PERENCANAAN IRIGASI DAN BENDUNG

NAMA : IRFAN L. HENUKH


NIM : 1501110026
SEMESTER : V (Lima)
a= 1.65

NO NAMA SALURAN L (ha)


1 SALURAN KANAN LUAS AREA
STKA (Saluran Tersier KAnan)
STKA 1 71
STKA 2 62
STKA 3 50
STKA 4 45
STKA 5 17
STKA 6 35
STKA 7 20
2 SSKA (Saluran Sekunder KAnan)
SSKA 1 133
SSKA 2 183
SSKA 3 62
SSKA 4 55
3 SPKA (Saluran Primer KAnan)
SPKA 1 245
SPKA 2 300
4 SALURAN KIRI
STKI (Saluran Tersier KIri)
STKI 1 60
STKI 2 51
STKI 3 7
STKI 4 43
STKI 5 70
5 SSKI (Saluran Sekunder KIri)
SSKI 1 118
SSKI 2 113
6 SPKI (Saluran Primer Kiri)
SKPI 1 231
PERHITUNGAN NILAI Q (Debit aliran m³/dtk)
Ket = Q: debit aliran m³/dtk
RUMUS Q = L.a.c a= 1.65 L: luas daerah (ha)
1000 a: kebutuhan air normal (ltr/dtk/ha)
SALURAN KANAN c: koef. lengkung kapasitas (lihat tabel)
STKA (Saluran Tersier KAnan) SSKA (Saluran Sekunder KAnan)
STKA 1 Q= L.a.c ### SSKA 1 Q= L.a.c 0
Q= 71 . 1.65 . 1.25 Q= 133 . 1.65 . 1.015
Q= 146 ltr/dtk Q= 223 ltr/dtk
Q= 0.1464 m³/dtk Q= 0.2227 m³/dtk

STKA 2 Q= L.a.c ### SSKA 2 Q= L.a.c 0


Q= 62 . 1.65 . 1.315 Q= 183 . 1.65 . 0.95
Q= 135 ltr/dtk Q= 287 ltr/dtk
Q= 0.1345 m³/dtk Q= 0.2869 m³/dtk

STKA 3 Q= L.a.c ### SSKA 3 Q= L.a.c 0


Q= 50 . 1.65 . 1.42 Q= 62 . 1.65 . 1.315
Q= 117 ltr/dtk Q= 135 ltr/dtk
Q= 0.1172 m³/dtk Q= 0.1345 m³/dtk

STKA 4 Q= L.a.c ### SSKA 4 Q= L.a.c 0


Q= 45 . 1.65 . 1.47 Q= 55 . 1.65 . 1.375
Q= 109 ltr/dtk Q= 125 ltr/dtk
Q= 0.1091 m³/dtk Q= 0.1248 m³/dtk

STKA 5 Q= L.a.c ### SPKA (Saluran Primer KAnan)


Q= 17 . 1.65 . 2.02 SPKA 1 Q= L.a.c 0
Q= 57 ltr/dtk C= 240 = 0.917
Q= 0.0567 m³/dtk 250 = 0.91
C= 0.917 - 245 - 240 ( 0.917 - 0.91 )
STKA 6 Q= L.a.c ### 250 - 240
Q= 35 . 1.65 . 1.6 C= 0.917 - 0.5 . 0.007
Q= 92.4 ltr/dtk C= 0.91
Q= 0.0924 m³/dtk jadi Q= 245 . 1.65 . 0.91
Q= 369 ltr/dtk
STKA 7 Q= L.a.c ### Q= 0.369 m³/dtk
Q= 20 . 1.65 . 1.93
Q= 64 ltr/dtk
Q= 0.0637 m³/dtk SPKA 2 Q= L.a.c 0
Q= 300 . 1.65 . 0.89
Q= 441 ltr/dtk
Q= 0.4406 m³/dtk
SALURAN KIRI SPKI (Saluran Primer Kiri)
STKI (Saluran Tersier KIri) SKPI 1 Q= L.a.c ###
STKI 1 Q= L.a.c ### C= 230 = 0.92
Q= 60 . 1.65 . 1.33 240 = 0.917
Q= 131.7 ltr/dtk C= 0.92 - 231 - 230 ( 0.92 -0.917 )
Q= 0.1317 m³/dtk 240 - 230
C= 0.92 - 0.100 . 0.003
STKI 2 Q= L.a.c 0 C= 0.9197
Q= 51 . 1.65 . 1.41 jadi Q= 231 . 1.65 . 0.9197
Q= 118.7 ltr/dtk Q= 351 ltr/dtk
Q= 0.1187 m³/dtk Q= 0.351 m³/dtk

STKI 3 Q= L.a.c 0
Q= 7 . 1.65 . 2.5
Q= 28.88 ltr/dtk
Q= 0.0289 m³/dtk

STKI 4 Q= L.a.c 0
Q= 43 . 1.65 . 1.495
Q= 106.1 ltr/dtk
Q= 0.1061 m³/dtk

STKI 5 Q= L.a.c 0
Q= 70 . 1.65 . 1.255
Q= 145 ltr/dtk
Q= 0.1450 m³/dtk

SSKI (Saluran Sekunder KIri)


SSKI 1 Q= L.a.c 0
Q= 118 . 1.65 . 1.05
Q= 204.4 ltr/dtk
Q= 0.2044 m³/dtk

SSKI 2 Q= L.a.c 0
Q= 113 . 1.65 . 1.06
Q= 197.6 ltr/dtk
Q= 0.1976 m³/dtk
PERHITUNGAN DIMENSI SALURAN IRIGASI
SALURAN KANAN
a= 1.65
STKA (Saluran Tersier KAnan)
STKA 1 tabel pedoman
DIK= L= 71 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.30-0.35 m/dtk
Q= 0.1464 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40
A. Luas Basah
Q= F.V
F= Q = 0.1464 = 0.488 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.48813 = 0.195 = 0.44 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.44 ²
= 0.48813 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x0.44 = 0.4419 m
O= 2. 0.4419 √ 2+ 0.442
O= 1.38098 m
E. Jari-jari hidrolig
R= F = 0.4881 = 0.353 m
O 1.381
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.3535 ²

I½= 0.02840 m
I½= 0.02840 ² x 100
I= 0.081 m
STKA 2 tabel pedoman
DIK= L= 62 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.1345 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40

A. Luas Basah
Q= F.V
F= Q = 0.1345 = 0.44842 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.44842 = 0.17937 = 0.42 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.42 ²
= 0.44842 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x0.42 = 0.42 m
O= 2. 0.42 √ 2+ 0.4235
O= 1.31863 m
E. Jari-jari hidrolig
R= F = 0.4484 = 0.34006 m
O 1.31863
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.34006 ²

I½= 0.03010 m
I½= 0.03010 ² x 100
I= 0.091 m
STKA 3 tabel pedoman
DIK= L= 50 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.1172 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40

A. Luas Basah
Q= F.V
F= Q = 0.1172 = 0.3905 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.3905 = 0.1562 = 0.40 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.40 ²
= 0.3905 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.40 = 0.40 m
O= 2. 0.40 √ 2+ 0.3952
O= 1.22333 m
E. Jari-jari hidrolig
R= F = 0.3905 = 0.31921 m
O 1.22333
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.31921 ²

I½= 0.03300 m
I½= 0.03300 ² x 100
I= 0.109 m
STKA 4 tabel pedoman
DIK= L= 45 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.1091 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40

A. Luas Basah
Q= F.V
F= Q = 0.1091 = 0.36383 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.363825 = 0.14553 = 0.38 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.38 ²
= 0.36383 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.38 = 0.38 m
O= 2. 0.38 √ 2+ 0.3815
O= 1.17742 m
E. Jari-jari hidrolig
R= F = 0.3638 = 0.309 m
O 1.17742
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.309 ²

I½= 0.0346 m
I½= 0.0346 ² x 100
I= 0.120 m
STKA 5 tabel pedoman
DIK= L= 17 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.0567 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40

A. Luas Basah
Q= F.V
F= Q = 0.0567 = 0.18887 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.18887 = 0.07555 = 0.27 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.27 ²
= 0.18887 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.27 = 0.27 m
O= 2. 0.27 √ 2+ 0.2749
O= 0.82912 m
E. Jari-jari hidrolig
R= F = 0.1889 = 0.22779 m
O 0.82912
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.22779 ²

I½= 0.0534 m
I½= 0.0534 ² x 100
I= 0.285 m
STKA 6 tabel pedoman
DIK= L= 35 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.0924 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40

A. Luas Basah
Q= F.V
F= Q = 0.0924 = 0.308 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.308 = 0.1232 = 0.35 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.35 ²
= 0.308 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.35 = 0.35 m
O= 2. 0.35 √ 2+ 0.3510
O= 1.07637 m
E. Jari-jari hidrolig
R= F = 0.3080 = 0.28615 m
O 1.07637
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.28615 ²

I½= 0.0387 m
I½= 0.0387 ² x 100
I= 0.150 m
STKA 7 tabel pedoman
DIK= L= 20 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.0637 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40

A. Luas Basah
Q= F.V
F= Q = 0.0637 = 0.2123 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.2123 = 0.08492 = 0.29 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.29 ²
= 0.2123 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.29 = 0.29 m
O= 2. 0.29 √ 2+ 0.2914
O= 0.88224 m
E. Jari-jari hidrolig
R= F = 0.2123 = 0.24064 m
O 0.88224
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.24064 ²

I½= 0.0387 m
I½= 0.0387 ² x 100
I= 0.150 m
SSKA (Saluran Sekunder KAnan) tabel pedoman
SSKA 1 b : h =1
DIK= L= 133 ha v tabel = 0.30-0.35 m/dtk
a= 1.65 ltr/dtk/ha v rencana = 0.30 m/dtk
Q= 0.2227 m³ talud = 1:01
k = 45

A. Luas Basah
Q= F.V
F= Q = 0.2227 = 0.74247 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.74247 = 0.29699 = 0.54 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.54 ²
= 0.742473 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.54 = 0.54 m
O= 2. 0.54 √ 2+ 0.5450
O= 1.738766 m
E. Jari-jari hidrolig
R= F = 0.7425 = 0.42701 m
O 1.73877
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
45 .³√ 0.42701 ²

I½= 0.0191 m
I½= 0.0191 ² x 100
I= 0.036 m
SSKA 2 tabel pedoman
DIK= L= 183 ha b : h = 1,5
a= 1.65 ltr/dtk/ha v tabel = 0.35-0.40 m/dtk
Q= 0.2869 m³ v rencana = 0.35 m/dtk
talud = 1:01
k = 45

A. Luas Basah
Q= F.V
F= Q = 0.2869 = 0.81958 m²
V 0.35

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.81958 = 0.32783 = 0.57 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.57 ²
= 0.81958 m³
D. Keliling Basah
O= 2 h √2+b
b= 1.5 . h
= 1.5 x 0.57= 0.86 m
O= 2. 0.86 √ 2+ 0.573
O= 2.75505 m
E. Jari-jari hidrolig
R= F = 0.8196 = 0.29748 m
O 2.75505
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.35
45 .³√ 0.29748 ²

I½= 0.0226 m
I½= 0.0226 ² x 100
I= 0.051 m
SSKA 3 tabel pedoman
b : h =1
DIK= L= 62 ha v tabel = 0.25-0.30 m/dtk
a= 1.65 ltr/dtk/ha v rencana = 0.30 m/dtk
Q= 0.1345 m³ talud = 1:01
k = 45

A. Luas Basah
Q= F.V
F= Q = 0.1345 = 0.448 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.44842 = 0.179 = 0.42 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.42 ²
= 0.44842 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.42= 0.42 m
O= 2. 0.42 √ 2 + 0.424
O= 1.31863 m
E. Jari-jari hidrolig
R= F = 0.4484 = 0.34 m
O 1.31863
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
45 .³√ 0.34006 ²

I½= 0.0537 m
I½= 0.0537 ² x 100
I= 0.288 m
SSKA 4 tabel pedoman
b : h =1
DIK= L= 55 ha v tabel = 0.25-0.30 m/dtk
a= 1.65 ltr/dtk/ha v rencana = 0.30 m/dtk
Q= 0.1248 m³ talud = 1:01
k = 45

A. Luas Basah
Q= F.V
F= Q = 0.1248 = 0.41594 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.41594 = 0.16638 = 0.41 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.41 ²
= 0.41594 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.41 = 0.41 m
O= 2. 0.41 √ 2 + 0.408
O= 1.26588 m
E. Jari-jari hidrolig
R= F = 0.4159 = 0.32858 m
O 1.26588
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
45 .³√ 0.32858 ²

I½= 0.0280 m
I½= 0.0280 ² x 100
I= 0.078 m
SPKA (Saluran Primer KAnan) tabel pedoman
SPKA 1 b : h = 1,5
DIK= L= 245 ha v tabel = 0.35-0.40 m/dtk
a= 1.65 ltr/dtk/ha v rencana = 0.35 m/dtk
Q= 0.3693 m³ talud = 1:01
k = 45

A. Luas Basah
Q= F.V
F= Q = 0.3693 = 1.0551 m²
V 0.35

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 1.05509 = 0.422 = 0.65 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.65 ²
= 1.05509 m³
D. Keliling Basah
O= 2 h √2+b
b= 1.5 . H
= 1.5 x 0.65 = 0.974 m
O= 2. 0.974 √ 2 + 0.6496
O= 3.17242 m
E. Jari-jari hidrolig
R= F = 1.055 = 0.3326 m
O 3.1724
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.35
45 .³√ 0.3326 ²

I½= 0.0191 m
I½= 0.0191 ² x 100
I= 0.036 m
SPKA 2 tabel pedoman
b : h = 1,5
DIK= L= 300 ha v tabel = 0.40-0.45 m/dtk
a= 1.65 ltr/dtk/ha v rencana = 0.40 m/dtk
Q= 0.4406 m³ talud = 1:01
k = 45

A. Luas Basah
Q= F.V
F= Q = 0.4406 = 1.10138 m²
V 0.40

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 1.101375 = 0.44055 = 0.66 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.66 ²
= 1.10138 m³
D. Keliling Basah
O= 2 h √2+b
b= 1.5 . H
= 1.5 x 0.4476 = 1.00 m
O= 2. 1.00 √ 2 + 0.6637
O= 3.24986 m
E. Jari-jari hidrolig
R= F = 1.1014 = 0.3389 m
O 3.249861
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.40
45 .³√ 0.338899 ²

I½= 0.0212 m
I½= 0.0212 ² x 100
I= 0.045 m
SALURAN KIRI
a= 1.65
STKI 1
tabel pedoman
DIK= L= 60 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.1317 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40
A. Luas Basah
Q= F.V
F= Q = 0.1317 = 0.4389 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.4389 = 0.17556 = 0.42 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.42 ²
= 0.4389 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.42 = 0.42 m
O= 2. 0.42 √ 2+ 0.419
O= 1.30335 m
E. Jari-jari hidrolig
R= F = 0.4389 = 0.33675 m
O 1.30335
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.33675 ²

I½= 0.03050 m
I½= 0.03050 ² x 100
I= 0.093 m
STKI 2
tabel pedoman
DIK= L= 51 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.1187 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40
A. Luas Basah
Q= F.V
F= Q = 0.1187 = 0.39551 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.39551 = 0.1582 = 0.40 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.40 ²
= 0.39551 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.40 = 0.40 m
O= 2. 0.40 √ 2+ 0.39775
O= 1.23179 m
E. Jari-jari hidrolig
R= F = 0.3955 = 0.32108 m
O 1.23179
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.32108 ²

I½= 0.03270 m
I½= 0.03270 ² x 100
I= 0.107 m
STKI 3
tabel pedoman
DIK= L= 7 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = min 0.25 m/dtk
Q= 0.0289 m³ v rencana = 0.25 m/dtk
talud = 1:01
k = 40
A. Luas Basah
Q= F.V
F= Q = 0.0289 = 0.1155 m²
V 0.25

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.1155 = 0.0462 = 0.21 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.21 ²
= 0.1155 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.21 = 0.21 m
O= 2. 0.21 √ 2+ 0.214942
O= 0.639782 m
E. Jari-jari hidrolig
R= F = 0.1155 = 0.18053 m
O 0.639782
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.25
40 .³√ 0.18053 ²

I½= 0.02518 m
I½= 0.02518 ² x 100
I= 0.063 m
STKI 4
tabel pedoman
DIK= L= 43 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.25-0.30 m/dtk
Q= 0.1061 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40
A. Luas Basah
Q= F.V
F= Q = 0.1061 = 0.35357 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.35357 = 0.14143 = 0.38 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.38 ²
= 0.35357 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.38 = 0.38 m
O= 2. 0.38 √ 2+ 0.37607
O= 1.15938 m
E. Jari-jari hidrolig
R= F = 0.3536 = 0.30496 m
O 1.15938
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.30496 ²

I½= 0.03520 m
I½= 0.03520 ² x 100
I= 0.124 m
STKI 5
tabel pedoman
DIK= L= 70 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.30-0.35 m/dtk
Q= 0.1450 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 40
A. Luas Basah
Q= F.V
F= Q = 0.1450 = 0.48318 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.48318 = 0.19327 = 0.44 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.44 ²
= 0.48318 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.44 = 0.44 m
O= 2. 0.44 √ 2+ 0.43962
O= 1.37333 m
E. Jari-jari hidrolig
R= F = 0.4832 = 0.35183 m
O 1.37333
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
40 .³√ 0.35183 ²

I½= 0.02860 m
I½= 0.02860 ² x 100
I= 0.082 m
SSKI (Saluran Sekunder KIri)
SSKI 1 tabel pedoman
DIK= L= 118 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.30-0.35 m/dtk
Q= 0.2044 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 45
A. Luas Basah
Q= F.V
F= Q = 0.2044 = 0.68145 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √F h= √ 0.68145 = 0.27258 = 0.52 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.52 ²
= 0.68145 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.52 = 0.52 m
O= 2. 0.52 √ 2+ 0.52209
O= 1.6582784 m
E. Jari-jari hidrolig
R= F = 0.6815 = 0.41094 m
O 1.65828
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
45 .³√ 0.41094 ²

I½= 0.02020 m
I½= 0.02020 ² x 100
I= 0.041 m
SSKI 2
tabel pedoman
DIK= L= 113 ha b : h =1
a= 1.65 ltr/dtk/ha v tabel = 0.30-0.35 m/dtk
Q= 0.1976 m³ v rencana = 0.30 m/dtk
talud = 1:01
k = 45
A. Luas Basah
Q= F.V
F= Q = 0.1976 = 0.65879 m²
V 0.30

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 0.65879 = 0.26352 = 0.51 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.51 ²
= 0.65879 m³
D. Keliling Basah
O= 2 h √2+b
b= 1 . h
= 1 x 0.51 = 0.51 m
O= 2. 0.51 √ 2+ 0.51334
O= 1.62764 m
E. Jari-jari hidrolig
R= F = 0.6588 = 0.40475 m
O 1.62764
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.30
45 .³√ 0.40475 ²

I½= 0.02072 m
I½= 0.02072 ² x 100
I= 0.043 m
SPKI (Saluran Primer Kiri)
SKPI 1 tabel pedoman
DIK= L= 231 ha b : h = 1.5
a= 1.65 ltr/dtk/ha v tabel = 0.35-0.40 m/dtk
Q= 0.3505 m³ v rencana = 0.35 m/dtk
talud = 1:01
k = 45
A. Luas Basah
Q= F.V
F= Q = 0.3505 = 1.00155 m²
V 0.35

B. h Rencana
F= 2.5 h²
h² = F
2.5
h= √ F h= √ 1.00155 = 0.40062 = 0.63 m
2.5 2.5
C. Kontrol F
F= 2.5 . 0.63 ²
= 1.00155 m³
D. Keliling Basah
O= 2 h √2+b
b= 1.5 . h
=1.5 x 0.4249 = 0.95 m
O= 2. 0.95 √ 2+ 0.63
O= 3.08112 m
E. Jari-jari hidrolig
R= F = 1.0016 = 0.32506 m
O 3.08112
F. Kemiringan dasar saluran
V= K . R²/³ . I½
I½= V
K . R²/³
I½= V
K . ³√R²

I½= 0.35
45 .³√ 0.32506 ²

I½= 0.01984 m
I½= 0.01984 ² x 100
I= 0.039 m