Sie sind auf Seite 1von 1

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA


(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 60,5756 24.996,34 1.514.169,03


2. Tukang (L02) Jam 36,3454 25.827,27 938.701,83
3. Mandor (L03) Jam 6,0576 30.066,21 182.128,00

JUMLAH HARGA TENAGA 2.634.998,86

B. BAHAN

1. Beton 30 Mpa (M59) M3 4,5938 2.228.721,01 10.238.298,59


2. Baja Tulangan (M39) Kg 1.071,2742 11.500,00 12.319.652,84
3. Urugan Porus (EI-241) M3 2,6040 245.773,23 639.993,50
4. Mat. Pilihan (M09) M3 563,0400 25.000,00 14.076.000,00
5 Cetakan ukuran 400 x 300 bh/M' 1,0000 1.965.968,85 1.965.968,85

JUMLAH HARGA BAHAN 39.239.913,78

C. PERALATAN

1. Tamper (E25) Jam 679,2578 99.646,36 67.685.572,46


2. Flat Bed Truck (E11) Jam 6,0576 327.365,72 1.983.038,66
3. Alat Bantu Ls 1,0000 0,00 0,00

JUMLAH HARGA PERALATAN 69.668.611,11

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 111.543.523,75


E. OVERHEAD & PROFIT 10,0 % x D 11.154.352,38
F. HARGA SATUAN PEKERJAAN ( D + E ) 122.697.876,13