Week No. 1 2 3 4 5 6 7 8 9 10 11 12 13
Item Work Description/Activity Start Finish Duration
January February
Week No. 1 2 3 4 5 6 7 8 9
Item Work Description/Activity Timeline Start Finish Duration
Target 01/05/20 01/05/20 0 days 1
1 Mobilization
Actual 01/10/20 01/10/20 0 days 2
Target 01/06/20 01/21/20 15 days 1111111111111111
2 Demolition Works
Actual 01/11/20 01/26/20 15 days 2222222222222222
3 Concrete & Masonry Works
Concrete slab topping 0.125m thk with 10mm dia. Target 01/21/20 02/05/20 15 days 1111111111111111
3.1
Temperature bar at 0.50m on center Actual 01/25/20 02/09/20 15 days 2222222222222222
Restoration of concrete wall affected by the repair Target 02/05/20 02/25/20 20 days 111111111111111111111
3.2 works Actual 02/07/20 02/27/20 20 days 222222222222222222222
4 Architectural Works
Target 02/25/20 03/06/20 10 days 111
4.1 Replacement of Ceiling
Actual 02/25/20 03/06/20 10 days 222
Target 02/25/20 03/06/20 10 days 111
4.2 Installation of New Drywall Partition
Actual 02/27/20 03/08/20 10 days 2
Target 03/06/20 03/11/20 5 days
4.3 Painting at interior and exterior sides
Actual 03/11/20 03/16/20 5 days
Target 03/11/20 03/18/20 7 days
4.4 Doors & Windows
Actual 03/01/20 03/08/20 7 days
5 Plumbing Works
Target 01/21/20 01/25/20 4 days 11111
5.1 Installation of Pipes & Fitting
Actual 01/24/20 01/28/20 4 days 22222
Target 03/11/20 03/14/20 3 days
5.2 Installation of plumbing fixtures
Actual 03/06/20 03/09/20 3 days
6 Electrical Works
Target 01/21/20 01/25/20 4 days 11111
6.1 Installation of Roughing-ins
Actual 01/24/20 01/28/20 4 days 22222
Target 03/06/20 03/10/20 4 days
6.2 Installation of AWG Wires
Actual 03/10/20 03/14/20 4 days
Target 03/18/20 03/22/20 4 days
6.3 Installation of fixtures and devices
Actual 03/22/20 03/26/20 4 days
Target 03/22/20 03/27/20 5 days
7 Demobilization
Actual 03/22/20 03/27/20 5 days
0000111111111111111143333111111111121111111111111111111322
0 0 0 0 1 2 3 4 5 6 7 8 9###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3 4 4 3 3 1 1 1 1 1 1 1 1 1 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 3
0 0 0 0 0 0 0 0 0 1 2 3 4 5 6 7 8 9###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
March
9 10 11 12 13
1 1 1 11 1 1 1
2 2 2 22 2 2 2
1 1 1 11 1 1 1
2 2 2 22222 2 2
111111
222222
11111111
22222222
1111
2222
11111
22222
11111
22222
111111
222222
2222222422223222111211121111100
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
2 2 3 3 3 3 3 4 3 3 1 1 2 2 2 2 1 1 0 0 0 0 0 2 2 2 2 2 1 0 0
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###