A. 4.1.1.1 Membuat 1 m3 beton mutu f'c = 7.4 Mpa (K 100),slump (12 ± 2) cm, w/c = 0.87
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 247 1,631.50 402,980.50
Pasir Beton kg 869 418.33 363,531.67
Kerikil (Maks 30 mm) kg 999 418.33 417,915.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,205,927.17
C PERALATAN
A. 4.1.1.3 Membuat 1 m3 beton mutu f'c = 12.2 Mpa (K 150),slump (12 ± 2) cm, w/c = 0.72
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 299 1,631.50 487,818.50
Pasir Beton kg 799 418.33 334,248.33
Kerikil (Maks 30 mm) kg 1,017 418.33 425,445.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,269,011.83
C PERALATAN
A. 4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7.4 Mpa (K 100),slump (3 - 6) cm, w/c = 0.87
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.200 100,000.00 120,000.00
Tukang batu OH 0.200 131,000.00 26,200.00
Kepala Tukang OH 0.020 157,000.00 3,140.00
Mandor OH 0.060 118,000.00 7,080.00
Jumlah Tenaga Kerja 156,420.00
B BAHAN
Semen Portland kg 230 1,631.50 375,245.00
Pasir Beton kg 893 418.33 373,571.67
Kerikil (Maks 30 mm) kg 1,027 418.33 429,628.33
Air Liter 200 100.00 20,000.00
Jumlah Harga Bahan 1,198,445.00
C PERALATAN
A. 4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0.61
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 352 1,631.50 574,288.00
Pasir Beton kg 731 418.33 305,801.67
Kerikil (Maks 30 mm) kg 1,031 418.33 431,301.67
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,332,891.33
C PERALATAN
A. 4.1.1.7 Membuat 1 m3 beton mutu f'c = 19.3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0.58
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 371 1,631.50 605,286.50
Pasir Beton kg 698 418.33 291,996.67
Kerikil (Maks 30 mm) kg 1,047 418.33 437,995.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,356,778.17
C PERALATAN
A. 4.4.1.7 Pemasangan 1 m2 dinding bata merah (5 x11x 22) cm tebal 1/2 batu campuran 1SP : 2PP
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang batu OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.015 118,000.00 1,770.00
Jumlah Tenaga Kerja 46,440.00
B BAHAN
Bata Merah bh 70.000 1,192.00 83,440.00
Semen Portland kg 18.950 1,631.50 30,916.93
Pasir Pasang m3 0.038 156,875.00 5,961.25
Jumlah Harga Bahan 120,318.18
C PERALATAN
A. 4.5.1.7 Pemasangan 1 m2 Langit-langit Gypsum Board ukuran (120 x 240) cm, tebal 9 mm
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Tukang Kayu OH 0.050 131,000.00 6,550.00
Kepala Tukang OH 0.005 157,000.00 785.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 17,925.00
B BAHAN
Gypsum Board Lembar 0.364 200,800.00 73,091.20
Paku Skrup kg 0.110 31,500.00 3,465.00
Jumlah Harga Bahan 76,556.20
C PERALATAN
A. 4.7.1.4 Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.070 100,000.00 7,000.00
Tukang Cat OH 0.009 131,000.00 1,179.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 9,475.00
B BAHAN
Cat Menie kg 0.200 81,575.00 16,315.00
Plamur kg 0.150 27,610.00 4,141.50
Cat Dasar kg 0.170 52,710.00 8,960.70
Cat Penutup kg 0.260 175,700.00 45,682.00
Kuas Bh 0.010 31,375.00 313.75
Pengencer/Thinner kg 0.030 31,375.00 941.25
Amplas Lbr 0.200 12,550.00 2,510.00
Jumlah Harga Bahan 78,864.20
C PERALATAN
A. 4.7.1.12 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.028 100,000.00 2,800.00
Tukang Cat OH 0.042 131,000.00 5,502.00
Kepala Tukang OH 0.0042 157,000.00 659.40
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 9,315.40
B BAHAN
Cat Dasar kg 0.120 52,710.00 6,325.20
Cat Penutup kg 0.180 175,700.00 31,626.00
Jumlah Harga Bahan 37,951.20
C PERALATAN