,000.00 100.00%