REALISASI PLANNING GENERAL OVERHAUL EXCAVATOR PC 200

PERIODE BULAN OKTOBER 2021 - NOVEMBER 2021


OKTOBER NOVEMBER
NO EQUIPMENT AKTIVITY R K J S M S S R K J S M S S R K KETERANGAN
20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
1 prepare

2 Pelepasan cylinder head cover

3 pelepasan Injektor

4 pelepasan head bold

5 pelepasan cylinder h+C10:C26ead

6 pelepasan exhaust manifold & turbo charge

7 pelepas distributor

8 pelepas join copling & flywheel

9 pelepasan fuel pump

10 pelepasan alternator

11 pelepasan oil cooler

12 pelepasan oil plan

13 pelepasan piston

14 pelepasan fan pullay

15 pelepasan chamshaft
pelepasan crankshaft balancer
16

17 pelepasan chamshaft pullay

18 pelepasan chamshaft timing gear

19 pelepasan cranjshaft timing gear

20 pelepasan connecting rod cap

21 pelepasan crankshaft

22 cleanning engine block

23 cleanning oil pan & oil pump

24 cleanning Hydrolick pump

25 Cleanning cylinder head dan intek manifold

26 c;eanning cover transmisi

27 cleanning exhaust manifold

28 cleaning join copling

29 pemasangan piston

30 Pemasangan tapet camp

31 pemasangan main bearing new 7 set

32 pemasangan press water pump new

33 EXCAVATOR pemasangan oil pump new

34 pemasangan coller new

35 pemasangan seal shaft belakanhg

36 pemasangan gear timing

37 pemasangan cover gear belakang

38 pemasangan cover flywheel

39 pemasangan flywheel

40 pemasangan piston new 6 each


EXCAVATOR

41 pemasangan ring piston new 6 each

42 pemasangan piston ke cylinder linner block

43 skir valve 24 each

44 pemasangan steam seal new

45 pemasangan oil jet new 6 each

46 pemasangan pipa oil pump

47 pemasangan oil pan & gasket new

48 pemasangan packing cylinder head new

49 pemasangan steam seal new 24 each

50 pemasangan spring valve new 24 each

51 pemasangan plug spring new 24 each

52 pemasangan coter new 24 each

53 pemasangan cylinder head

54 pemasangan conrood bearing new 6 each

55 pemasangan injektor new 6 each

56 pemasangan pump hydroulick

57 pemasangan termostart new

58 pemasangan sensor oil new

59 pemasangan sensor udara bilas

60 pemasangan pipa injector

61 double chek kegiatan

62 cleanning area engine excavator

63 running test

64

65

KET
PLANNING
LIBUR
Cirebon, 5 November 2021
Mengetahui,

PT. JASA PERALATAN PELABUHAN INDONESIA PT. JASA PERALATAN PELABUHAN INDONESIA
CABANG BANTEN

DADANG ANA MULYANA


Koordinator Area Senior Chief Specialist (Maintenance Peralatan Marine )
REALISASI PEKERJAAN GENERAL OVERHAUL GANTRY LUFFING CRANE
PERIODE BULAN NOVEMBER 2021 - DESEMBER 2021

NOVEMBER DESEMBER
NO EQUIPMENT EQUIPMENT S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R KETERANGAN
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29 30 31 1 2 3 4 5 6 7 8
PEKAN PERTAMA

1 GANTRY LUFFING CRANE

PEKAN KE DUA

2 GANTRY LUFFING CRANE

PEKAN KE TIGA

3 GANTRY LUFFING CRANE

PEKAN KE TIGA
4 GANTRY LUFFING CRANE

REALISASI
PEKERJAAN MINGGU SEBELUMNYA
LIBUR

Deskripsi Jumlah Persentase


Pekerjaan Terealisasi 70 71%
Pekerjaan Tidak Terealisasi 29 33%
Jumlah Pekerjaan 89 103%

Cirebon, 2021
Mengetahui,

PT. JASA PERALATAN PELABUHAN INDONESIA


PT. JASA PERALATAN PELABUHAN INDONESIA
CABANG BANTEN

ANA MULYANA
DADANG
KOORDINATOR AREA