Title :
SUB STRUCTURE
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
WORK DESCRIPTION
SUB STRUCTURE
WORK DESCRIPTION
1.0 Foundation & Basement floor works
Excavation & Earthwork
Site clearing to an average depth of 30cm. m² 257.55 257.55 1 2/22/2023 2/23/2023 X X
Bulk excavation in Ordinary Soil to a depth <1m m³ 257.55 128.78 1 2/23/2023 2/24/2023 X X
Bulk excavation in Ordinary Soil to a depth >1m & <2m m³ 257.55 103.02 2/24/2023 2/27/2023 X X X X
Bulk excavation in Ordinary Soil to a depth >2 & <4m m³ 515.10 257.55 2/27/2023 3/1/2023 X X X
Lean concrete (C5) to Mat Foundation m² 207.22 207.22 3/1/2023 3/2/2023 X X
Mat Beams, Slab, Found. Columns & Shearwalls
Formwork m² 356.22 60.00 3/3/2023 3/9/2023 X X X X X X X
Reinforcement work Kg 21,134.88 3,000.00 3/3/2023 3/11/2023 X X X X X X X X X
Concrete work m³ 142.40 142.40 2 3/10/2023 3/12/2023 X X X