BACK UP VOLUME RESERVOIR KAP.

100 M3

SKET GAMBAR
Perhitungan

1 2 3 4

1. Galian Tanah

a. Segmen 1 b. Segmen 2 c. Segmen 3 d. Segmen 4


Panjang = 1.40 m Panjang = 9.44 m Panjang = 1.66 m Panjang = 1.40 m
Tinggi Galian = 0.70 m Tinggi Galian = 1.25 m Tinggi Galian = 1.55 m Tinggi Galian = 1.55 m
Lebar Galian = 2.80 m Lebar Galian = 5.90 m Lebar Galian = 5.90 m Lebar Galian = 3.60 m
Volume Segmen 1 = 2.74 m3 Volume Segmen 1 = 69.62 m3 Volume Segmen 1 = 15.18 m3 Volume Segmen 1 = 7.81 m3
Total Volume Galian Tanah = 95.36 M3
Perhitungan

2. Pekerjaan Anstamping

a. Segmen 1 b. Segmen 2 c. Segmen 3 d. Segmen 4


Panjang = 1.40 m Panjang = 9.44 m Panjang = 2.24 m Panjang = 1.40 m
Tinggi Anstamping = 0.30 m Tinggi Anstamping = 0.30 m Tinggi Anstamping = 0.30 m Tinggi Anstamping = 0.30 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 5.90 m Lebar = 3.60 m
Volume Segmen 1 = 1.18 m3 Volume Segmen 1 = 16.71 m3 Volume Segmen 1 = 3.96 m3 Volume Segmen 1 = 1.51 m3
Total Anstamping = 23.36 M3

3. Urugan Sirtu Padat

a. Segmen 1 b. Segmen 2 c. Segmen 3 d. Segmen 4


Panjang = 1.60 m Panjang = 9.44 m Panjang = 2.24 m Panjang = 1.40 m
Tinggi Anstamping = 0.10 m Tinggi Anstamping = 0.10 m Tinggi Anstamping = 0.10 m Tinggi Anstamping = 0.10 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 5.90 m Lebar = 3.60 m
Volume Segmen 1 = 0.45 m3 Volume Segmen 1 = 5.57 m3 Volume Segmen 1 = 1.32 m3 Volume Segmen 1 = 0.50 m3
Total Anstamping = 7.84 M3

4. Lantai Kerja Beton Cam. 1:3:5 tebal 5 cm

a. Segmen 1 b. Segmen 2 c. Segmen 3 d. Segmen 4


Panjang = 1.60 m Panjang = 9.44 m Panjang = 2.24 m Panjang = 1.40 m
Tinggi Anstamping = 0.05 m Tinggi Anstamping = 0.05 m Tinggi Anstamping = 0.05 m Tinggi Anstamping = 0.05 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 5.90 m Lebar = 3.60 m
Volume Segmen 1 = 0.22 m3 Volume Segmen 2 = 2.78 m3 Volume Segmen 3 = 0.66 m3 Volume Segmen 4 = 0.25 m3
Total Anstamping = 3.92 M3

1
2 3

Beton Plat Lantai


Perhitungan

5. Pekerjaan Plat Lantai


a. Beton Plat Lantai

1. Pekerjaan Beton Plat Lantai 1 2. Pekerjaan Beton Plat Lantai 2 3. Pekerjaan Beton Plat Lantai 3
Panjang = 1.60 m Panjang = 10.73 m Panjang = 1.85 m
Tebal Beton = 0.25 m Tebal Beton = 0.30 m Tebal Beton = 0.30 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 3.60 m
Volume 1 = 1.12 m3 Volume 2 = 18.99 m3 Volume 3 = 2.00 m3
Volume Beton Plat Lantai = 22.11 M3

2. Bekisting Lantai reservoir


Panjang = 45.60 m
Lebar = 0.25 m
Volume 1 = 11.40 m3
Volume Bekisting Lantai Reservoir = 11.40 M2

b.Penulangan Plat Lantai


1. Penulangan Plat Lantai 1 ( Ø12 - 150 mm) 2. Penulangan Plat Lantai 2 ( Ø12 - 150 mm) 3. Penulangan Plat Lantai 3 ( Ø12 - 150 mm)
Panjang = 1.60 m Panjang ###
= 10.73 m Panjang =### 1.85 m
Lebar = 2.80 m Lebar ###
= 5.90 m Lebar =### 3.60 m
Berat Tulangan = 0.89 Kg/m Berat Tulangan ###
= 0.89 Kg/m Berat Tulangan =### 0.89 Kg/m

Penulangan Arah Memanjang - 150 mm Penulangan Arah Memanjang - 150 mm Penulangan Arah Memanjang - 150 mm
Jumlah Tulangan = 10.67 m Jumlah Tulangan ###= 39.33 m Jumlah Tulangan =### 12.33 m
Panjang Tul. = 3.05 m Panjang Tul. ###
= 11.03 m Panjang Tul. =### 3.90 m
Panjang Total Tul. = 32.53 M Panjang Total Tul.###
= 433.85 M Panjang Total Tul. =### 48.10 M
Berat Tulangan = 29.01 Kg Berat Tulangan ### = 386.85 Kg Berat Tulangan =### 42.89 Kg

Penulangan Arah Melintang - 150 mm Penulangan Arah Melintang - 150 mm Penulangan Arah Melintang - 150 mm
Jumlah Tulangan = 18.67 m Jumlah Tulangan ###= 71.53 m Jumlah Tulangan =### 24.00 m
Panjang Tul. = 1.85 m Panjang Tul. ###
= 6.20 m Panjang Tul. =### 2.15 m
Panjang Total Tul. = 34.53 M Panjang Total Tul.###
= 443.51 M Panjang Total Tul. =### 51.60 M
Berat Tulangan = 30.79 Kg Berat Tulangan ### = 395.46 Kg Berat Tulangan =### 46.01 Kg
Total Tulangan Plat Lantai

Berat Total Tul. = 119.60 Kg Berat Total Tul. ###


= 1,564.61 Kg Berat Total Tul. =### 177.80 Kg 1,862.01 Kg
Sketsa Perhitungan

6. Perhitungan Dinding
a. Perhitungan Dinding Utama
Panjang = 27.40 m Panjang = 5.00 m
Tinggi = 2.60 m Tinggi = 2.90 m
Tebal Dinding = 0.25 m Tebal Dinding = 0.25 m
Volume 1 = 17.81 m3 Volume 1 = 3.63 m3
Volume Total Dinding Utama = 21.44 m3
Bakisting = 142.48 m2 Bakisting = 29.00 m2
Total Bakisting Dinding Utama = 171.48 m2
Acian Luar = 36.99 m2 Bakisting = 29.00 m2
Acian Dalam = 71.24 m2
Total Acian = 137.23 m2

- Penulangan Beton Dinding ( Ø12 - 150 mm) - Penulangan Beton Dinding ( Ø12 - 150 mm)
Arah Memanjang - 150 Arah Memanjang - 150
Jumlah Tulangan = 17.33 Btng Jumlah Tulangan = 19.33 Btng
Panjang Tulangan = 27.65 m Panjang Tulangan = 5.25 m
Berat Tulangan Ø12 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 854.69 Kg Berat Total Tul. = 181.01 Kg

Arah Melintang - 150 Arah Melintang - 150


Jumlah Tulangan = 182.67 Btng Jumlah Tulangan = 33.33 Btng
Panjang Tulangan = 2.85 m Panjang Tulangan = 3.15 m
Berat Tulangan Ø12 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 928.40 Kg Berat Total Tul. = 187.25 Kg

Berat Total Tulangan Untuk Dinding Utama = 2,151.35 Kg

b. Perhitungan Skat Dinding


Panjang = 4.00 m
Tinggi = 2.60 m
Tebal Dinding = 0.20 m
1 Volume 1 = 2.08 m3
2 3 4 Untuk 3 Skat Dinding = 6.24 m3
Bakisting Skat = 62.40 m2
Acian = 62.40 m2
- Penulangan Beton Dinding ( Ø12 - 150 mm)
Arah Memanjang - 150
Jumlah Tulangan = 17.33 Btng
Panjang Tulangan = 4.25 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 131.37 Kg

Arah Melintang - 150


Jumlah Tulangan = 26.67 Btng
Panjang Tulangan = 2.85 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 135.53 Kg
Volume Total Beton Dinding Skat = 800.72 Kg
Sketsa Perhitungan

c. Perhitungan Dinding Bangunan Kontrol In dan Out


Panjang = 3.65 m Panjang = 4.45 m
Tinggi = 2.10 m Tinggi = 2.90 m
Tebal Dinding = 0.20 m Tebal Dinding = 0.20 m
Volume 1 = 1.53 m3 Volume 1 = 3.14 m
Volume Total Dinding Utama = 4.67 m3
Bakisting = 15.33 Bakisting = 25.81 m2
Volume Bakisting = 41.14 m2
Acian Dalam = 7.67 m2 Acian Dalam = 12.91 m2
Acian Luar = 5.11 m2 Acian Luar = 6.01 m2
Total Acian = 31.69 m2

- Penulangan Beton Dinding ( Ø12 - 150 mm) - Penulangan Beton Dinding ( Ø12 - 150 mm)
Arah Memanjang - 150 Arah Memanjang - 150
Jumlah Tulangan = 14.00 Btng Jumlah Tulangan = 19.33 Btng
Panjang Tulangan = 3.90 m Panjang Tulangan = 4.70 m
Berat Tulangan Ø12 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 97.37 Kg Berat Total Tul. = 162.05 Kg

Arah Melintang - 150 Arah Melintang - 150


Jumlah Tulangan = 24.33 Btng Jumlah Tulangan = 29.67 Btng
Panjang Tulangan = 2.35 m Panjang Tulangan = 3.15 m
Berat Tulangan Ø12 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 101.98 Kg Berat Total Tul. = 166.65 Kg

Berat Total Tulangan Untuk Dinding Utama = 528.05 Kg

a. Beton K-225 = 32.35 m3


b. Bakisting = 275.02 m2
c. Penulangan Polos Ø12 = 3,480.12 Kg
d. Acian Tembok = 231.32 M2
e. Pengcetan = 48.11 M2
Sketsa Perhitungan

7. Perhitungan Plat atas


Panjang = 2.00 m Panjang = 11.65 m
Lebar = 1.80 m Lebar = 5.50 m
Tebal Plat = 0.15 m Tebal Dinding = 0.15 m
Volume 1 = 0.54 m3 Volume 2 = 10.03 m
Volume Total Plat Atas = 10.57 m3
Bakisting = 3.60 Bakisting = 64.08 m2
Volume Bakisting = 67.68 m2

- Penulangan Beton Plat ( Ø12 - 150 mm) - Penulangan Beton Plat ( Ø12 - 150 mm)
Arah Memanjang - 150 Arah Memanjang - 150
Jumlah Tulangan = 12.00 Btng Jumlah Tulangan = 36.67 Btng
Panjang Tulangan = 2.25 m Panjang Tulangan = 11.90 m
Berat Tulangan Ø12 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 48.15 Kg Berat Total Tul. = 778.13 Kg

Arah Melintang - 150 Arah Melintang - 150


Jumlah Tulangan = 13.33 Btng Jumlah Tulangan = 77.67 Btng
Panjang Tulangan = 2.05 m Panjang Tulangan = 5.75 m
Berat Tulangan Ø12 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 48.74 Kg Berat Total Tul. = 796.41 Kg

Berat Total Tulangan Untuk Plat Atas = 1,671.43 Kg

a. Beton Plat Atas K-225 = 10.57 m3


b. Bakisting Plat = 67.68 m2
c. Tulangan Ø12 = 1,671.43 Kg
Uraian Volume Reservoar

Jenis Pekerjaan Satuan Volume

1. Galian Tanah M3 95.36

2. Pekerjaan Anstamping M3 23.36

3. Urugan Sirtu Padat M3 7.84

4. Lantai Kerja Beton Cam. 1:3:5 tebal 5 cm M3 3.92

5. Pekerjaan Plat Lantai

a. Beton Plat Lantai M3 22.11

b.Penulangan Plat Lantai Kg 1,862.01

c. Bekisting M2 11.40

6. Perhitungan Dinding

a. Beton K-225 M3 32.35

b. Bakisting M2 275.02

c. Penulangan Polos Ø12 Kg 3,480.12

d. Acian Tembok M2 231.32

e. Pengcetan M2 48.11

7. Perhitungan Plat atas

a. Beton Plat Atas K-225 M3 10.57

b. Bakisting Plat M2 67.68

c. Tulangan Ø12 Kg 1,671.43


BACK UP VOLUME BAK PENGUMPUL KAP. 10 M3

Sketsa Perhitungan

1. Galian Tanah
a. Galian Tanah 1 b. Galian Tanah 2
Lebar Atas = 1.30 m Lebar Atas = 0.86 m
Lebar Bawah = 0.76 m Lebar Bawah = 0.59 m
Tinggi = 2.68 m Tinggi = 1.62 m
Lebar Bangunan = 2.30 m Lebar Bangunan = 2.30 m
Volume Galian 1 = 6.35 m3 Volume Galian 1 = 2.70 m3

- Pengurangan Galian 2
Alas = 0.20 m
Tinggi = 0.20 m
Volume = 0.05 m3
Volume Galian 2 = 2.66 m3
Total Volume Galian Tanah = 9.00 m3

2. Pekerjaan Pasangan dan Urugan


Panjang = 4.38 m
Lebar = 2.30 m

a. Pekerjaan Pasangan Batu kali


Tinggi = 0.30 m
Volume = 3.02 m3

b. Urugan Pasir c. Lantai Kerja


Tebal = 0.10 m Tebal = 0.05 m
Volume = 1.01 m3 Volume = 0.50 m3

2. Pekerjaan Struktur
a. Plat Lantai b. Bekisting
Tebal = 0.20 m Panjang = 4.38 m
Volume = 2.01 m3 Lebar = 2.30 m
Berat Tulangan = 0.89 Kg/m Volume = 2.67 M2

- Penulangan Plat Lantai 1 ( Ø12 - 100 mm)


Penulangan Arah Memanjang - 100 mm
Jumlah Tulangan = 23.00 m
1 Panjang Tul.
Panjang Total Tul.
=
=
4.63
106.49
m
M
Berat Tulangan = 94.95 Kg
2
Penulangan Arah Melintang - 150 mm
Jumlah Tulangan = 43.80 m
Panjang Tul. = 2.55 m
Panjang Total Tul. = 111.69 M
Berat Tulangan = 99.59 Kg
Sket Kemirian Galian Tanah Total Tulangan Plat Lantai = 194.54 Kg
Sketsa Perhitungan

b. Pekerjaan Struktur Dinding


Dinding 1 Dinding 2
Panjang = 3.30 m LA = 3.30 m
Tinggi = 2.10 m LB = 2.10 m
Tebal = 0.15 m T = 0.20 m
Volume Beton = 2.08 m3 Volume = 0.16 m3
1 Bakisting = 27.72 m2 Bakisting = 2.16 m2

Dinding 3 Dinding 4
Panjang = 2.30 m Panjang = 2.30 m
Tinggi = 2.10 m Tinggi = 2.30 m
Tebal = 0.15 m Tebal = 0.15 m
Volume Beton = 1.45 m3 Volume Beton = 1.59 m3
Bakisting = 9.66 m2 Bakisting = 10.58 m2
2
- Penulangan 1 ( Ø10 - 150 mm dan Ø12 - 100 mm)
Berat Tulangan Ø10 = 0.62 Kg/m
Berat Tulangan Ø12 = 0.89 Kg/m

Panjang = 3.30 m
Tinggi = 2.30 m
Penulangan memanjang Ø12 Penulangan melintang Ø10
Jumlah Tulangan = 23.00 Bt Jumlah Tulangan = 22.00 Bt
Panjang Tulangan = 3.80 m Panjang Tulangan = 2.80 m
Berat Tulangan = 155.86 Kg Berat Tulangan = 75.97 Kg

- Penulangan 2 ( Ø10 - 150 mm dan Ø12 - 100 mm)


Berat Tulangan Ø10 = 0.62 Kg/m
Berat Tulangan Ø12 = 0.89 Kg/m

Panjang = 2.30 m
Tinggi = 2.10 m

Penulangan memanjang Ø12 Penulangan melintang Ø10


Jumlah Tulangan = 21.00 Bt Jumlah Tulangan = 15.33 Bt
Panjang Tulangan = 3.00 m Panjang Tulangan = 2.60 m
Berat Tulangan = 56.18 Kg Berat Tulangan = 24.58 Kg

- Penulangan 3 ( Ø10 - 150 mm dan Ø12 - 100 mm)


Berat Tulangan Ø10 = 0.62 Kg/m
Berat Tulangan Ø12 = 0.89 Kg/m

Panjang = 2.30 m
Tinggi = 2.30 m

Penulangan memanjang Ø12 Penulangan melintang Ø10


Jumlah Tulangan = 23.00 Bt Jumlah Tulangan = 15.33 Bt
Panjang Tulangan = 2.80 m Panjang Tulangan = 2.80 m
Berat Tulangan = 57.42 Kg Berat Tulangan = 26.48 Kg
Sketsa Perhitungan

- Beton Dinding K-225 = 5.28 M3


- Pekerjaan Bakisting = 50.12 M2
- Penulangan = 396.50 Kg

c. Pekerjaan Plat Atap


Panjang = 3.30 m
Lebar = 2.30 m
Tebal = 0.10 m

Pengurangan
Panjang = 0.70 m
Lebar = 0.70 m

Volume = 0.71 m3
Bakisting = 7.59 m2

- Penulangan ( Ø10 - 150 mm dan Ø12 - 100 mm)


Berat Tulangan Ø10 = 0.62 Kg/m
Berat Tulangan Ø12 = 0.89 Kg/m

Panjang = 3.30 m
Tinggi = 2.30 m

Penulangan memanjang Ø12 Penulangan melintang Ø10


Jumlah Tulangan = 23.00 Bt Jumlah Tulangan = 22.00 Bt
Panjang Tulangan = 3.80 m Panjang Tulangan = 2.80 m
Berat Tulangan = 155.86 Kg Berat Tulangan = 75.97 Kg

- Beton Plat Atap K-225 = 0.71 M3


- Pekerjaan Bakisting = 7.59 M2
- Penulangan = 231.84 Kg

3. Pekerjaan Finishing
a. Pekerjaan Acian Luar B. Pekerjaan Acian dalam
Lebar Atas = 2.30 m Panjang = 3.30 m
Lebar Bawah = 1.51 m Tinggi = 2.30 m
Tinggi = 3.30 m
Luas = 12.57 m2 Luas = 15.18 m2

c. Pekerjaan Acian Melintang Luar d. Pekerjaan Acian Melintang Dalam


Panjang = 1.51 m Panjang = 2.10 m
Tinggi = 2.30 m Tinggi = 2.30 m
Luas = 3.47 m2 Luas = 4.83 m2

c. Pekerjaan Acian Melintang 2


Panjang = 2.30 m
Tinggi = 2.30 m

Luas = 10.58 m2
- Pekerjaan Acian = 46.64 m2
- Pekerjaan Pengecetan = 21.34 m2
Uraian Volume Bak Pengumpul

Jenis Pekerjaan Satuan Volume

1. Galian Tanah M3 9.00

2. Pekerjaan Pasangan dan Urugan


a. Pekerjaan Pasangan Batu kali 3.02

b. Urugan Pasir m3 1.01

c. Lantai Kerja m3 0.50

2. Pekerjaan Struktur
a. Plat Lantai
- Pekerjaan Beton K-225 m3 2.01
- Pekerjaan Penulangan Polos Kg 194.54

b. Pekerjaan Struktur Dinding


- Beton Dinding K-225 m3 5.28
- Pekerjaan Bakisting m2 50.12
- Penulangan Kg 396.50

c. Pekerjaan Plat Atap


- Beton Plat Atap K-225 M3 0.71
- Pekerjaan Bakisting M2 7.59
- Penulangan Kg 231.84

3. Pekerjaan Finishing
- Pekerjaan Acian M2 46.64
- Pekerjaan Pengecetan M2 21.34
BAK UMUM KAP. 4,5 M3

SKET GAMBAR

0.15

0.20

1.00

0.20 0.20 1.50 0.20 0.20 1.00

KRAN KRAN
Man Hole
0.20 0.20

0.20 0.20

Pipa Hawa HDPE Ø 63 mm

KRAN
A

1.50
1.50

KRAN
0.25 0.25

0.20 0.20

0.20 0.20

KRAN KRAN

0.80
1.00 1.00

0.20 0.20 1.00 0.80

0.15 0.15

KOLAM RESAPAN

B
Perhitungan

Pipa Hawa
Ø50mm

0 .20 0.70 0.20 0 .60 0.20

Plat Atas (T = 12 cm)


0.15

0 .12
Bend 90°
0.20
Muka Air

Kran Pelampung
Wather Stop
Ta ngga Pipa GIP Ø 25 mm

2.47
1 .80
2 .20
2.00

1 .50 Plat Dinding (T = 20 cm)

0.20 1 .00

Plat Lantai (T = 25 cm) Kran

Lantai beton K-125


0 .25
Sirtu (10 cm)
0.75 Pas. Batu Kosong

1 .00

0 .30
Bend 90° Pas. Batu Bataco 0.50

Pas. Pondasi 1 Pc : 4Ps

Pas. Batu Kosong 0 .20


Lantai beton K-125
Urugan Pasir 0 .10 Sirtu (5 cm)
Pas. Batu Kosong
0.10 0 .60 0.10 0 .10 0.60 0.10
0 .80 0 .90 0.80

0.85 0.15 0 .20 0.15


Lantai Kerja beton K-100 (5 cm)
Sirtu (10 cm)
U rugan Ta nah Dipadatkan

POTONGAN A - A
SKALA 1 : 30

1. Galian Tanah

a. Segmen 1 b. Segmen 2
Panjang = 6.00 m Panjang = 10.90 m
Tinggi Galian = 0.25 m Tinggi Galian = 0.20 m
Lebar Galian = 0.80 m Lebar Galian = 0.85 m
Volume Segmen 1 = 1.20 m3 Volume Segmen 1 = 1.85 m3
3.05
Total Volume Galian Tanah = M3
Perhitungan

2. Pekerjaan Anstamping

a. Segmen 1 b. Segmen 2 a. Pas. Batu Kali


Panjang = 6.00 m Panjang = 10.90 m Panjang = 8.40 m
Tinggi Anstamping = 0.10 m Tinggi Anstamping = 0.20 m Tinggi Anstamping = 0.70 m
Lebar = 0.80 m Lebar = 0.85 m Lebar = 0.40 m
Volume Segmen 1 = 0.48 m3 Volume Segmen 1 = 1.85 m3 Volume Segmen 1 = 2.35 m3
Total Anstamping = 2.33 M3

Total Pas batu Kali 1:4 = 2.35 0

3. Urugan Pasir

a. Segmen 1 - Urugan Sirtu b. Segmen 2 - Urugan Pasir c. Segmen 3 - Urugan Sirtu lantai luar
Panjang = m Panjang = m Panjang = m
Tinggi = m Tinggi = m Tinggi = m
Lebar = m Lebar = m Lebar = m
Volume Segmen 1 = - m3 Volume Segmen 1 = - m3 Volume Segmen 1 = - m3
-
Total Sirtu Padat = M3
-
Total Urugan Pasir = M3

4. Pekerjaan Beton

a. Segmen 1 - Beton K-125 b. Segmen 2- Lantai Kerja Beton K-100 c. Segmen 3- Lantai Beton K-125
Panjang = 10.90 m Panjang = 1.50 m Panjang = m
Tinggi = 0.08 m Tinggi = 0.08 m Tinggi = m
Lebar = 0.85 m Lebar = 1.50 m Lebar = m
Volume Segmen 1 = 0.69 m3 Volume Segmen 2 = 0.17 m3 Volume Segmen 1 = - m3
0.69
Beton K-125 = M3
0.17
Beton K-100 = M3
Perhitungan

5. Pekerjaan Plat Lantai


a. Beton Plat Lantai

1. Pekerjaan Beton Plat Lantai 1


Panjang = 2.10 m
Tebal Beton = 0.20 m
Lebar = 2.10 m
Volume 1 = 0.88 m3
0.88
Volume Beton Plat Lantai = M3

2. Bekisting Lantai reservoir


Panjang = 8.40 m
Lebar = 0.20 m
Volume 1 = 1.68 M2
1.68
Volume Bekisting Lantai Reservoir = M2

b.Penulangan Plat Lantai


1. Penulangan Plat Lantai 1 ( Ø12 - 150 mm)
Panjang = 2.10 m
Lebar = 2.10 m
Berat Tulangan = 0.89 Kg/m

Penulangan Arah Memanjang - 150 mm


Jumlah Tulangan = 14.00 m
Panjang Tul. = 2.35 m
Panjang Total Tul. = 32.90 M
Berat Tulangan = 29.34 Kg

Penulangan Arah Melintang - 150 mm


Jumlah Tulangan = 14.00 m
Panjang Tul. = 2.35 m
Panjang Total Tul. = 32.90 M
Berat Tulangan = 29.34 Kg
Total Tulangan Plat Lantai

Berat Total Tul. = 117.34 Kg 117.34 Kg


Sketsa Perhitungan

6. Perhitungan Dinding
a. Perhitungan Dinding Utama
Panjang = 6.00 m
Tinggi = 1.70 m
Tebal Dindin= 0.15 m
Volume 1 = 1.53 m3
Pipa Hawa
Ø50mm Volume Total Dinding Utama
0.20 0.70 0.20 0.60 0.20 Bakisting = 20.40 m2
Total Bakisting Dinding Utama
0.15
Acian = 20.40 m2
0.12 0.12

Ø 1 2 - 150

Pengecatan = 7.92 m2

- Penulangan Beton Dinding ( Ø12 - 150 mm)


Arah Memanjang - 150
Jumlah Tula = 11.33 Btng
Ø 16 - 150 Wather Stop
Panjang Tul = 6.25 m
Tangga Pipa GIP Ø 25 mm Ø 1 6 - 150
Berat Tulang= 0.89 Kg/m
Berat Total T= 62.90 Kg
2.20

Arah Melintang - 150


1.50 Jumlah Tula = 40.00 Btng
Panjang Tul = 1.95 m
GIP Ø 20 mm Berat Tulang= 0.89 Kg/m
Kran
Ø 12 - 150
Kran Berat Total T= 69.26 Kg
Ø 12 - 150

0.25
Berat Total Tulangan Untuk Dinding Utam = 132.16 Kg

0.20 0.20 1.50 0.20 0.20


2.30

DETAIL PENULANGAN
SKALA 1 : 20
Sketsa Perhitungan

7. Perhitungan Plat atas


Panjang = 1.80 m Panjang = 0.60 m
Lebar = 1.80 m Lebar = 0.60 m
Tebal Plat = 0.12 m Tebal Dinding = 0.12 m
Volume 1 = 0.35 m3 Volume 2 = 0.04 m
Volume Total Plat Atas = 0.31 m3
Bakisting = 3.24
Volume Bakisting = 3.24 m2

- Penulangan Beton Plat ( Ø12 - 150 mm)


Arah Memanjang - 150
Jumlah Tula = 12.00 Btng
Panjang Tul = 2.05 m
Berat Tulang= 0.89 Kg/m
Berat Total T= 43.87 Kg

Arah Melintang - 150


Jumlah Tula = 12.00 Btng
Panjang Tul = 2.05 m
Berat Tulang= 0.89 Kg/m
Berat Total T= 43.87 Kg

Berat Total Tulangan Untuk Plat Atas = 87.74 Kg

a. Beton Plat Atas K-= 0.31 m3


b. Bakisting Plat = 3.24 m2
c. Tulangan Ø12 = 87.74 Kg
Sketsa Perhitungan

8. Pekerjaan Saluran Buangan


a. Galian Tanah
Panjang = 12.80 m
Lebar = 0.75 m
Tinggi = 0.53 m
= 5.09 M3
b. Pasangan Batako
Panjang = 12.80 m
Lebar = 0.50 m
Volume = 12.80 m2

c. Anstamping
Tinggi = 0.10 m
Lebar = 0.30 m
Volume = 0.38 M3

e. Lantai Beton K-125 = 0.19 M3

f. Plesteran
Lebar = 0.90 m
Panjang = 12.80 m
= 11.52 M2
g. Acian = 11.52 M2

9. Pekerjaan Kolam Resapan

a. Galian Tanah
Panjang = 0.80 m
Lebar = 0.80 m
Tinggi = 0.80 m
Volume = 0.51 M3

b. Anstamping
Tinggi = 0.30 m
Volume = 0.19 M3
Uraian Volume Reservoar

Jenis Pekerjaan Satuan Volume

1. Galian Tanah M3 3.05

2. Pekerjaan Anstamping M3 2.33

3. Urugan Pasir M3 -

4. Urugan Sirtu M3 -

4. Lantai Kerja Beton K-100 M3 0.17

5. Lantai Kerja Beton K-125 M3 0.69

5. Pekerjaan Plat Lantai

a. Beton Plat Lantai M3 0.88

b.Penulangan Plat Lantai Kg 117.34

c. Bekisting M2 1.68

6. Perhitungan Dinding

a. beton dinding & sekat M3 1.53

b. Penulangan dinding & sekat Kg 132.16

c. bekisting M2 20.40

d. acian M2 20.40

e. pengecatan M2 7.92

7. Perhitungan Plat atas

a. Beton Plat Atas K-225 M3 0.31

b. Bakisting Plat M2 3.24

c. Tulangan Ø12 Kg 87.74

8. Pemasangan Waterstop 200 mm M' 6.00

8. Pekerjaan Saluran Buangan

a. Galian Tanah M3 5.09

b. Pasangan Batako M2 12.80


c. Anstamping M3 0.38

e. Lantai Beton K-125 M3 0.19

f. Plesteran M2 11.52

g. Acian M2 11.52

9. Pekerjaan Kolam Resapan

a. Galian Tanah M3 0.51

b. Anstamping M3 0.19

10 . Aksesories
a Tee All Socket 50mm x 50mm x 25 mm Buah 1.00
b Pipa GIP Dia. 25 mm M' 6.00
c Pipa GIP Dia. 20 mm M' 12.00
d Pipa GIP Dia. 20 mm untuk keran M' 3.00
e Bend 90 - dia. 20 mm Buah 3.00
f Stop kran dia. 25 mm Buah 1.00
g Double neeple dia. 25 mm Buah 1.00
h Double neeple dia. 20 mm Buah 1.00
i Socket dia. 20 mm Buah 1.00
j Reducher 25 mm - 20 mm Buah 1.00
k Tap kran dia. 20 mm Buah 6.00
l Kran pelampung Buah 1.00
m Pipa udara Buah 1.00
n Tutupan bak Buah 1.00
BAK UMUM KAP. 4,5 M3

SKET GAMBAR

0.15

0.20

1.00

0.20 0.20 1.50 0.20 0.20 1.00

KRAN KRAN
Man Hole
0.20 0.20

0.20 0.20

Pipa Hawa HDPE Ø 63 mm

KRAN
A

1.50
1.50

KRAN
0.25 0.25

0.20 0.20

0.20 0.20

KRAN KRAN

0.80
1.00 1.00

0.20 0.20 1.00 0.80

0.15 0.15

KOLAM RESAPAN

B
Perhitungan

Pipa Hawa
Ø50mm

0 .20 0.70 0.20 0 .60 0.20

Plat Atas (T = 12 cm)


0.15

0 .12
Bend 90°
0.20
Muka Air

Kran Pelampung
Wather Stop
Ta ngga Pipa GIP Ø 25 mm

2.47
1 .80
2 .20
2.00

1 .50 Plat Dinding (T = 20 cm)

0.20 1 .00

Plat Lantai (T = 25 cm) Kran

Lantai beton K-125


0 .25
Sirtu (10 cm)
0.75 Pas. Batu Kosong

1 .00

0 .30
Bend 90° Pas. Batu Bataco 0.50

Pas. Pondasi 1 Pc : 4Ps

Pas. Batu Kosong 0 .20


Lantai beton K-125
Urugan Pasir 0 .10 Sirtu (5 cm)
Pas. Batu Kosong
0.10 0 .60 0.10 0 .10 0.60 0.10
0 .80 0 .90 0.80

0.85 0.15 0 .20 0.15


Lantai Kerja beton K-100 (5 cm)
Sirtu (10 cm)
U rugan Ta nah Dipadatkan

POTONGAN A - A
SKALA 1 : 30

1. Galian Tanah

a. Segmen 1 b. Segmen 2
Panjang = 6.00 m Panjang = 10.90 m
Tinggi Galian = 0.25 m Tinggi Galian = 0.20 m
Lebar Galian = 0.80 m Lebar Galian = 0.85 m
Volume Segmen 1 = 1.20 m3 Volume Segmen 1 = 1.85 m3
3.05
Total Volume Galian Tanah = M3
Perhitungan

2. Pekerjaan Anstamping

a. Segmen 1 b. Segmen 2 a. Pas. Batu Kali


Panjang = 6.00 m Panjang = 10.90 m Panjang = 8.40 m
Tinggi Anstamping = 0.10 m Tinggi Anstamping = 0.20 m Tinggi Anstamping = 0.70 m
Lebar = 0.80 m Lebar = 0.85 m Lebar = 0.40 m
Volume Segmen 1 = 0.48 m3 Volume Segmen 1 = 1.85 m3 Volume Segmen 1 = 2.35 m3
Total Anstamping = 2.33 M3

Total Pas batu Kali 1:4 = 2.35 0

3. Urugan Pasir

a. Segmen 1 - Urugan Sirtu b. Segmen 2 - Urugan Pasir c. Segmen 3 - Urugan Sirtu lantai luar
Panjang = m Panjang = m Panjang = m
Tinggi = m Tinggi = m Tinggi = m
Lebar = m Lebar = m Lebar = m
Volume Segmen 1 = - m3 Volume Segmen 1 = - m3 Volume Segmen 1 = - m3
-
Total Sirtu Padat = M3
-
Total Urugan Pasir = M3

4. Pekerjaan Beton

a. Segmen 1 - Beton K-125 b. Segmen 2- Lantai Kerja Beton K-100 c. Segmen 3- Lantai Beton K-125
Panjang = 10.90 m Panjang = 1.50 m Panjang = m
Tinggi = 0.08 m Tinggi = 0.08 m Tinggi = m
Lebar = 0.85 m Lebar = 1.50 m Lebar = m
Volume Segmen 1 = 0.69 m3 Volume Segmen 2 = 0.17 m3 Volume Segmen 1 = - m3
0.69
Beton K-125 = M3
0.17
Beton K-100 = M3
Perhitungan

5. Pekerjaan Plat Lantai


a. Beton Plat Lantai

1. Pekerjaan Beton Plat Lantai 1


Panjang = 2.10 m
Tebal Beton = 0.20 m
Lebar = 2.10 m
Volume 1 = 0.88 m3
0.88
Volume Beton Plat Lantai = M3

2. Bekisting Lantai reservoir


Panjang = 8.40 m
Lebar = 0.20 m
Volume 1 = 1.68 M2
1.68
Volume Bekisting Lantai Reservoir = M2

b.Penulangan Plat Lantai


1. Penulangan Plat Lantai 1 ( Ø12 - 150 mm)
Panjang = 2.10 m
Lebar = 2.10 m
Berat Tulangan = 0.89 Kg/m

Penulangan Arah Memanjang - 150 mm


Jumlah Tulangan = 14.00 m
Panjang Tul. = 2.35 m
Panjang Total Tul. = 32.90 M
Berat Tulangan = 29.34 Kg

Penulangan Arah Melintang - 150 mm


Jumlah Tulangan = 14.00 m
Panjang Tul. = 2.35 m
Panjang Total Tul. = 32.90 M
Berat Tulangan = 29.34 Kg
Total Tulangan Plat Lantai

Berat Total Tul. = 117.34 Kg 117.34 Kg


Sketsa Perhitungan

6. Perhitungan Dinding
a. Perhitungan Dinding Utama
Panjang = 6.00 m
Tinggi = 1.50 m
Tebal Dindin= 0.15 m
Volume 1 = 1.35 m3
Pipa Hawa
Ø50mm Volume Total Dinding Utama
0.20 0.70 0.20 0.60 0.20 Bakisting = 18.00 m2
Total Bakisting Dinding Utama
0.15
Acian = 18.00 m2
0.12 0.12

Ø 1 2 - 150

Pengecatan = 6.72 m2

- Penulangan Beton Dinding ( Ø12 - 150 mm)


Arah Memanjang - 150
Jumlah Tula = 10.00 Btng
Ø 16 - 150 Wather Stop
Panjang Tul = 6.25 m
Tangga Pipa GIP Ø 25 mm Ø 1 6 - 150
Berat Tulang= 0.89 Kg/m
Berat Total T= 55.50 Kg
2.20

Arah Melintang - 150


1.50 Jumlah Tula = 40.00 Btng
Panjang Tul = 1.75 m
GIP Ø 20 mm Berat Tulang= 0.89 Kg/m
Kran
Ø 12 - 150
Kran Berat Total T= 62.16 Kg
Ø 12 - 150

0.25
Berat Total Tulangan Untuk Dinding Utam = 117.66 Kg

0.20 0.20 1.50 0.20 0.20


2.30

DETAIL PENULANGAN
SKALA 1 : 20
Sketsa Perhitungan

7. Perhitungan Plat atas


Panjang = 1.80 m Panjang = 0.60 m
Lebar = 1.80 m Lebar = 0.60 m
Tebal Plat = 0.12 m Tebal Dinding = 0.12 m
Volume 1 = 0.35 m3 Volume 2 = 0.04 m
Volume Total Plat Atas = 0.31 m3
Bakisting = 3.24
Volume Bakisting = 3.24 m2

- Penulangan Beton Plat ( Ø12 - 150 mm)


Arah Memanjang - 150
Jumlah Tula = 12.00 Btng
Panjang Tul = 2.05 m
Berat Tulang= 0.89 Kg/m
Berat Total T= 43.87 Kg

Arah Melintang - 150


Jumlah Tula = 12.00 Btng
Panjang Tul = 2.05 m
Berat Tulang= 0.89 Kg/m
Berat Total T= 43.87 Kg

Berat Total Tulangan Untuk Plat Atas = 87.74 Kg

a. Beton Plat Atas K-= 0.31 m3


b. Bakisting Plat = 3.24 m2
c. Tulangan Ø12 = 87.74 Kg
Sketsa Perhitungan

8. Pekerjaan Saluran Buangan


a. Galian Tanah
Panjang = 12.80 m
Lebar = 0.75 m
Tinggi = 0.53 m
= 5.09 M3
b. Pasangan Batako
Panjang = 12.80 m
Lebar = 0.50 m
Volume = 12.80 m2

c. Anstamping
Tinggi = 0.10 m
Lebar = 0.30 m
Volume = 0.38 M3

e. Lantai Beton K-125 = 0.19 M3

f. Plesteran
Lebar = 0.90 m
Panjang = 12.80 m
= 11.52 M2
g. Acian = 11.52 M2

9. Pekerjaan Kolam Resapan

a. Galian Tanah
Panjang = 0.80 m
Lebar = 0.80 m
Tinggi = 0.80 m
Volume = 0.51 M3

b. Anstamping
Tinggi = 0.30 m
Volume = 0.19 M3
Uraian Volume Reservoar

Jenis Pekerjaan Satuan Volume

1. Galian Tanah M3 3.05

2. Pekerjaan Anstamping M3 2.33

3. Urugan Pasir M3 -

4. Urugan Sirtu M3 -

4. Lantai Kerja Beton K-100 M3 0.17

5. Lantai Kerja Beton K-125 M3 0.69

5. Pekerjaan Plat Lantai

a. Beton Plat Lantai M3 0.88

b.Penulangan Plat Lantai Kg 117.34

c. Bekisting M2 1.68

6. Perhitungan Dinding

a. beton dinding & sekat M3 1.35

b. Penulangan dinding & sekat Kg 117.66

c. bekisting M2 18.00

d. acian M2 18.00

e. pengecatan M2 6.72

7. Perhitungan Plat atas

a. Beton Plat Atas K-225 M3 0.31

b. Bakisting Plat M2 3.24

c. Tulangan Ø12 Kg 87.74

8. Pemasangan Waterstop 200 mm M' 6.00

8. Pekerjaan Saluran Buangan

a. Galian Tanah M3 5.09

b. Pasangan Batako M2 12.80


c. Anstamping M3 0.38

e. Lantai Beton K-125 M3 0.19

f. Plesteran M2 11.52

g. Acian M2 11.52

9. Pekerjaan Kolam Resapan

a. Galian Tanah M3 0.51

b. Anstamping M3 0.19

10 . Aksesories
a Tee All Socket 50mm x 50mm x 25 mm Buah 1.00
b Pipa GIP Dia. 25 mm M' 6.00
c Pipa GIP Dia. 20 mm M' 12.00
d Pipa GIP Dia. 20 mm untuk keran M' 3.00
e Bend 90 - dia. 20 mm Buah 3.00
f Stop kran dia. 25 mm Buah 1.00
g Double neeple dia. 25 mm Buah 1.00
h Double neeple dia. 20 mm Buah 1.00
i Socket dia. 20 mm Buah 1.00
j Reducher 25 mm - 20 mm Buah 1.00
k Tap kran dia. 20 mm Buah 6.00
l Kran pelampung Buah 1.00
m Pipa udara Buah 1.00
n Tutupan bak Buah 1.00
BACK UP VOLUME RESERVOIR KAP. 50 M3

SKET GAMBAR

5.00

Man Hole
0.20

0.25
Man Hole

1.15
Pipa Penguras
5
0.80

0.20
Pi pa Wash Out
0.20 V Nocth GIP. Ø 50 mm
Pipa Inlet GIP Ø 50 mm
0.20
Pipa Outlet

Inlet Dari MA. Pansui GIP. Ø 75 mm

DOP

1.60
Inlet Dari MA. Buti Pipa Outlet
GIP. Ø 50 mm

DOP
Inlet Dari MA. Buti

2.80

5.00
Pipa Outlet
2.00 GIP. Ø 50 mm
Pipa Hawa GIP Ø 50 mm Pipa Hawa GIP Ø 50 mm

Pintu Besi GIP Ø 75 mm

1.20
0.20 Pi ntu Besi
Pipa Wash Out
0.20 GIP. Ø 75 mm

0.20

1.20
0.20 0.20
1.40
1.15
0.20
By Pass Ke Bak Umum Ex 3
0.25

0.20

D
0.25 2.40 2.40 0.25
0.20 0.20 0.20
5.50
5.90

DENAH RESERVOAR 50M3 (CP.1)


Skala 1:50
Perhitungan

1.80 1.80

0.40 0.20 1.20 0.25 0.60 0.20 1.60 0.20 2.40 0.25 1.20 0.20 0.40

Man Hole Pipa Hawa


Ø75mm

0.15
0.30
0.15 0.15
55.00
0.30
4 6 0.55
Wather Stop
Wather Stop 0.60 6 4
Pintu Besi 1 Pintu Besi
0.40 1
V Nocth
7 0.45
1.90 0.40 7 1.90
Pipa inlet 0.80
GIP. Ø 50 mm
Wather Stop Pipa
0.40 Over Fllow

Pipa Inlet
GIP. Ø 50 mm 8 2 3 2.00
4 0.40
0.80 1.60
0.20 0.50 0.50 0.20
0.40
0.25 3
0.05 0.40
5 8
Pipa Outlet
GIP. Ø 75 mm 1.00
0.10 0.25 0.30 3 0.80
0.30
0.30 0.30 2
0.05
0.10 Pipa Wash Out 0.30
GIP. Ø 75 mm
0.30 0.05
0.10
0.30
Beton Bertulang
Lantai Kerja beton 1:3:5 (5 cm)
Sirtu (10 cm)
Pasangan Batu Kosong (30 cm)

0.20
7.30

1. Galian Tanah

a. Segmen 1 b. Segmen 2 c. Segmen 2


Panjang = 1.60 m Panjang = 5.90 m Panjang = 3.60 m
Tinggi Galian = 0.70 m Tinggi Galian = 1.55 m Tinggi Galian = 1.55 m
Lebar Galian = 2.80 m Lebar Galian = 5.90 m Lebar Galian = 1.40 m
Volume Segmen 1 = 3.14 m3 Volume Segmen 1 = 53.96 m3 Volume Segmen 1 = 7.81 m3
Total Volume Galian Tanah = 64.90 M3
Perhitungan

2. Pekerjaan Anstamping

a. Segmen 1 b. Segmen 2 c. Segmen 3


Panjang = 1.60 m Panjang = 5.90 m Panjang = 3.60 m
Tinggi Anstamping = 0.30 m Tinggi Anstamping = 0.30 m Tinggi Anstamping = 0.30 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 1.40 m
Volume Segmen 1 = 1.34 m3 Volume Segmen 1 = 10.44 m3 Volume Segmen 1 = 1.51 m3
Total Anstamping = 13.30 M3

3. Urugan Sirtu Padat

a. Segmen 1 b. Segmen 2 b. Segmen 2


Panjang = 1.60 m Panjang = 5.90 m Panjang = 3.60 m
Tebal Urugan Sirtu = 0.10 m Tebal Urugan Sirtu = 0.10 m Tebal Urugan Sirtu = 0.10 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 1.40 m
Volume Segmen 1 = 0.45 m3 Volume Segmen 1 = 3.48 m3 Volume Segmen 1 = 0.50 m3
Total Urugan Sirtu = 4.43 M3

4. Lantai Kerja Beton Cam. 1:3:5 tebal 5 cm

a. Segmen 1 b. Segmen 2 c. Segmen 3


Panjang = 1.60 m Panjang = 5.90 m Panjang = 3.60 m
Tebal lantai kerja = 0.05 m Tebal lantai kerja = 0.05 m Tebal lantai kerja = 0.05 m
Lebar = 2.80 m Lebar = 5.90 m Lebar = 1.40 m
Volume Segmen 1 = 0.22 m3 Volume Segmen 2 = 1.74 m3 Volume Segmen 2 = 0.25 m3
Total Vol. lantai kerja = 2.22 M3
Perhitungan

5. Pekerjaan Plat Lantai


a. Beton Plat Lantai

1. Pekerjaan Beton Plat Lantai 1 2. Pekerjaan Beton Plat Lantai 2 2. Pekerjaan Beton Plat Lantai 2
Panjang = 1.60 m Panjang = 5.90 m Panjang : 3.60
Tebal Beton = 0.25 m Tebal Beton = 0.30 m Tebal Beton : 0.30
Lebar = 2.80 m Lebar = 5.90 m Lebar : 1.40
Volume 1 = 1.12 m3 Volume 2 = 10.44 m3 Volume 2 : 1.51
Volume Beton Plat Lantai = 13.08 M3

2. Bekisting Lantai reservoir


Panjang = 31.30 m
Lebar = 0.25 m
Volume 1 = 7.83 m2
Volume Bekisting Lantai Reservoir = 7.83 M2

b.Penulangan Plat Lantai


1. Penulangan Plat Lantai 1 ( Ø12 - 150 mm) 2. Penulangan Plat Lantai 2 ( Ø12- 150 mm) 2. Penulangan Plat Lantai 2 ( Ø12 - 150 mm)
Panjang = 1.70 m Panjang ###
= 5.90 m Panjang = 3.60 m
Lebar = 1.35 m Lebar ###
= 5.90 m Lebar = 1.40 m
Berat Tulangan = 0.89 Kg/m Berat Tulangan ###
= 0.89 Kg/m Berat Tulangan = 0.89 Kg/m

Penulangan Arah Memanjang - 150 mm Penulangan Arah Memanjang - 150 mm Penulangan Arah Memanjang - 150 mm
Jumlah Tulangan = 11.33 m Jumlah Tulangan ###= 39.33 m Jumlah Tulangan = 9.33 m
Panjang Tul. = 1.60 m Panjang Tul. ###
= 6.20 m Panjang Tul. = 3.90 m
Panjang Total Tul. = 18.13 M Panjang Total Tul.###
= 243.87 M Panjang Total Tul.= 36.40 M
Berat Tulangan = 16.10 Kg Berat Tulangan ### = 216.55 Kg Berat Tulangan = 32.32 Kg

Penulangan Arah Melintang - 150 mm Penulangan Arah Melintang - 150 mm Penulangan Arah Melintang - 150 mm
Jumlah Tulangan = 9.00 m Jumlah Tulangan ###= 39.33 m Jumlah Tulangan = 24.00 m
Panjang Tul. = 1.95 m Panjang Tul. ###
= 6.20 m Panjang Tul. = 1.70 m
Panjang Total Tul. = 17.55 M Panjang Total Tul.###
= 243.87 M Panjang Total Tul.= 40.80 M
Berat Tulangan = 15.58 Kg Berat Tulangan ### = 216.55 Kg Berat Tulangan = 36.23 Kg
Total Tulangan Plat Lantai

Berat Total Tul. = 63.37 Kg Berat Total Tul. ###


= 866.21 Kg Berat Total Tul. = 137.11 Kg 1,066.70 Kg
Sketsa Perhitungan

1.80 1.80 6. Perhitungan Dinding


0.40 0.20 1.20 0.25 0.60 0.20 1.60 0.20 2.40 0.25 1.20 0.20 0.40
a. Perhitungan Dinding Utama
Panjang = 4.40 m Panjang = 30.00 m
0.15
0.15
0.30
0.15 Tinggi = 2.10 m Tinggi = 2.75 m
0.30
0.60 0.55 Tebal Dinding = 0.20 m Tebal Dinding = 0.20 m
0.40
Volume 1 = 1.85 m3 Volume 1 = 15.84 m3
V Nocth

1.90
0.40
0.45
1.90
Volume Total Dinding Utama = 17.69 m3
0.80

0.40
Bakisting = 18.48 m2 Bakisting = 165.00 m2
2.00 Total Bakisting Dinding Utama = 183.48 m2
0.40

0.20
0.80 1.60

0.20
Acian = 18.48 m2 Acian = 162.72 m2
0.50 0.50
0.25
0.40
Total Acian = 181.20 m2
0.05 0.40
0.10
0.30
0.25 0.30 0.80
Pengecatan = 89.46 m2
0.30 0.30
0.05
0.10
0.30
0.30 0.05
0.10
- Penulangan Beton Dinding ( Ø12 - 150 mm) - Penulangan Beton Dinding ( Ø12 - 150 mm)
0.30 Arah Memanjang - 150 Arah Memanjang - 150
0.20
7.30 Jumlah Tulangan = 14.00 Btng Jumlah Tulangan = 18.33 Btng
Panjang Tulangan = 4.65 m Panjang Tulangan = 30.25 m
Berat Tulangan Ø1 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. 57.81 Kg Berat Total Tul. = 492.47 Kg
5.00

0.20 Arah Melintang - 150 Arah Melintang - 150


0.25
Jumlah Tulangan = 29.33 Btng Jumlah Tulangan = 200.00 Btng
1.15
Panjang Tulangan = 2.35 m Panjang Tulangan = 3.00 m
0.80

Berat Tulangan Ø1 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m


0.20
0.20 Berat Total Tul. 61.21 Kg Berat Total Tul. = 532.80 Kg
0.20

Berat Total Tulangan Untuk Dinding Utama = 1,144.29 Kg


0.25

1 .60
2 .80
5 .00
2.00
b. Perhitungan Skat Dinding
Panjang = 5.00 m
1.20

Tinggi = 2.75 m
1 .20
0.20
0.20 Tebal Dinding = 0.20 m
Volume 1 = 2.75 m3
0.20

1.20
0.20 0.20
1.40
Untuk Skat Dinding
1.15
0.20
Bakisting Skat 82.50 m2
0.25

0.20
Acian 27.50 m2
- Penulangan Beton Dinding ( Ø19 - 150 mm)
0.25
Arah Memanjang - 150
2.40 2.40 0.25
0.20 0.20 0.20
5.50
5.90
Jumlah Tulangan = 18.33 Btng
Panjang Tulangan = 5.25 m
Berat Tulangan Ø1 = 0.89 Kg/m
Berat Total Tul. 85.47 Kg

Arah Melintang - 150


Jumlah Tulangan = 33.33 Btng
Panjang Tulangan = 3.00 m
Berat Tulangan Ø1 = 0.89 Kg/m
Berat Total Tul. 88.80 Kg
Volume Total tulangan Skat = 174.27 Kg
Sketsa Perhitungan

7. Perhitungan Plat atas


Panjang = 3.00 m Panjang = 6.10 m
1.80 1.80 Lebar = 1.80 m Lebar = 6.10 m
0.40 0.20 1.20 0.25 0.60 0.20 1.60 0.20 2.40 0.25 1.20 0.20 0.40
Tebal Plat = 0.15 m Tebal Dinding = 0.15 m
Volume 1 = 0.77 m3 Volume 2 = 5.51 m
0.15
0.30
0.15 0.15

Panjang = 3.80 m
0.30
0.60 0.55

0.40
V Nocth
Lebar = 1.60 m
0.45
1.90
0.40
0.80 1.90 Tebal Dinding = 0.15 m
0.40 Volume 3 = 0.84 m
2.00
0.40

= 7.12 m3
0.80 1.60

0.20 0.50 0.50 0.20 Volume Total Plat Atas


0.40
Bakisting 2
5.00
0.25
0.05 0.40
Bakisting 1 5.40 = 37.21 m2
0.10 0.30 0.20

0.30
0.25 0.80
0.25
Bakisting 3 = 6.08 m2
0.30 0.30
0.05
0.10
0.30 1.15
Volume Bakisting = 48.69 m2
0.30 0.05
0.80 0.10

0.30
0.20 - Penulangan Beton Plat ( Ø12 - 150 mm) - Penulangan Beton Plat ( Ø12 - 150 mm)
0.20
0.20
0.20
7.30 Arah Memanjang - 150 Arah Memanjang - 150
0.25
Jumlah Tulangan = 12.00 Btng Jumlah Tulangan = 40.67 Btng

1 .60
Panjang Tulangan = 3.25 m Panjang Tulangan = 6.35 m
Berat Tulangan Ø1 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m

2 .80
5 .00
2.00

1.20
Berat Total Tul. 34.63 Kg Berat Total Tul. = 229.31 Kg

1 .20
0.20
Arah Melintang - 150 Arah Melintang - 150
0.20
0.20
Jumlah Tulangan = 20.00 Btng Jumlah Tulangan = 40.67 Btng
1.20
Panjang Tulangan = 2.05 m Panjang Tulangan = 6.35 m
Berat Tulangan Ø1 = 0.89 Kg/m Berat Tulangan Ø12 = 0.89 Kg/m
0.20 0.20
1.40
1.15
0.20

0.25
Berat Total Tul. 36.41 Kg Berat Total Tul. = 229.31 Kg
0.20

0.25 2.40 2.40 0.25


- Penulangan Beton Plat ( Ø12 - 150 mm)
0.20
5.50
0.20 0.20
Arah Memanjang - 150
5.90
Jumlah Tulangan = 10.67 Btng
Panjang Tulangan = 0.25 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 2.37 Kg

Arah Melintang - 150


Jumlah Tulangan = 25.33 Btng
Panjang Tulangan = 0.25 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Total Tul. = 5.62 Kg

Berat Total Tulangan Untuk Plat Atas = 529.66 Kg

a. Beton Plat Atas K- = 7.12 m3


b. Bakisting Plat = 48.69 m2
c. Tulangan Ø12 = 529.66 Kg
Uraian Volume Reservoar

Jenis Pekerjaan Satuan Volume

1. Galian Tanah M3 64.90

2. Pekerjaan Anstamping M3 13.30

4. Lantai Kerja Beton Cam. 1:3:5 tebal 5 cm M3 2.22

5. Pekerjaan Plat Lantai

a. Beton Plat Lantai M3 13.08

b.Penulangan Plat Lantai Kg 1,066.70

c. Bekisting M2 7.83

6. Perhitungan Dinding

a. beton dinding & sekat M3 20.44

b. Penulangan dinding & sekat M2 1,318.56

c. bekisting Kg 265.98

d. acian M2 208.70

e. pengecatan M2 89.46

7. Perhitungan Plat atas

a. Beton Plat Atas K-225 M3 7.12

b. Bakisting Plat M2 48.69

c. Tulangan Ø12 Kg 529.66


BACK UP VOLUME RUMAH GENSET

Sketsa Perhitungan

1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat
Tinggi Galian = 1.05 m
Lebar Galian = 1.00 m
Panjang Galian = 1.00 m
Jumlah = 9.00 Bh
Volume = 9.45 m3

b. Urugan Tanah Kembali


Tinggi Urugan = 0.85 m Urugan Pondasi Foot Plat
Panjang = 1.00 m
Lebar = 0.35 m
Volume urugan = 2.68 m3

Tinggi Urugan = 0.15 m Urugan Tanah Timbunan Lantai


Panjang = 6.00 m
Lebar = 5.00 m
Volume Urugan = 4.50 m3

2. Pekerjaan Struktur
a. Foot Plat
- Beton
Lebar Atas = 0.30 m
Lebar Bawah = 0.20 m
Tinggi = 0.35 m
Panjang = 1.00 m
Volume = 0.18 m3

Lebar = 0.30
Tinggi = 0.30
Volume = 0.09 m3

Lebar = 0.30 m
Tinggi = 0.70 m
Volume = 0.06 m3

Total Volume Beton = 2.95 m3


- Penulangan Ø12 - 150 mm
Panjang Tul. = 2.50 m
Jumlah = 7.67 Btng
Panjang Total = 19.17 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Arah x = 17.06 Kg

Panjang Tul. = 1.30 m


Jumlah = 12.00 Btng
Panjang Total = 15.60 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Arah y = 13.88 Kg

Total Berat Tul. 1 = 278.48 Kg


Sketsa Perhitungan

- Penulangan 2 (8- Ø12, Ø8-150)


Panjang Tul. = 1.65 m
Jumlah = 8.00 Btng
Panjang Total = 13.20 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 11.75 Kg

Panjang Tul. = 1.10 m


Jumlah = 8.33 Btng
Panjang 1 Seng. = 1.30 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 4.28 Kg

Total Berat Tul. 2 = 144.24 Kg

Berat Total Tul. = 422.73 Kg

- Bakisting = 7.56 m2

b. Sloof 30 x 40 cm
Panjang = 27.00 m
Lebar = 0.30 m
Tinggi = 0.40 m
Volume Beton = 3.24 m3

Bakisting = 21.60 m2

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 27.00 m
Jumlah = 10.00 Btng
Panjang Total = 270.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 240.30 Kg

Panjang Tul. = 27.00 m


Jumlah = 181.00 Btng
Panjang 1 Seng. = 1.50 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 107.24 Kg

Berat Total = 347.54 Kg

c. Kolom 15 x 15 cm
Tinggi = 3.50 m
Lebar = 0.15 m
Panjang = 0.15 m
Jumlah Kolom = 9.00 bh
Volume Beton = 0.71 m3

Bakisting = 18.90 m2
Sketsa Perhitungan

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 3.50 m
Jumlah = 4.00 Btng
Panjang Total = 14.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 12.46 Kg

Panjang Tul. = 3.50 m


Jumlah = 24.33 Btng
Panjang 1 Seng. = 0.95 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 9.13 Kg

Berat Total = 194.32 Kg

d. Ring Balk 15 x 20 cm
Panjang = 27.00 m
Lebar = 0.20 m
Tinggi = 0.15 m
Volume Beton = 0.81 m3

Bakisting = 10.80 m2

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 27.00 m
Jumlah = 4.00 Btng
Panjang Total = 108.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 96.12 Kg

Panjang Tul. = 27.00 m


Jumlah = 181.00 Btng
Panjang 1 Seng. = 0.70 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 50.05 Kg

Total Tulangan = 146.17 Kg

e. Plat Lantai T = 0.2 m


Panjang = 6.00 m
Lebar = 5.00 m
Tebal = 0.20 m
Volume Beton = 6.00 m3

- Penulangan Ø12 -150 mm


Panjang = 6.00 m
Lebar = 5.00 m
Panjang Tul. Atas 1 = 1.30 m
Panjang Tul. Atas 2 = 0.90 m
Berat Tulangan Ø12 = 0.89 Kg/m
Sketsa Perhitungan

- Tulangan Atas Arah Memanjang


Panjang = 4.88 m
Jumlah Tulangan = 34.33 Btng

- Tulangan Bawah Arah Memanjang


Panjang = 6.00 m
Total Panjang Tul. = 373.55 m
Berat Tulangan = 332.46 Kg

- Tulangan Atas Arah Melintang


Panjang = 2.66 m
Jumlah Tulangan = 41.00 Btng

- Tulangan Bawah Arah Memanjang


Panjang = 5.00 m
Total Panjang Tul. = 314.06 m
Berat Tulangan = 279.51 Kg

Total Berat Tulangan = 611.97 Kg

3. Pekerjaan Dinding
Panjang = 27.00 m
Tinggi Dinding = 3.50 m
Luas Dinding = 94.50 m2

Pengurangan Dinding
Pintu 1
Tinggi = 2.30 m
Lebar = 1.70 m

Pintu 2
Tinggi = 2.30 m
Lebar = 0.90 m

Pintu 1
Tinggi = 1.55 m
Lebar = 1.15 m

Rooster 1
Tinggi = 1.20 m
Lebar = 0.80 m

Rooster 2
Tinggi = 0.60 m
Lebar = 1.60 m

Luasan = 14.48 m2

Luas Tembok = 80.02 m2

Plesteran = 160.04 m2
Acian = 160.04 m2
Pengecetan = 160.04 m2
Sketsa Perhitungan

4. Pekerjaan Atap
Kayu 6/12 Kuda-Kuda 1
Panjang Kayu = 19.25 m
Volume Kayu = 0.14 m3

Kayu 6/12 Kuda-Kuda 2


Panjang Kayu = 2.77 m
Volume Kayu = 0.12 m3

Total Kayu Atap = 0.26 M3

Kayu Gording 5/10 Kuda-Kuda 1


Panjang Gording = 7.45 m
Jumlah Gording = 6.00 Btng
Volume Kayu = 0.45 m3

Beugel u = 2.00 Bh
Plat Strip = 4.00 bh
Bout 15 cm = 5.00 bh
Bout 30 cm = 4.00 bh

- Penutup Atap Seng


Panjang = 7.45 m
Lebar 1 = 4.00 m
Lebar 2 = 1.84 m
Luas = 73.31 m2
Seng Bubungan = 7.45 m

5. Pekerjaan List Plank 3 x 20

Panjang = 41.35 m

6. Pekerjaan Plafon
Panjang = 7.45 m
Lebar = 6.45 m
Luas Plafon = 48.05 m2
Pengecetan Plafon = 48.05 m2
List Plafond = 69.00 m'

7. Pekerjaan Teras

Panjang = 5.00 m Lebar Rabat Lantai K-125 = 1.35 m


Lebar = 1.50 m Labar Rabat Lantai K-125 = 0.25 m
Tebal Urugan = 0.05 m Lebar Lantai Rabat K-175 = 2.10 m
Tebal Anstamping = 0.15 m Tebal Rabat K-125 = 0.10 m
Lebar Anstamping = 0.50 m Tebal Rabat K-175 = 0.05 m
Lebar Pondasi = 0.30 m Tinggi Sloof = 0.20 m
Tinggi Pondasi = 0.30 m Lebar Sloof = 0.15 m
Tinggi Galian = 0.45 m

- Volume Galian Tanah = 2.93 m3 - Volume Rabat Lantai K-125 = 0.80 m3


- Volume Urugan Pasir = 0.33 m3 - Volume Rabat K-175 = 0.53 m3
- Volume Anstamping = 0.98 m3 - Volume Sloof = 0.39 m3
- Urugan Tanah = 0.78 m3
- Pasangan Batu = 1.17 m3
Sketsa Perhitungan

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 13.00 m
Jumlah = 4.00 Btng
Panjang Total = 52.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 46.28 Kg

Panjang Tul. = 13.00 m


Jumlah = 87.67 Btng
Panjang 1 Seng. = 0.70 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 24.24 Kg

Total Tulangan = 70.52 Kg

8. Pekerjaan Pintu dan Jendela


Pintu 1
Tinggi = 2.30 m
Lebar = 1.70 m
Luas = 3.91 m2
Volume Kayu = 0.03 m3

Pintu 2
Tinggi = 2.30 m
Lebar = 0.90 m
Luas = 2.07 m2
Volume Kayu = 0.03 m3

Jendela 1
Tinggi = 1.55 m
Lebar = 1.15 m
Luasan = 1.78 m2
Volume Kayu = 0.03 m3

Total Volume Jendela dan Pintu


= 0.09 m3

9. Beton Dudukan Genset

Panjang = 2.00 m
Lebar = 1.50 m
Tebal = 0.20 m
Volume = 0.60 m3
Uraian Volume Rumah Genset

Jenis Pekerjaan Satuan Volume

1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat M3 9.45
b. Urugan Tanah Kembali m3 7.18
2. Pekerjaan Struktur
a. Foot Plat
- Beton m3 2.95
- Penulangan Ø12 - 150 mm Kg 422.73
- Bakisting M2 7.56
b. Sloof 30 x 40 cm
- Beton m3 3.24
- Bakisting M2 21.60
- Penulangan Polos Kg 347.54
c. Kolom 15 x 15 cm
- Beton m3 0.71
- Bakisting M2 18.90
- Penulangan Polos Kg 194.32
d. Ring Balk 15 x 20 cm
- Beton m3 0.81
- Bakisting M2 10.80
- Penulangan Polos Kg 146.17
e. Plat Lantai T = 0.2 m
- Beton m3 6.00
- Bakisting M2
- Penulangan Polos Kg 611.97
3. Pekerjaan Dinding
- Dinding Batako M2 80.02
- Dinding Rooster M2 1.92
- Plesteran M2 160.04
- Acian M2 160.04
- Pengecatan M2 160.04
4. Pekerjaan Atap
- Kuda-Kuda Kayu 6/12 cm M3 0.26
- Gording Kayu 5/12 cm M3 0.45
Beugel u Bh 2.00
Plat Strip Bh 4.00
Bout 15 cm Bh 5.00
Bout 30 cm Bh 4.00
- Seng Gelombang BJLS. 0.30 M2 73.31
5. Pekerjaan List Plank 3 x 20 M2 41.35
6. Pekerjaan Plafon M2 48.05
7. Pekerjaan Teras
- Volume Galian Tanah M3 2.93
- Volume Urugan Pasir M3 0.33
- Volume Anstamping M3 0.98
- Urugan Tanah M3 0.78
- Pasangan Batu M3 1.17
- Volume Rabat Lantai K-125 M3 0.80
- Volume Rabat K-175 M3 0.53
- Volume Sloof M3 0.39
- Penulangan Sloof 15 x 20 Kg 70.52
8. Pekerjaan Pintu dan Jendela
- Kayu Jendela dan Pintu M3 0.09
- Daun Jendela M2 1.78
- Daun Pintu M2 5.98
- Engsel Pintu Bh 12.00
- Engsel Jendela Bh 4.00
- Kait Angin Bh 2.00
- Kunci Tanam Bh 2.00
9. Beton Dudukan Genset M3 0.60
BACK UP VOLUME RUMAH POMPA

Sketsa Perhitungan
6.00

3.00 3.00 1. Galian Tanah


a. Galian Tanah Untuk Pondasi Foot Plat
Tinggi Galian = 1.05 m
Lebar Galian = 1.00 m
Panjang Galian = 1.00 m
Jumlah = 4.00 Bh
Rabat Beton Untuk Pompa Volume = 4.20 m3

b. Urugan Tanah Kembali


Tinggi Urugan = 0.85 m Urugan Pondasi Foot Plat
Panjang = 1.00 m
4.00
Lebar = 0.35 m
Volume urugan = 1.19 m3
Tinggi Urugan = 0.15 m Urugan Tanah Timbunan Lantai
Rabat Beton Untuk Pompa Panjang = 6.00 m
Lebar = 5.00 m
Volume Urugan = 4.50 m3

c. Urugan Pasir Di Bawah Pondasi


Tinggi Urugan = 0.05 m Urugan Pasir Di Bawah Pondasi Teras
Panjang = 8.00 m
Lebar = 0.50 m
Volume urugan = 0.20 m3

2. Pekerjaan Struktur
D E NAH a. Foot Plat
Skala 1:50 - Beton
Lebar Atas = 0.30 m
Lebar Bawah = 0.20 m
Bubungan +5.00 Tinggi = 0.35 m
Panjang = 1.00 m
Volume = 0.18 m3

Lebar = 0.30
Ring Balk + 3.5
Tinggi = 0.30
Volume = 0.09 m3

Lebar = 0.30 m
Tinggi = 0.70 m
Volume = 0.06 m3
Total Volume Beton = 1.31 m3

- Penulangan Ø12 - 150 mm


Panjang Tul. = 2.50 m
Jumlah = 7.67 Btng
Panjang Total = 19.17 m
Sloof ± 0.00
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Arah x = 17.06 Kg
Muka Tanah - 0.40 0.15

1.40
Panjang Tul. = 1.30 m
Jumlah = 12.00 Btng
Foot Plate Panjang Total = 15.60 m
Berat Tulangan Ø12 = 0.89 Kg/m
5.70

POT. C
S kala 1:50
1.40

Foot Plate

5.70
Berat Arah y = 13.88 Kg
Total Berat Tul. 1 = 123.77 Kg
POT. C
S kala 1:50
Sketsa Perhitungan

- Penulangan 2 (8- Ø12, Ø8-150)


Panjang Tul. = 1.65 m
Jumlah = 8.00 Btng
Panjang Total = 13.20 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 11.75 Kg

Panjang Tul. = 1.10 m


Jumlah = 8.33 Btng
Panjang 1 Seng. = 1.30 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 4.28 Kg

Total Berat Tul. 2 = 64.11 Kg

Berat Total Tul. = 187.88 Kg

- Bakisting = 7.56 m2

b. Sloof 30 x 40 cm
Panjang = 27.00 m
Lebar = 0.30 m
Tinggi = 0.40 m
Volume Beton = 3.24 m3

Bakisting = 21.60 m2

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 27.00 m
Jumlah = 10.00 Btng
Panjang Total = 270.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 240.30 Kg

Panjang Tul. = 27.00 m


Jumlah = 181.00 Btng
Panjang 1 Seng. = 1.50 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 107.24 Kg

Berat Total = 347.54 Kg

c. Kolom 15 x 15 cm
Tinggi = 3.50 m
Lebar = 0.15 m
Panjang = 0.15 m
Jumlah Kolom = 9.00 bh
Volume Beton = 0.71 m3

Bakisting = 18.90 m2
Sketsa Perhitungan

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 3.50 m
Jumlah = 4.00 Btng
Panjang Total = 14.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 12.46 Kg

Panjang Tul. = 3.50 m


Jumlah = 24.33 Btng
Panjang 1 Seng. = 0.95 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 9.13 Kg

Berat Total = 194.32 Kg

d. Ring Balk 15 x 20 cm
Panjang = 20.00 m
Lebar = 0.20 m
Tinggi = 0.15 m
Volume Beton = 0.60 m3

Bakisting = 8.00 m2

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 20.00 m
Jumlah = 4.00 Btng
Panjang Total = 80.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 71.20 Kg

Panjang Tul. = 20.00 m


Jumlah = 134.33 Btng
Panjang 1 Seng. = 0.70 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 37.14 Kg

Total Tulangan = 108.34 Kg

e. Plat Lantai T = 0.2 m


Panjang = 6.00 m
Lebar = 5.00 m
Tebal = 0.20 m
Volume Beton = 6.00 m3

- Penulangan Ø12 -150 mm


Panjang = 6.00 m
Lebar = 5.00 m
Panjang Tul. Atas 1 = 1.30 m
Panjang Tul. Atas 2 = 0.90 m
Berat Tulangan Ø12 = 0.89 Kg/m
Rooster

Sketsa Perhitungan
Rooster

- Tulangan Atas Arah Memanjang


Panjang = 4.88 m
Rabat Beton Untuk Pompa Sloof 30/40 Jumlah Tulangan = 34.33 Btng

0.15 - Tulangan Bawah Arah Memanjang


0.40 0.20
Panjang = 6.00 m
Total Panjang Tul. = 373.55 m
0.70
Berat Tulangan = 332.46 Kg

0.10 - Tulangan Atas Arah Melintang


Foot Plate
0.20
Panjang = 2.66 m
4.00 1.00
Jumlah Tulangan = 41.00 Btng

- Tulangan Bawah Arah Memanjang


Panjang = 5.00 m
Plat Lantai (T = 20 cm) Sloof Lantai 30/40 Total Panjang Tul. = 314.06 m
Ø 12 - 150 Ø 12 - 150 Ø 12 - 150
Berat Tulangan = 279.51 Kg
0.20 Ø 8 - 150
10 - Ø 12
0.40
Total Berat Tulangan = 611.97 Kg
Foot Plate
0.30
3. Pekerjaan Dinding
0.75
Panjang = 20.00 m
Tinggi Dinding = 3.30 m
0.10
Luas Dinding = 66.00 m2
Foot Plate
0.20

1.00 3.00 1.00


Pengurangan Dinding
3.70
Pintu 1
Tinggi = 2.05 m
DETAIL PLAT LANTAI
Skala 1:20
Lebar = 1.70 m

Rooster 1
Tinggi = 1.20 m
Lebar = 0.80 m

Rooster 2
Tinggi = 2.60 m
Lebar = 1.20 m

Luasan = 23.17 m2

Luas Tembok = 42.84 m2

Plesteran = 85.67 m2
Acian = 85.67 m2
Pengecetan = 85.67 m2
Sketsa Perhitungan

4. Pekerjaan Atap
Seng Bubungan 20 Kayu 6/12 Kuda-Kuda 1
Seng BJLS 30
Kaki Kuda-kuda 6x12 Panjang Kayu = 27.00 m
Tiang Kuda Volume Kayu = 0.19 m3
Gording 5x10
Total Kayu Atap = 0.19 M3
Balok Jepit 3x12x2

Balok Penyokong 6x12


Balok Tarik 6x12 Kayu Gording 5/10 Kuda-Kuda 1
Panjang Gording = 7.45 m
Jumlah Gording = 12.00 Btng
Klos
Volume Kayu = 0.89 m3
Listplank
Beugel u = 2.00 Bh
Plat Strip = 4.00 bh
Ringbalk
Bout 15 cm = 5.00 bh
Beugel Plat Strip 5 mm Bout 30 cm = 4.00 bh
Plafond

- Penutup Atap Seng


Panjang = 7.45 m
DETAIL KUDA-KUDA TYPE 1
Skala 1:30 Lebar 1 = 4.00 m
Lebar 2 = 1.84 m
Luas = 73.31 m2

- Seng Bubungan = 7.75 m'

5. Pekerjaan List Plank 3 x 20


Panjang = 23.98 m
1.00
2.00 6. Pekerjaan Plafon
0.20 Panjang = 6.00 m
0.05 Lebar = 4.00 m
0.15
0.30 0.10 Luas Plafon = 36.00 m2
0.15
Pengecetan Plafon = 36.00 m2
0.05
0.30
0.50
Pekerjaan List Plafond = 48.54 m'

7. Pekerjaan Teras
1.00 Panjang = 8.00 m Lebar Rabat Lantai K-125 = 2.03 m
Lebar = 0.50 m Labar Rabat Lantai K-125 = 0.85 m
Tebal Urugan = 0.05 m Lebar Lantai Rabat K-175 = 3.00 m
Tebal Anstamping = 0.15 m Tebal Rabat K-125 = 0.10 m
Lebar Anstamping = 0.50 m Tebal Rabat K-175 = 0.05 m
Lebar Pondasi = 0.30 m Tinggi Sloof = 0.20 m
Tinggi Pondasi = 0.30 m Lebar Sloof = 0.15 m
Tinggi Galian = 0.25 m

- Volume Galian Tanah = 2.13 m3 - Volume Rabat Lantai K-125 = 2.30 m3


- Volume Urugan Pasir = 0.43 m3 - Volume Rabat K-175 = 1.20 m3
- Volume Anstamping = 1.28 m3 - Volume Sloof = 0.51 m3
- Urugan Tanah = 1.02 m3
- Pasangan Batu = 1.53 m3
Sketsa Perhitungan

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 17.00 m
3.66 Jumlah = 4.00 Btng
1.00 Panjang Total = 68.00 m
2.00 Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 60.52 Kg
0.20
0.05
0.15
0.30 0.10 Panjang Tul. = 17.00 m
0.15 Jumlah = 114.33 Btng
Panjang 1 Seng. = 0.70 m
0.05
0.30 Berat Tulangan Ø8 = 0.40 Kg/m
0.50 Berat Tul. Sengkang = 31.61 Kg
Rooster

Total Tulangan = 92.13 Kg


1.00

Rooster
8. Pekerjaan Pintu
Kusen Pintu
Panjang = 5.80 m
Rabat Beton Untuk Pompa Sloof 30/40 Lebar = 0.10 m
Tebal = 0.05 m2
0.15
Volume Kusen = 0.03 m3
0.40 0.20

Daun Pintu
0.70 Tinggi = 1.60 m
Lebar = 2.00 m
0.10
Foot Plate Volume Kayu = 3.20 m2
0.20
4.00 1.00

9. Beton Dudukan Pompa

Panjang = 2.00 m
Rabat Beton Untuk Pompa Lebar = 1.00 m
Tebal = 0.30 m
Jumlah = 2.00 Unit
Volume = 1.20 m3

Rabat Beton Untuk Pompa 1.00

2.50
Uraian Volume Rumah Pompa

Jenis Pekerjaan Satuan Volume

1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat M3 4.20
b. Urugan Tanah Kembali m3 5.69
2. Pekerjaan Struktur
a. Foot Plat
- Beton m3 1.31
- Penulangan Ø12 - 150 mm Kg 187.88
- Bakisting M2 7.56
b. Sloof 30 x 40 cm
- Beton m3 3.24
- Bakisting M2 21.60
- Penulangan Polos Kg 347.54
c. Kolom 15 x 15 cm
- Beton m3 0.71
- Bakisting M2 18.90
- Penulangan Polos Kg 194.32
d. Ring Balk 15 x 20 cm
- Beton m3 0.60
- Bakisting M2 8.00
- Penulangan Polos Kg 108.34
e. Plat Lantai T = 0.2 m
- Beton m3 6.00
- Bakisting M2
- Penulangan Polos Kg 611.97
3. Pekerjaan Dinding
- Dinding Batako M2 42.84
- Dinding Rooster M2 4.08
- Plesteran M2 85.67
- Acian M2 85.67
- Pengecatan M2 85.67
4. Pekerjaan Atap
- Kuda-Kuda Kayu 6/12 cm M3 0.19
- Gording Kayu 5/12 cm M3 0.89
Beugel u Bh 2.00
Plat Strip Bh 4.00
Bout 15 cm Bh 5.00
Bout 30 cm Bh 4.00
- Seng Gelombang BJLS. 0.30 M2 73.31
5. Pekerjaan List Plank 3 x 20 M2 23.98
6. Pekerjaan Plafon M2 36.00
7. Pekerjaan Teras
- Volume Galian Tanah M3 2.13
- Volume Urugan Pasir M3 0.43
- Volume Anstamping M3 1.28
- Urugan Tanah M3 1.02
- Pasangan Batu M3 1.53
- Volume Rabat Lantai K-125 M3 2.30
- Volume Rabat K-175 M3 1.20
- Volume Sloof M3 0.51
- Penulangan Sloof 15 x 20 Kg 92.13
8. Pekerjaan Pintu
- Kusen Pintu M3 0.03
- Daun Pintu M2 3.20
- Engsel Pintu Bh 8.00
- Kunci Tanam Bh 1.00
9. Beton Dudukan Pompa M3 1.20
BACK UP VOLUME PEKERJAAN
NAMA KEGIATAN : PEMBANGUNAN RUMAH SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH 10 X 10 METER 1 UNIT
LOKASI : JALAN NISNONI KEC. KOTA LAMA KEL. KUANINO KOTA KUPANG
TAHUN ANGGARAN : 2021

BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN

1 Bak Pengumpul
Galian Tanah 2.10 2.20 0.85 3.93 M3

Pas batu kosong 2.10 2.20 0.30 1.39 M3

Beton Rabat lantai kerja K-100 2.10 2.20 0.05 0.23 M3

Lantai BP
Beton K-225 2.10 2.20 0.20 0.92 M3

Pembesian
Memanjang 2.50 14.67 0.89 65.12
Melintang 2.60 14.00 0.89 64.65
total 129.77 Kg

Bekisting 8.60 0.20 1.72 M2

Dinding BP
Beton K-225 7.80 0.20 4.00 6.24 M3

Pembesian
Memanjang 7.90 26.67 0.89 187.07
Melintang 4.30 52.00 0.89 198.56
total 385.63 Kg

Bekisting 14.00 4.00 56.00 M2

Plat atap BP
Beton K-225 2.00 1.90 0.10 0.38
Pengurang 0.60 0.60 0.10 0.04
total 0.34 M3

Pembesian
Memanjang 2.10 12.67 0.89 23.62
Melintang 2.00 13.33 0.89 23.68
total 47.30 Kg

Bekisting 7.80 0.10 0.78


1.50 1.60 2.40
total 3.18 m2

Plesteran/ Aciian 7.80 1.50 11.70 M2

Pengecatan 7.80 1.50 11.70


2.00 1.90 3.80
Total 15.50 M2
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN

Waterstop 20 cm 7.80 7.80 m


Tutup manhole 1.00 1.00 Bh
pipa overflow GIP 90 mm 1.50 1.50 Bh
pipa hawa 1.00 1.00 Bh

2 PAGAR BRC KELILING SOLAR CELL


galian tanah 60.00 0.80 0.50 24.00 M3

pasangan batu kosong 60.00 0.80 0.10 4.80 M3

pas. Pondasi 1 PC : 4PS 60.00 0.45 0.70 18.90


pengurang 0.20 0.20 0.55 16.00 0.35
TOTAL 19.25 M3

beton tumbuk K-100 0.20 0.20 0.55 16.00 0.35 M3

Sloof 15 x 20 beton K-100 57.50 0.15 0.20 1.73 M3

Pembesian sloof 0.50 383.33 0.22 42.55


57.50 16.00 0.40 363.40
TOTAL 405.95 KG

Bekisting Sloof 57.50 0.20 2.00 23.00 Lbr

Pemasangan pagar BRC 24.00 24.00 Lbr

3 SOLAR CELL
Pompa SP 17 - 7 DOL 1.00 1.00 unit
Solar Modul GF 270 ( 18 in series x 2 parallel ) 36.00 36.00 pcs
Array to controler wire kit (MC4) 10.00 10.00 set
Array to Array wire kit (MC4) 1.00 1.00 set
OTDCP16, Circuit Breaker, 16Amp ( DC ) 2.00 2.00 pcs
OVR PV 40-1000 P, Surge Protection ( DC ) 1.00 1.00 pcs
RSI 3x380V IP66 5,5kW 12A, 1.00 1.00 pcs
Sine Wafe Filter 1.00 1.00 pcs
MCB 3P 40 A 6/10kA, Circuit Breaker AC 1.00 1.00 pcs
Level Switch Complet 3M 2.00 2.00 pcs

4 PEKERJAAN AIR VALVE


Galian Tanah 1.50 1.50 0.85 1.91 M3
Urugan Pasir 1.50 1.50 0.45 1.01 M3
Beton Tumbuk 1.40 1.40 0.10 0.20
4.00 0.15 0.10 0.06
TOTAL 0.26 M3

Pasangan Bata 4.00 0.90 3.60 M2


Plesteran & Acian 4.00 0.90 3.60
4.00 0.90 3.60
TOTAL 7.20 M2
Urugan Tanah 4.00 0.10 0.30 0.12 M3

Tee All Flange Ø50 X 50 X 50 mm 1.00 1.00 Buah


Flange Air Valve Ø 50 mm 1.00 1.00 Buah
Paking Karet 50mm 4.00 4.00 Buah
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
Gilbout Joint Joint CI. Ø 50 mm 1.00 1.00 Buah
Baut-moer 5/8 20.00 20.00 Buah
Engsel 2.00 2.00 Buah
Kunci Gembok 1.00 1.00 Buah
Tutup bak kontrol 1.00 1.00 Buah

5 PEKERJAAN WASH OUT


Galian Tanah 1.80 1.30 1.00 2.34 M3
Beton Tumbuk 1.50 1.00 0.10 0.15
5.00 0.15 0.10 0.08
TOTAL 0.23 M3

Pasangan Bata 5.00 0.90 4.50 M2


Plesteran & Acian 5.00 0.90 4.50
5.00 0.90 4.50
TOTAL 9.00 M2
Urugan Tanah 5.00 0.10 0.30 0.15 M3

Tee All Flange 75 x 75 x 75 1.00 1.00 Buah


Gate Valve All Flange dia. 75 mm 3.00 3.00 Buah
Giboult Join dia. 75 mm 6.00 6.00 Buah
Pipa HDPE dia. 90 mm 1.50 1.50 Buah
Packing Karet dia. 75 mm 6.00 6.00 Buah
Stub Flange Ø 90 mm 3.00 3.00 Buah
Baut Moer 5/8 x 3 Metal + Ring 36.00 36.00 Buah
Engsel 2.00 2.00 Buah
Kunci Gembok 1.00 1.00 Buah
Tutup bak kontrol 1.00 1.00 Buah

6 Reservoar 30 m3
Galian Tanah 6.30 3.90 1.15 28.26
1.70 1.15 0.60 1.17
Total 29.43 M3

Pasangan Batu Kosong 6.30 3.90 0.30 7.37


1.70 1.15 0.30 0.59
Total 7.96 M3

Lantai Kerja Beton 1PC:3PS:5KR 6.30 3.90 0.05 1.23


1.70 1.15 0.05 0.10
Total 1.33 M3

Lantai Reser K-225


Beton Bertulang 6.30 3.90 0.25 6.14
1.70 1.15 0.25 0.49
Total 6.63 M3

Pembesian
Memanjang 1 6.75 26.00 0.89 155.84
Melintang 2 4.35 42.00 0.89 162.24
Memanjang 1 2.15 7.67 0.89 14.64
Melintang 2 1.60 11.33 0.89 16.10
Total 697.64 Kg

Bekisting Lantai 22.70 0.25 5.68 M2


BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN

Dinding Reser K-225


Beton Bertulang 25.80 0.20 2.75 14.19
2.60 0.15 0.80 0.31
Jumlah 14.50
Pengurang 1.90 1.20 0.20 2.00 0.91
Total 13.59 M3

Pembesian
Memanjang 1 25.80 18.33 0.89 420.02
Melintang 2 3.10 172.00 0.89 473.48
Memanjang 1 2.70 5.33 0.89 12.79
Melintang 2 1.35 17.33 0.89 20.78
Total 1854.14 Kg

Bekisting Lantai 3.60 0.80 2.88


3.00 0.80 2.40
24.05 2.75 66.14
18.00 2.75 49.50
8.00 2.75 22.00
2.00 2.75 5.50
Jumlah 148.42
Pengurang 1.90 1.20 2.00 4.56
Total 143.86 M3

Plat atap Reser K-225


Beton Bertulang 5.90 3.50 0.12 2.48
1.30 1.15 0.10 0.15
Jumlah 2.63
Pengurang 0.60 0.60 0.12 3.00 0.13
Total 2.50 M3

Pembesian
Memanjang 1 6.00 23.33 0.89 124.32
Melintang 2 3.60 39.33 0.89 125.74
Memanjang 1 1.40 7.67 0.89 9.53
Melintang 2 1.25 1.45 0.89 1.61
Total 522.40 Kg

Bekisting Plat atap 18.80 0.12 2.26


3.60 0.10 0.36
2.00 3.00 6.00
2.00 3.00 6.00
1.00 3.00 3.00
1.00 1.00 1.00
Jumlah 18.62
Pengurang 0.60 0.60 3.00 1.08
Total 17.54 M2

Plesteran/ acian 25.80 2.75 70.95


2.60 0.80 2.08
Jumlah 73.03
1.90 1.20 2.00 4.56
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
Total 68.47 M2

Pengecatan 25.80 2.75 70.95


2.60 0.80 2.08
5.90 3.50 20.65
1.30 1.15 1.50
Jumlah 95.18
1.90 1.20 2.00 4.56
0.60 0.60 3.00 1.08
Total 89.54 M2

Waterstop 20cm 16.00 3.00 48.00 M'


Flange Threaded GIP. Ǿ 50 mm 28.00 28.00 Bh
Tee All Threaded G.I Ø 50 X 50 X 50 mm 2.00 2.00 Bh
Gate Valve All Flange PN. 10 Ø 50 mm 5.00 5.00 Bh
Knie GIP. Ø 50 mm - 90˚ 4.00 4.00 Bh
Dop/Kop dia 50 mm 1.00 1.00 Bh
Paking Karet Ǿ 50 mm 31.00 31.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 232.00 232.00 Bh
Gilbout Joint Joint CI. Ø 50 mm 3.00 3.00 Bh
Tangga Kontrol 3.00 3.00 Bh
Pipa Hawa 2.00 2.00 Bh
Tutup bak kontrol 3.00 3.00 Bh
Pintu Besi 1.00 1.00 Bh

7 Pipa Transmisi
GIP 75 mm (CP.0 - CP.1)
Pipa Galvanized Steel Pipe (GSP) Ø 750 mm 2040.00 2040.00 M'
Socket GIP. Ø 75 mm 320.00 320.00 Bh
Water Moor GIP. dia 75 mm 20.00 20.00 Bh
Knie GIP. Ø 75 mm - 90˚ 1.00 1.00 Bh
Knie GIP. Ø 75 mm - 45˚ 14.00 14.00 Bh

Galian Tanah 2040.00 0.30 0.60 367.20 M3


Urugan Tanah Kembali 2040.00 0.30 0.60 0.00 367.20 M3

8 Pipa Distribusi
HDPE 63 mm (CP.1 - P.47)
Pipa Polyethylene (PE) Ø 63 mm (2") 2058.00 2058.00 M'
Coupler/Coupling Ø 63 mm 21.00 21.00 Bh
End Cap Ø 63 mm 1.00 1.00 Bh

Galian Tanah 2058.00 0.26 0.50 267.54 M3


Urugan Tanah Kembali 2058.00 0.26 0.50 0.00 267.54 M3

HDPE 63 mm (CP.1 - CP.3)


Pipa Polyethylene (PE) Ø 63 mm (2") 4408.00 4408.00 M'
Coupler/Coupling Ø 63 mm 44.00 44.00 Bh
End Cap Ø 63 mm 1.00 1.00 Bh

Galian Tanah 4408.00 0.26 0.50 573.04 M3


Urugan Tanah Kembali 4408.00 0.26 0.50 0.00 573.04 M3

HDPE 50 mm (CP.3 - CP.5)


Pipa HDPE 50 mm 582.00 582.00 M'
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
Coupler/Coupling Ø 50 mm 6.00 6.00 Bh
End Cap Ø 50 mm 1.00 1.00 Bh

Galian Tanah 0.30 0.40 69.84 M3


Urugan Tanah Kembali 0.30 0.40 0.00 68.70 M3

HDPE 63 mm (CP.3 - P.75)


Pipa Polyethylene (PE) Ø 63 mm (2") 1094.00 1094.00 M'
Coupler/Coupling Ø 63 mm 11.00 11.00 Bh
End Cap Ø 63 mm 1.00 1.00 Bh

Galian Tanah 1094.00 0.26 0.50 142.22 M3


Urugan Tanah Kembali 1094.00 0.26 0.50 0.00 142.22 M3

HDPE 50 mm (CP.3 - CP.4)


Pipa HDPE 50 mm 1660.00 1660.00 M'
Coupler/Coupling Ø 50 mm 17.00 17.00 Bh
End Cap Ø 50 mm 1.00 1.00 Bh

Galian Tanah 0.30 0.40 199.20 M3


Urugan Tanah Kembali 0.30 0.40 0.00 195.94 M3

10 SR
Galian Tanah 19.00 0.10 0.10 0.19 M3

Urugan Tanah Kembali 0.19 M3

Beton Tumbuk Dudukan Box Water Meter 0.50 0.20 0.10 0.01 M3

Beton perkuatan Kran SR 0.20 0.20 0.10 0.00 M3

Bekisting dudukan Box 0.50 0.20 0.10


1.40 0.10 0.14
Total 0.24 M2

Bekisting beton perkuatan kran 0.80 0.10 0.08


0.20 0.20 0.04
Total 0.12 M3

- Pipa GIP Ǿ 25 mm 18.00 18.00 M'


- Pipa GIP Ǿ 15 mm 6.00 6.00 M'
- Clamp Sadle HDPE ∅ 63 x 25 mm 1.00 1.00 Bh
- Knie GIP Ǿ 15 mm 6.00 6.00 Bh
- Socket GIP. Ǿ 25 mm 3.00 3.00 Bh
- Double Nipple GIP. Ǿ 15 mm 2.00 2.00 Bh
- Water Meter GIP. Ǿ 15 mm 1.00 1.00 Bh
- Stop Kran 20mm 1.00 1.00 Bh
- Tap Kran Ǿ 15 mm 1.00 1.00 Bh
- Box Water Meter 1.00 1.00 Bh
Beton Slof K-175 (S) Uk.(15 x 20) cm Bekisting Slof (S) Uk.(15 x 20) cm Pembesian Slof (S) Uk.(15 x 20) cm

Dimensi Dimensi Dimensi


Volume
n Tulangan (kg)
b (m') h (m) l (m') n (bh) l Total (m') V (m3) b (m') h (m') l (m') n (bh) V (m2) Diameter l (m') Jarak (m') n Slof BJ Besi
Arah XY Ket Arah XY Ket No (bh) Arah Ket
(mm)
e=
a b c d e = cxd f = axbxcxd a b c d a b c d f = a*c*d*e
N0 N0 2xbxcxd e
1 12 78.50 4.00 1.00 0.89 278.63 Tul Pokok
1 0.15 0.20 35.50 1.00 35.50 1.07 X S 1 0.15 0.20 39.25 1.00 15.70 S 2 8 0.60 0.12 655.17 1.00 0.39 155.03 Tul. Sengkang
2 0.15 0.20 43.00 1.00 43.00 1.29 Y

Total Volume A 78.50 2.36 Total Volume 15.70 Total Volume 433.66

Beton K-175 Kolom (K1) Uk.(15 x 15) cm Bekisting Kolom (K1) Uk.(15 x 15) cm Pembesian Kolom (K1) Uk.(15 x 15) cm

N0 Dimensi Ket N0 Dimensi Ket Dimensi


Volume
n Tulangan (kg)
b (m') l (m) h (m') n (bh) l Total (m') V (m3) b (m') h (m') l (m') n (bh) V (m2) l (m') Jarak (m') n Kolom BJ Besi
Diameter (bh)
Arah XY Arah XY No Arah Ket
e=((2xa) (mm)
a b c d e = cxd e = axbxcxd a b c d +(2xb))xcx a b c d f = a*c*d*e
d e
1 12 75.10 4.00 1.00 0.89 266.56 Tul Pokok
1 0.15 0.15 3.40 11.00 37.40 0.84 K1 1 0.15 0.15 3.40 16.00 4.80 K1 2 8 0.48 0.12 626.83 1.00 0.39 118.66 Tul. Sengkang
2 0.15 0.15 2.90 13.00 37.70 0.85 K2 & K3 2 0.15 0.15 2.90 7.00 2.10 K2 & K3
Total Volume 385.23
Total Volume 75.10 0.84 Total Volume 6.90

Pembesian Ring Balk (R) Uk.(10 x 15) cm


Beton Ring Balk K-175 (R) Uk.(10 x 15) cm Bekisting Ring Balk (R) Uk.(10 x 15) cm
Dimensi
Volume
Diameter n Tulangan (kg)
No l (m') Jarak (m') n Slof BJ Besi Arah Ket
Dimensi Dimensi (mm) (bh)
b (m') h (m) l (m') n (bh) l Total (m') V (m3) Arah XY Ket b (m') h (m') l (m') n (bh) V (m2) Arah XY Ket a b c d e f = a*c*d*e
e=
a b c d e = cxd f = axbxcxd a b c d
N0 N0 2xbxcxd 1 10 78.50 4.00 1.00 0.62 193.49 Tul Pokok
2 8 0.39 0.12 655.17 1.00 0.39 100.77 Tul. Sengkang
1 0.10 0.15 35.50 1.00 35.50 0.53 X R 1 0.10 0.15 39.25 1.00 11.78 R
2 0.10 0.15 43.00 1.00 43.00 0.65 Y
Total Volume 294.27
` Total Volume A 78.50 1.18 Total Volume 11.78
Pembesian Meja Beton
Beton K-100 Meja Beton Tebal 10cm Begisting Meja Beton Tebal 10 cm
Dimensi
Volume
Diameter n Tulangan (kg)
No l (m') Jarak (m') n Plat BJ Besi Arah Ket
Dimensi Dimensi (mm) (bh)
b (m') l (m') h (m') n (bh) V (m3) Arah XY Ket N0 b (m') l (m') h (m') n (bh) V (m2) Arah XY Ket a b c d e f = a*c*d*e
a b c d e = axbxcxd a b c
N0 1 10 0.90 0.15 17.14 1.00 0.62 9.51 X Atas
10 0.70 0.15 10.37 1.00 0.62 4.47 Y Bawah
1 0.80 0.60 0.08 1.00 0.04 1 0.80 0.60 0.08 1.00 0.64 - 2 10 0.80 0.15 17.78 1.00 0.62 8.76 X Atas
2 0.80 0.60 0.08 1.00 0.04 2 0.80 0.60 0.08 1.00 0.64 10 0.60 0.15 10.00 1.00 0.62 3.70 Y Bawah
Total Volume 26.44
Total Volume A 0.08 Total Volume 1.28

Beton Gewel K-175 (GEWEL 1) Uk.(10 x 15) cm Bekisting Gewel (GEWEL 1) Uk.(10 x 15) cm Pembesian Gewel
Dimensi
Volume
Diameter n Tulangan (kg)
No l (m') Jarak (m') n Slof BJ Besi Arah Ket
Dimensi Dimensi (mm) (bh)
b (m') h (m) l (m') n (bh) l Total (m') V (m3) Arah XY Ket b (m') h (m') l (m') n (bh) V (m2) Arah XY Ket a b c d e f = a*c*d*e
e=
a b c d e = cxd f = axbxcxd a b c d
N0 N0 2xbxcxd 1 10 27.45 4.00 1.00 0.62 67.66 Tul Pokok
2 8 0.39 0.12 229.75 1.00 0.39 35.34 Tul. Sengkang
1 0.10 0.15 9.15 2.00 18.30 0.27 GEWEL 1 1 0.10 0.15 13.73 1.00 2.75 GEWEL 1
2 0.10 0.15 9.15 1.00 9.15 0.14 GEWEL 2
3 0.10 0.15 3.15 1.00 3.15 0.05 GEWEL 3 Total Volume 103.00
Total Volume A 27.45 0.41 Total Volume 2.75
PEKERJAAN ATAP DAN PLAFOND

KUDA - KUDA BAJA RINGAN 0,75 MM

TYPE A T N M2 KET

KUDA - KUDA 1 10.15 1.85 5 46.944 BAJA RINGAN

KUDA - KUDA 2 10.15 1.85 4 37.555 BAJA RINGAN

KUDA - KUDA 3 4.15 0.8 3 4.980 BAJA RINGAN

TOTAL VOLUME 84.499

RENG BAJA RINGAN 0,35 MM

TYPE P L N M2 KET

KUDA - KUDA 1 5.25 0.035 36 6.615 BAJA RINGAN

KUDA - KUDA 2 3.50 0.035 36 4.410 BAJA RINGAN

KUDA - KUDA 3 3.5 0.035 14 1.715 BAJA RINGAN

TOTAL VOLUME 12.74

ATAP SENG MULTIROOF

TYPE B H N M² KET

ATAP 1 5.25 5.4 2 56.7 GENTENG MULTIROOF 0,30

ATAP 2 5.25 5.4 2 56.7 GENTENG MULTIROOF 0,30

ATAP 3 2.22 3.5 2 15.54 GENTENG MULTIROOF 0,30

TOTAL VOLUME 128.94

SENG NOK MULTIROOF

TYPE P N M KET

12.25 1 12.25 BUBUNGAN NOK MULTIROOF

TOTAL VOLUME 12.25

LISTPLANK

TYPE P N M KET
59.10 1 59.1 KALSIPLANK 30 CM

TOTAL VOLUME 59.1

PLAFOND GYPSUM

TYPE P L M2 KET

1.43 4.00 5.720 Teras Depan

1.43 2.93 4.190 Teras Samping

3.85 2.85 10.973 Ruang Tamu

2.85 2.85 8.123 K. TIDUR 2

2.85 2.85 8.123 K. TIDUR 3

2.85 2.85 8.123 K. TIDUR 1

1.35 1.35 1.823 KM/WC 1

1.35 1.85 2.498 KM/WC2

3.85 4.50 17.325 R. KEL 1

1.35 1.50 2.025 R. KEL 2

2.85 5.35 15.248 DAPUR

46.40 0.50 23.200 TIRIS LUAR

TOTAL VOLUME 84.167

LIST PLAFOND GYPSUM

TYPE P N M' KET

18.80 18.80 TERAS

88.65 88.65 BANGUNAN INDUK

46.40 46.40 TIRIS LUAR

TOTAL VOLUME 153.85


PEKERJAAN GALIAN TANAH DAN URUGAN

VOLUME GALIAN

TYPE P L T M³ KET

PONDASI MENERUS 1 35.5 1 0.8 28.4 HORIZONTAL

PONDASI MENERUS 1 43 1 0.8 34.4 VERTICAL

TOTAL VOLUME 62.8 M3

URUG PASIR

TYPE P L T M³ KET

PONDASI MENERUS 1 35.50 1 0.05 1.775 HORIZONTAL

PONDASI MENERUS 1 43.00 1 0.05 2.15 VERTICAL

3.925 M3

URUGAN PASIR BAWAH LANTAI 1.43 4.00 0.05 0.286 Teras Depan

1.43 2.93 0.05 0.209 Teras Samping

3.85 2.85 0.05 0.143 Ruang Tamu

2.85 2.85 0.05 0.143 K. TIDUR 2

2.85 2.85 0.05 0.143 K. TIDUR 3

2.85 2.85 0.05 0.143 K. TIDUR 1

1.35 1.35 0.05 0.068 KM/WC 1

1.35 1.85 0.05 0.093 KM/WC2

3.85 4.50 0.05 0.225 R. KEL 1

1.35 1.50 0.05 0.075 R. KEL 2

2.85 5.35 0.05 0.268 DAPUR

1.793 M3

URUG SIRTU

TYPE P L T M³ KET

1.43 4.00 0.25 1.430 Teras Depan

1.43 2.93 0.25 1.047 Teras Samping

3.85 2.85 0.25 2.743 Ruang Tamu


2.85 2.85 0.25 2.031 K. TIDUR 2

2.85 2.85 0.25 2.031 K. TIDUR 3

2.85 2.85 0.25 2.031 K. TIDUR 1

1.35 1.35 0.25 0.456 KM/WC 1

1.35 1.85 0.25 0.624 KM/WC2

3.85 4.50 0.25 4.331 R. KEL 1

1.35 1.50 0.25 0.506 R. KEL 2

2.85 5.35 0.25 3.812 DAPUR

TOTAL VOLUME 21.04185 m3


PEKERJAAN PONDASI

ANSTAMPING

TYPE P L T M³ KET

PONDASI MENERUS 1 35.50 1.00 0.15 5.33 HORIZONTAL

PONDASI MENERUS 1 43.00 1.00 0.15 6.45 VERTICAL

TOTAL VOLUME 11.78

PASANGAN PONDASI

TYPE La Lb T P M³ KET

PONDASI MENERUS 1 0.3 0.8 0.8 35.50 15.62 HORIZONTAL

PONDASI MENERUS 1 0.3 0.8 0.8 43.00 10.32 VERTICAL

TOTAL VOLUME 25.94


PEKERJAAN LANTAI/ DINDING KERAMIK

PENUTUP LANTAI KERAMIK DAN GRANIT

TYPE P L M² KET

GRANIT 60 x 60 1.43 4.00 5.72 Teras Depan

GRANIT 60 x 60 1.43 2.93 4.19 Teras Samping

GRANIT 60 x 60 3.85 2.85 10.97 Ruang Tamu

GRANIT 60 x 60 3.85 4.50 17.33 R. KEL 1

GRANIT 60 x 60 1.35 1.50 2.03 R. KEL 2

GRANIT 60 x 60 2.85 5.35 15.25 DAPUR

55.48

KERAMIK 40 x 40 2.85 2.85 8.12 K. TIDUR 2

KERAMIK 40 x 40 2.85 2.85 8.12 K. TIDUR 3

KERAMIK 40 x 40 2.85 2.85 8.12 K. TIDUR 1

0.000 LORONG

24.37

LANTAI KERAMIK 25 x 25 1.35 1.35 1.823 KM/WC 1

LANTAI KERAMIK 25 x 25 1.35 1.85 2.498 KM/WC2

4.32

DINDING KERAMIK 25 x 40 1.00 4.68 4.680 KM/WC 1

DINDING KERAMIK 25 x 40 1.00 5.68 5.680 KM/WC2

DINDING KERAMIK 25 x 40 2.34 0.60 0.7 0.983 MEJA BETON

11.34

RABAT

TYPE P L T M3 KET

1.43 4.00 0.05 0.286 Teras Depan

1.43 2.93 0.05 0.209 Teras Samping

3.85 2.85 0.05 0.549 Ruang Tamu

2.85 2.85 0.05 0.406 K. TIDUR 2

2.85 2.85 0.05 0.406 K. TIDUR 3


2.85 2.85 0.05 0.406 K. TIDUR 1

3.85 4.50 0.05 0.866 R. KEL 1

1.35 1.50 0.000 R. KEL 2

2.85 5.35 0.05 0.762 DAPUR

1.35 1.35 0.05 0.091 KM/WC 1

1.35 1.85 0.05 0.125 KM/WC2

4.11
PEKERJAAN KUSEN

PEKERJAAN KUSEN PINTU/ JENDELA

TYPE P L T N M³ KET

PJ1 19.52 0.12 0.06 2 0.281 KUSEN KAYU MERANTI

P1 5.25 0.12 0.06 4 0.151

J1 5.52 0.12 0.06 1 0.040

J2 4.40 0.12 0.06 2 0.063

TOTAL VOLUME 0.535 M3

LUASAN KUSEN DAN BUVEN/ LUBANG ANGIN

TYPE P L N M2 KET

P1 2.05 1.00 4 8.20

P2 2.05 0.72 2 2.95

PJ1 2.05 0.9 2 3.69 Pintu

PJ1 1.82 1.18 2 4.30 Jendela

J1 1.82 1.18 2 4.30

J2 1.82 0.52 2 1.89

LUBANG ANGIN 0.3 0.3 12 1.08

TOTAL VOLUME 26.405

PEKERJAAN DAUN PINTU & JENDELA

TYPE P L N M2 KET

P1 2 0.90 2 3.60 DAUN PINTU JATI

P2 2 0.80 4 6.40 DAUN PINTU JATI

TOTAL VOLUME 10.000

J1 1.06 1.70 6 10.81 DAUN JATI + KACA

J2 0.5 1.70 2 1.70 DAUN JATI + KACA

TOTAL VOLUME 12.512


PEKERJAAN PENGECATAN

PEKERJAAN CAT KUSEN

TYPE P L N M² KET

PJ1 19.52 0.21 2 8.20 CAT KAYU

P1 5.25 0.21 4 4.41

J1 5.52 0.21 1 1.16

J2 4.40 0.21 2 1.85

TOTAL VOLUME 15.62

PEKERJAAN TAKE OIL DAUN PINTU & JENDELA

TYPE P L N M² KET

P1 2 0.90 2 7.20 TAKE OIL KAYU

P2 2 0.80 4 12.80

J1 1.06 1.70 6 21.62

J2 0.5 1.70 2 3.40

TOTAL VOLUME 45.02

CAT PLAFOND

TYPE P L M² KET

1.43 4.00 5.720 TERAS

1.43 2.93 4.190 TERAS

3.85 2.85 10.973 R. TAMU

2.85 2.85 8.123 K. TIDUR 2

2.85 2.85 8.123 K. TIDUR 3

2.85 2.85 8.123 K. TIDUR 1

3.85 4.50 17.325 R. KEL

1.35 1.50 2.025 R. KEL

2.85 5.35 15.248 DAPUR

1.35 1.35 1.823 KM/WC 1

1.35 1.85 2.498 KM/WC2


0.50 0.50 0.250 TIRIS LUAR

TOTAL VOLUME 84.42


PEKERJAAN PASANGAN DINDING

PASANGAN DINDING BATAKO

TYPE P H M² KET

DINDING 30.00 3.40 102.00 TRAP 1

DINDING 24.00 2.90 69.60 TRAP 2

DINDING 9.00 2.90 26.10 TRAP 3

TOTAL LUASAN BRUTO 171.60

TOTAL LUASAN TEMBOK BERSIH 145.19

TYPE ALAS H N M² KET

GEWEL 1 9.15 1.86 2 8.51

GEWEL 2 9.15 1.86 1 8.51

GEWEL 3 3.15 0.8 1 1.260

TOTAL 17.02

PLESTERAN

TYPE P H M² KET

DINDING 30.00 3.40 204.00 TRAP 1

DINDING 24.00 2.90 139.20 TRAP 2

DINDING 9.00 2.90 52.20 TRAP 3

TOTAL VOLUME PLESTERAN TEMBOK 395.40

TEMBOK GEWEL 1 9.15 0.50 2 9.15 TRAP 1

TEMBOK GEWEL 2 9.15 1.50 1 27.45 TRAP 2

TEMBOK GEWEL 3 3.15 2.50 1 15.75 TRAP 3

TOTAL VOLUME PLESTERAN PONDASI 52.35

PONDASI 43.50 0.50 21.75 PLESTERAN

TOTAL VOLUME PLESTERAN PONDASI 21.75


REKAPITULASI
RENCANA ANGGARAN BIAYA
NAMA KEGIATAN : PEMBANGUNAN RUMAH SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH 10 X 10 METER 1 UNIT
LOKASI : JALAN NISNONI KEC. KOTA LAMA KEL. KUANINO KOTA KUPANG
TAHUN : 2021

JUMLAH
No URAIAN PEKERJAAN SATUAN VOLUME HARGA
(RP.)
1 2 3 4 5

I PEKERJAAN PERSIAPAN 1.00 Rp 900,000.00

II PEKERJAAN GALIAN TANAH DAN URUGAN 1.00 Rp 10,839,641.61

III PEKERJAAN PASANGAN DAN PLESTERAN 1.00 Rp 122,531,710.18

IV PEKERJAAN BETON 1.00 Rp 42,337,159.23

V PEKERJAAN KAYU & ALUMUNIUM KUSEN PINTU & JENDELA 1.00 Rp 20,745,869.95

VI PEKERJAAN ATAP DAN PLAFOND 1.00 Rp 60,263,879.46

VII PEKERJAAN LANTAI DAN PENUTUP DINDING 1.00 Rp 32,999,147.65

VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1.00 Rp 2,505,918.00

IX PEKERJAAAN INSTALASI AIR 1.00 Rp 21,788,471.00

X PEKERJAAN INSTALASI LISTRIK 1.00 Rp 7,254,380.00

XI PEKERJAAN PENGECETAN 1.00 Rp 11,376,003.65

XII PEKERJAAN LAIN - LAIN 1.00 Rp 1,505,310.80

Jumlah Biaya Rp 335,047,491.52

Dibulatkan Rp 335,000,000.00

Terbilang : TIGA RATUS TIGA PULUH LIMA JUTA RUPIAH

Kupang, Januari 2022


Di Hitung Oleh :

TTD

LUKIM NOMLENI
RENCANA ANGGARAN BIAYA

NAMA KEGIATAN : PEMBANGUNAN RUMAH SEDERHANA

PEKERJAAN : PEMBANGUNAN RUMAH 10 X 10 METER 1 UNIT

LOKASI : JALAN NISNONI KEC. KOTA LAMA KEL. KUANINO KOTA KUPANG

TAHUN : 2021

HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6 = 4x5

I PEKERJAAN PERSIAPAN
- Pembersihan Lokasi Ls 1.00 400,000.00 400,000.00

- Penyediaan Air Bersih Ls 1.00 500,000.00 500,000.00

- Pemasangan Papan nama Ls 750,000.00 -


Jumlah Harga Pekerjaan Rp 900,000.00

II PEKERJAAN GALIAN TANAH DAN URUGAN

- Galian Tanah M3 62.80 66,962.00 4,205,213.60

- Urugan Kembali Sisa Galian M3 20.93 24,062.00 503,697.87

- Urugan Pasir Bawah Pondasi M3 3.93 392,369.00 1,540,048.33

- Urugan Pasir Bawah Lantai M3 1.79 392,369.00 703,515.66

- Urugan Sirtu Peninggi Lantai M3 21.04 184,735.00 3,887,166.16

Jumlah Harga Pekerjaan Rp 10,839,641.61

III PEKERJAAN PASANGAN DAN PLESTERAN

- Pas. Anstamping batu Kosong (Kali/Karang) M3 11.78 935,931.00 11,020,587.53

- Pas. Pondasi 1 Pc : 5 Psr M3 25.94 1,266,724.00 32,858,820.56

- Pas. Tembok Gewel 1 Pc : 4 Psr M2 17.02 183,110.00 3,116,349.09

- Pas. Dinding Batako 1 Pc : 4 Psr M2 171.60 183,110.00 31,421,676.00

- Plesteran Pondasi 1 Pc : 5 Psr M2 21.75 58,129.00 1,264,305.75

- Plesteran Dinding dan Tembok Gewel 1 Pc : 3 Psr M2 447.75 60,911.00 27,272,900.25

- Acian bidang plesteran seluruhnya M2 469.50 33,178.00 15,577,071.00

Jumlah Harga Pekerjaan Rp 122,531,710.18

IV PEKERJAAN BETON

Cor Sloof 15/20 (Mutu K125)

- Beton M3 2.36 1,027,951.00 2,420,824.61

- Pembesian Besi Polos Kg 433.66 24,047.70 10,428,637.32

- Begisting M2 15.70 186,692.00 2,931,064.40

Cor Kolom 15/15 (Mutu K125)

- Beton M3 0.84 1,027,951.00 865,020.77

- Pembesian Besi Polos Kg 385.23 24,047.70 9,263,808.98

- Begisting M2 6.90 186,692.00 1,288,174.80

Cor Ring Balk 10/15 (Mutu K125)

- Beton M3 1.18 1,027,951.00 1,210,412.30

- Pembesian Besi Polos Kg 294.27 24,047.70 7,076,412.74

- Begisting M2 11.78 186,692.00 2,198,298.30

Cor Meja Beton (Mutu K100)

- Beton M3 0.08 992,061.00 76,190.28

- Pembesian Besi Polos Kg 26.44 24,047.70 635,875.23

- Begisting M2 1.28 425,463.00 544,592.64

Cor Balok Gewel Uk. 10/15 (Mutu K100)


- Beton M3 0.41 992,061.00 408,481.12
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6 = 4x5
- Pembesian Besi Polos Kg 103.00 24,047.70 2,476,896.20

- Begisting M2 2.75 186,692.00 512,469.54


Jumlah Harga Pekerjaan Rp 42,337,159.23
V PEKERJAAN KAYU & ALUMUNIUM KUSEN PINTU & JENDELA
- Pek. Kusen Pintu dan Jendela Kayu Kelas I M3 0.54 10,906,842.00 5,839,435.95
- Pek. Daun Panel Pintu Papan Kayu Kelas I M2 10.00 727,375.00 7,273,750.00
- Pek. Daun Jendela Papan Kayu Kelas I + Kaca Tebal 5 mm M2 12.51 510,125.00 6,382,684.00
- Pas. Kosen & Daun Pintu Alumunium komplit KM/WC Unit 2.00 355,000.00 710,000.00
- Pek. Buven/ Lubang Angin Buah 12.00 45,000.00 540,000.00
Jumlah Harga Pekerjaan Rp 20,745,869.95
VI PEKERJAAN ATAP DAN PLAFOND
- Pek. Kuda-Kuda Baja Ringan 75.35-0,75 + Reng Baja Ringan M2 97.24 244,054.00 23,731,505.89
- Pas. Atap Multiroof Tebal 0,30mm M2 128.94 117,280.00 15,122,083.20
- Pas. Bubungan Multiroof 0,30 mm M' 12.25 35,000.00 428,750.00
- Pek. Plafond Gypsum Board M2 84.17 75,375.00 6,344,117.78
- Pek. Rangka Plafon Pipa Kotak Baja Ringan 2 x 4 cm M2 84.17 91,017.00 7,660,664.25
- Pek. List Plafond Gypsum M' 153.85 19,925.00 3,065,461.25
- Pas. List Plank (Wood Plank) M' 59.10 66,181.00 3,911,297.10
Jumlah Harga Pekerjaan Rp 60,263,879.46
VII PEKERJAAN LANTAI DAN PENUTUP DINDING
- Pek. Lantai Rabat M3 4.11 931,274.00 3,824,854.07
- Pek. Lantai Keramik 40 x 40 cm Platinum M2 24.37 168,751.00 4,112,039.99
- Pek. Lantai Keramik Granit 60 x 60 cm M2 55.48 253,619.00 14,070,756.76
- Pek. Plint Keramik 10 x 60 cm M' 32.71 70,443.00 2,304,190.53
- Pek. Lantai Keramik 25 x 25 cm KM/WC (Bertekstur) M2 4.32 1,329,243.00 5,742,329.76
- Pek. Dinding Keramik 25 x 40 cm Dapur, meja beton & KM/MC M2 11.34 259,634.00 2,944,976.54

Jumlah Harga Pekerjaan Rp 32,999,147.65


VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI
- Handel Pintu Unit 2.00 355,000.00 710,000.00
- Pas Kunci Tanam 2x Putar Bh 4.00 145,755.00 583,020.00
- Pas. Kait Angin (Stenlis) Bh 16.00 18,210.00 291,360.00
- Pas. Grendel Jendela (Stenlis) Bh 8.00 26,500.00 212,000.00
- Pas. Grendel Pintu (Stenlis) Bh 2.00 27,000.00 54,000.00
- Pas. Engsel Jendela (Stenlis) Set 8.00 36,550.00 292,400.00
- Pas. Engsel pintu (Stenlis) Set 6.00 60,523.00 363,138.00
Jumlah Harga Pekerjaan Rp 2,505,918.00
IX PEKERJAAAN INSTALASI AIR
Pekerjaan Instalasi Air Bersih
- Pekerjaan Pemasangan Instalasi Air Bersih Pipa PVC 1/2" M' 12.00 50,487.00 605,844.00
- Pekerjaan Pemasangan Instalasi Air Bersih Pipa PVC 3/4" M' 8.00 48,705.00 389,640.00
- Tower Besi Jadi Penempatan Tandon Air Unit 1.00 3,500,000.00 3,500,000.00
- Tandon Air 1200 Liter Buah 1.00 2,200,000.00 2,200,000.00
- Pompa Air Sumersible Unit 1.00 1,500,000.00 1,500,000.00

Pekerjaan Instalasi Air Kotor


- Pekerjaan Pemasangan Instalasi Air Kotor Pipa PVC AW 3" M' 4.00 128,576.00 514,304.00
- Pekerjaan Pemasangan Instalasi Air Kotor Pipa PVC AW4" M' 8.00 129,951.00 1,039,608.00
- Pekerjaan Bak Cuci Piring Stainles Steel Buah 1.00 371,761.00 371,761.00
- Pekerjaan Septi Tanck dan Resapan Buah 1.00 1,500,000.00 1,500,000.00

Pekerjaan Sanitair
- Pemasangan Closed Duduk Monoblock Lengkap Asesorisnya Unit 2.00 2,889,813.00 5,779,626.00
- Pemasangan Kran 1/2" Buah 2.00 135,000.00 270,000.00
- Pemasangan Wastafel Buah 1.00 950,248.00 950,248.00
- Pekerjaan Pemasangan Floor Drain Buah 2.00 33,720.00 67,440.00
- Pekerjaan Bak Air 8 M3 Unit 1.00 1,800,000.00 1,800,000.00
- Penutup Bak Air Manhole 50 x 50 cm Unit 1.00 300,000.00 300,000.00
- Pemasangan Jet/ Sower Buah 2.00 350,000.00 700,000.00
- Pemasangan Perlengkapan Kamar Mandi Buah 2.00 150,000.00 300,000.00

Jumlah Harga Pekerjaan Rp 21,788,471.00


X PEKERJAAN INSTALASI LISTRIK
- Pemasangan Meteran Listrik PLN 2300 KWA Unit 1.00 3,500,000.00 3,500,000.00
- Pemasangan 1 MCB Unit 1.00 70,000.00 70,000.00
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6 = 4x5
- Pasangan Titik Instalasi Bh 18.00 85,910.00 1,546,380.00
- Pasang Lampu LED Dwonlight Tutup 23 WATT Bh 10.00 105,000.00 1,050,000.00
- Pasang Lampu LED Dwonlight Tutup 18 WATT Bh 8.00 95,000.00 760,000.00
- Pasang Saklar Tunggal Bh 5.00 20,000.00 100,000.00
- Pasang Saklar Ganda Set 4.00 22,000.00 88,000.00
- Stop Kontak Dinding Set 8.00 17,500.00 140,000.00
Jumlah Harga Pekerjaan Rp 7,254,380.00
XI PEKERJAAN PENGECETAN
- Take Oil M2 45.02 27,753.00 1,249,551.07
- Cat Kayu Besi, Dll M2 15.62 48,783.00 761,775.81
- Cat Tembok M2 203.52 32,523.00 6,619,169.66
- Cat Plafond M2 84.42 32,523.00 2,745,507.10
Jumlah Harga Pekerjaan Rp 11,376,003.65
XII PEKERJAAN LAIN - LAIN
- Pembersihan Kembali Ls 1.00 200,000.00 200,000.00
- Pekerjaan Tiang Kolom Teras 25 x 25 cm Unit 2.00 600,000.00 1,200,000.00
- Pekerjaan Finishing Siar Dinding Expose M2 5.40 19,502.00 105,310.80
Jumlah Harga Pekerjaan Rp 1,505,310.80
ANALISA PEKERJAAN
A.2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.1000 78,000 7,800.00
Tukang Kayu L.02.04 OH 0.1000 85,000 8,500.00
Kepala Tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0050 95,000 475.00
JUMLAH TENAGA KERJA 17,675.00
B BAHAN -
Kayu balok 5/7 m3 0.1200 2,127,500 255,300.00
Paku 2”-3” Kg 0.0200 10,000 200.00
Kayu papan 3/20 m3 0.0070 2,185,000 15,295.00
JUMLAH HARGA BAHAN 298,345.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 302,245.00
E Overhead & Profit 15% 10% 30,224.50
F Harga Satuan Pekerjaan (D+E) - 332,469.00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.7500 78,000 58,500.00
Mandor L.04.01 OH 0.0250 95,000 2,375.00
JUMLAH TENAGA KERJA 60,875.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 60,875.00
E Overhead & Profit 15% 10% 6,087.50
F Harga Satuan Pekerjaan (D+E) - 66,962.00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedalam 1 M


Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.2500 78,000 19,500.00
Mandor L.04.01 OH 0.0250 95,000 2,375.00
JUMLAH TENAGA KERJA 21,875.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 21,875.00
E Overhead & Profit 15% 10% 2,187.50
F Harga Satuan Pekerjaan (D+E) - 24,062.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.3000 78,000 23,400.00
Mandor L.04.01 OH 0.0100 95,000 950.00
JUMLAH TENAGA KERJA 24,350.00
B BAHAN - -
Pasir urug M3 1.2000 276,958 332,349.85
JUMLAH HARGA BAHAN 332,349.85
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 356,699.85
E Overhead & Profit 15% 10% 35,669.99
F Harga Satuan Pekerjaan (D+E) - 392,369.00

A.2.3.1.14. Pengurugan 1 m3 sirtu padat


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.2500 78,000 19,500.00
Mandor L.04.01 OH 0.0250 95,000 2,375.00
JUMLAH TENAGA KERJA 21,875.00
B BAHAN - -
Sirtu m3 1.2000 121,722 146,066.09
JUMLAH HARGA BAHAN 146,066.09
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 167,941.09
E Overhead & Profit 15% 10% 16,794.11
F Harga Satuan Pekerjaan (D+E) - 184,735.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.3. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.5000 78,000 117,000.00
Tukang Batu L.02.03 OH 0.7500 85,000 63,750.00
Kepala Tukang L.03.01 OH 0.0750 90,000 6,750.00
Mandor L.04.01 OH 0.0750 95,000 7,125.00
JUMLAH TENAGA KERJA 194,625.00
B BAHAN - -
Batu belah m3 1.2000 524,997 629,996.11
Semen portland Kg 136.0000 1,296 176,281.51
Pasir Pasang m3 0.5440 276,958 150,665.27
JUMLAH HARGA BAHAN 956,942.88
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,151,567.88
E Overhead & Profit 15% 10% 115,156.79
F Harga Satuan Pekerjaan (D+E) - 1,266,724.00

A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping)

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.7800 78,000 60,840.00
Tukang Batu L.02.03 OH 0.3900 85,000 33,150.00
Kepala Tukang L.03.01 OH 0.0390 90,000 3,510.00
Mandor L.04.01 OH 0.0390 95,000 3,705.00
JUMLAH TENAGA KERJA 101,205.00
B BAHAN
Batu belah m3 1.2000 524,997 629,996.11
Pasir urug m3 0.4320 276,958 119,645.95
JUMLAH HARGA BAHAN 749,642.05
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 850,847.05
E Overhead & Profit 15% 10% 85,084.71
F Harga Satuan Pekerjaan (D+E) - 935,931.00

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.6500 78,000 128,700.00
Tukang Batu L.02.03 OH 0.2750 85,000 23,375.00
Kepala Tukang L.03.01 OH 0.0280 90,000 2,520.00
Mandor L.04.01 OH 0.0830 95,000 7,885.00
JUMLAH TENAGA KERJA 162,480.00
B BAHAN
Semen portland kg 247.0000 1,296 320,158.33
Pasir Beton kg 869.0000 198 171,911.92
Kerikil (Maks 30 mm) kg 999.0000 242 241,949.08
Air Liter 215.0000 25 5,375.00
JUMLAH HARGA BAHAN 739,394.32
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 901,874.32
E Overhead & Profit 15% 10% 90,187.43
F Harga Satuan Pekerjaan (D+E) - 992,061.00

A.4.1.1.2 Membuat 1 m3 beton mutu f’= 9,8 MPa (K 125)

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.6500 78,000 128,700.00
Tukang Batu L.02.03 OH 0.2750 85,000 23,375.00
Kepala Tukang L.03.01 OH 0.0280 90,000 2,520.00
Mandor L.04.01 OH 0.0830 95,000 7,885.00
JUMLAH TENAGA KERJA 162,480.00
B BAHAN
Semen portland kg 276.0000 1,296.19 357,747.77
Pasir Beton kg 828.0000 197.83 163,801.00
Kerikil (Maks 30 mm) kg 1012.0000 242.19 245,097.56
Air Liter 215.0000 25.00 5,375.00
JUMLAH HARGA BAHAN 772,021.33
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 934,501.33
E Overhead & Profit 15% 10% 93,450.13
F Harga Satuan Pekerjaan (D+E) - 1,027,951.00

A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.2000 78,000 93,600.00
Tukang Batu L.02.03 OH 0.2000 85,000 17,000.00
Kepala Tukang L.03.01 OH 0.0200 90,000 1,800.00
Mandor L.04.01 OH 0.0600 95,000 5,700.00
JUMLAH TENAGA KERJA 118,100.00
B BAHAN
Semen portland kg 230.0000 1,296 298,123.14
Pasir Beton kg 893.0000 198 176,659.77
Kerikil (Maks 30 mm) kg 1027.0000 242 248,730.43
Air Liter 200.0000 25 5,000.00
JUMLAH HARGA BAHAN 728,513.34
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 846,613.34
E Overhead & Profit 15% 10% 84,661.33
F Harga Satuan Pekerjaan (D+E) - 931,274.00

A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.0700 78,000 5,460.00
Tukang Besi L.02.05 OH 0.0700 85,000 5,950.00
Kepala Tukang L.03.01 OH 0.0070 90,000 630.00
Mandor L.04.01 OH 0.0040 95,000 380.00
JUMLAH TENAGA KERJA 12,420.00
B BAHAN
Besi beton (polos/ulir) kg 10.5000 19,350 203,176.91
Kawat beton kg 0.1500 20,125 3,018.75
JUMLAH HARGA BAHAN 206,195.66
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 218,615.66
E Overhead & Profit 15% 10% 21,861.57
F Harga Satuan Pekerjaan (D+E) - 240,477.00

A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.5200 78,000 40,560.00
Tukang Kayu L.02.04 OH 0.2600 85,000 22,100.00
Kepala Tukang L.03.01 OH 0.0260 90,000 2,340.00
Mandor L.04.01 OH 0.0260 95,000 2,470.00
JUMLAH TENAGA KERJA 67,470.00
B BAHAN
Kayu kelas III m3 0.0450 2,127,500 95,737.50
Paku 5 - 10 cm kg 0.3000 15,000 4,500.00
Minyak bekisting Liter 0.1000 20,125 2,012.50
JUMLAH HARGA BAHAN 102,250.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 169,720.00
E Overhead & Profit 15% 10% 16,972.00
F Harga Satuan Pekerjaan (D+E) - 186,692.00

A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.6600 78,000 51,480.00
Tukang Kayu L.02.04 OH 0.3300 85,000 28,050.00
Kepala Tukang L.03.01 OH 0.0330 90,000 2,970.00
Mandor L.04.01 OH 0.0330 95,000 3,135.00
JUMLAH TENAGA KERJA 85,635.00
B BAHAN
Kayu kelas III m3 0.0400 2,127,500 85,100.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0150 3,047,500 45,712.50
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 2.0000 55,000 110,000.00
JUMLAH HARGA BAHAN 301,150.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 386,785.00
E Overhead & Profit 15% 10% 38,678.50
F Harga Satuan Pekerjaan (D+E) - 425,463.00

A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.1800 78,000 14,040.00
Tukang batu L.02.03 OH 0.0200 85,000 1,700.00
Tukang kayu L.02.04 OH 0.0200 85,000 1,700.00
Tukang besi L.02.05 OH 0.0200 85,000 1,700.00
Kepala tukang L.03.01 OH 0.0060 90,000 540.00
Mandor L.04.01 OH 0.0090 95,000 855.00
JUMLAH TENAGA KERJA 20,535.00
B BAHAN
Kayu kelas III m3 0.0020 2,127,500 4,255.00
Paku Biasa kg 0.0100 17,250 172.50
Minyak bekisting Liter 1.2000 20,125 24,150.00
Besi beton (polos/ulir) kg 3.0000 19,350 58,050.55
Kawat beton kg 0.4500 19,550 8,797.50
Semen portland kg 4.0000 1,296 5,184.75
Pasir Beton m3 0.0060 276,958 1,661.75
Kerikil m3 0.0090 326,958 2,942.62
JUMLAH HARGA BAHAN 105,214.67
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 125,749.67
E Overhead & Profit 15% 10% 12,574.97
F Harga Satuan Pekerjaan (D+E) - 138,324.00

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2970 78,000 23,166.00
Tukang batu L.02.03 OH 0.0330 85,000 2,805.00
Tukang kayu L.02.04 OH 0.0330 85,000 2,805.00
Tukang besi L.02.05 OH 0.0330 85,000 2,805.00
Kepala tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0150 95,000 1,425.00
JUMLAH TENAGA KERJA 33,906.00
B BAHAN
Kayu kelas III m3 0.0030 2,127,500 6,382.50
Paku Biasa kg 0.0200 17,250 345.00
Minyak bekisting Liter 1.2000 20,125 24,150.00
Besi beton (polos/ulir) kg 3.6000 19,350 69,660.65
Kawat beton kg 0.0500 19,550 977.50
Semen portland kg 5.5000 1,296 7,129.03
Pasir Beton m3 0.0090 276,958 2,492.62
Kerikil m3 0.0150 326,958 4,904.37
JUMLAH HARGA BAHAN 116,041.68
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 149,947.68
E Overhead & Profit 15% 10% 14,994.77
F Harga Satuan Pekerjaan (D+E) - 164,942.00

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.0430 -
Tukang Alumunium L.02.02 OH 0.0430 -
Kepala tukang L.03.01 OH 0.0043 -
Mandor L.04.01 OH 0.0021 -
JUMLAH TENAGA KERJA -
B BAHAN
Profil alluminium m 1.1000 -
Skrup fixer buah 2.0000 -
Sealant Tube 0.0600 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.4.2.1.21. Pemasangan 1 m2 Rangka Baja Ringan Reng 58 x 30 x 600 mm, untuk Plafon
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3500 78,000 27,300.00
Tukang Besi L.02.05 OH 0.3500 85,000 29,750.00
Kepala Tukang L.03.01 OH 0.0350 90,000 3,150.00
Mandor L.04.01 OH 0.0180 95,000 1,710.00
JUMLAH TENAGA KERJA 61,910.00
B BAHAN
Pipa Kotak Baja Ringan 2 x 4 M1 1.0000 5,833 5,833.33
Assesoris (perkuatan, las dll) Ls 1.0000 15,000 15,000.00
JUMLAH HARGA BAHAN 20,833.33
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 82,743.33
E Overhead & Profit 15% 10% 8,274.33
F Harga Satuan Pekerjaan (D+E) - 91,017.00

A.4.2.1.24. Pemasangan 1 M2 PASANG KUDA-KUDA BAJA RINGAN + RENG UNTUK ATAP GENTENG BIASA/METAL
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2000 78,000 15,600.00
Tukang Besi L.02.05 OH 0.4500 85,000 38,250.00
Kepala Tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0500 95,000 4,750.00
JUMLAH TENAGA KERJA 59,500.00
B BAHAN
Baja ringan canai dingin C75 M' 4.7200 20,852 98,421.50
Baut (Srew driver) bh 28.0000 450 12,600.00
Dynabol dia 12 x 120 mm bh 2.0000 500 1,000.00
Reng CanalDingin M' 6.2000 5,833 36,166.67
Talang / Jurai Canai Dingin M' 0.1240 52,000 6,448.00
JUMLAH HARGA BAHAN 154,636.17
C PERALATAN
Alat Rangka Atap Baja Canai Dingin 0.1000 15,463.62
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 221,867.98
E Overhead & Profit 15% 10% 22,186.80
F Harga Satuan Pekerjaan (D+E) - 244,054.00

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.3. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.6000 78,000 46,800.00
Tukang Batu L.02.03 OH 0.2000 85,000 17,000.00
Kepala Tukang L.03.01 OH 0.0200 90,000 1,800.00
Mandor L.04.01 OH 0.0300 95,000 2,850.00
JUMLAH TENAGA KERJA 68,450.00
B BAHAN
Bata merah m3 140.0000 978 136,850.00
Semen portland Kg 26.5500 1,296 34,413.78
Pasir Pasang m3 0.0930 276,958 25,757.11
JUMLAH HARGA BAHAN 197,020.89
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 265,470.89
E Overhead & Profit 15% 10% 26,547.09
F Harga Satuan Pekerjaan (D+E) - 292,017.00

A.4.4.1.23 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :4PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.3000 78,000 23,400.00
Tukang Batu L.02.03 OH 0.1000 85,000 8,500.00
Kepala Tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0150 95,000 1,425.00
JUMLAH TENAGA KERJA 34,225.00
B BAHAN
Bata berongga m3 30.0000 25,000 750,000.00
Semen portland Kg 11.0000 1,296 14,258.06
Pasir Pasang m3 0.0350 276,958 9,693.54
JUMLAH HARGA BAHAN 773,951.60
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 808,176.60
E Overhead & Profit 15% 10% 80,817.66
F Harga Satuan Pekerjaan (D+E) - 888,994.00

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 78,000 23,400.00
Tukang Batu L.02.03 OH 0.1500 85,000 12,750.00
Kepala Tukang L.03.01 OH 0.0150 90,000 1,350.00
Mandor L.04.01 OH 0.0150 95,000 1,425.00
JUMLAH TENAGA KERJA 38,925.00
B BAHAN
Semen portland Kg 7.7760 1,296 10,079.15
Pasir Pasang m3 0.0230 276,958 6,370.04
JUMLAH HARGA BAHAN 16,449.19
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 55,374.19
E Overhead & Profit 15% 10% 5,537.42
F Harga Satuan Pekerjaan (D+E) - 60,911.00

A.4.4.2.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 78,000 23,400.00
Tukang Batu L.02.03 OH 0.1500 85,000 12,750.00
Kepala Tukang L.03.01 OH 0.0150 90,000 1,350.00
Mandor L.04.01 OH 0.0150 95,000 1,425.00
JUMLAH TENAGA KERJA 38,925.00
B BAHAN
Semen portland Kg 5.1840 1,296 6,719.44
Pasir Pasang m3 0.0260 276,958 7,200.91
JUMLAH HARGA BAHAN 13,920.35
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 52,845.35
E Overhead & Profit 15% 10% 5,284.53
F Harga Satuan Pekerjaan (D+E) - 58,129.00

A.4.4.2.25. Pemasangan 1 m2 finishing siar pasangan conblock ekspose


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.0700 78,000 5,460.00
Tukang Batu L.02.03 OH 0.0350 85,000 2,975.00
Kepala Tukang L.03.01 OH 0.0040 90,000 360.00
Mandor L.04.01 OH 0.0040 95,000 380.00
JUMLAH TENAGA KERJA 9,175.00
B BAHAN
Semen portland Kg 6.6000 1,296 8,554.84
JUMLAH HARGA BAHAN 8,554.84
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 17,729.84
E Overhead & Profit 15% 10% 1,772.98
F Harga Satuan Pekerjaan (D+E) - 19,502.00

A.4.4.2.27. Pemasangan 1 m2 acian.


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 78,000 15,600.00
Tukang Batu L.02.03 OH 0.1000 85,000 8,500.00
Kepala Tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0100 95,000 950.00
JUMLAH TENAGA KERJA 25,950.00
B BAHAN
Semen portland Kg 3.2500 1,296 4,212.61
JUMLAH HARGA BAHAN 4,212.61
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 30,162.61
E Overhead & Profit 15% 10% 3,016.26
F Harga Satuan Pekerjaan (D+E) - 33,178.00

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


A.4.4.3.1. Pemasangan 1m2 lantai Keramik ukuran 40cm x40cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2400 78,000 18,720.00
Tukang Batu L.02.03 OH 0.1200 85,000 10,200.00
Kepala tukang L.03.01 OH 0.0120 90,000 1,080.00
Mandor L.04.01 OH 0.0120 95,000 1,140.00
JUMLAH TENAGA KERJA 31,140.00
B BAHAN
ubin PC abu-abu ukuran 40cm x40cm Bh 6.0000 16,184 97,104.66
Semen portland kg 9.8000 1,296 12,702.64
Pasir Pasang M3 0.0450 276,958 12,463.12
JUMLAH HARGA BAHAN 122,270.41
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 153,410.41
E Overhead & Profit 15% 10% 15,341.04
F Harga Satuan Pekerjaan (D+E) - 168,751.00

A.4.4.3.3. Pemasangan 1m2 lantai ubin PC abu-abu ukuran 25cm x25 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2400 78,000 18,720.00
Tukang Batu L.02.03 OH 0.1200 85,000 10,200.00
Kepala tukang L.03.01 OH 0.0120 90,000 1,080.00
Mandor L.04.01 OH 0.0120 95,000 1,140.00
JUMLAH TENAGA KERJA 31,140.00
B BAHAN
ubin PC abu-abu ukuran 25cm x25 cm Bh 16.5000 69,777 1,151,319.29
Semen portland kg 10.4000 1,296 13,480.35
Pasir Pasang M3 0.0450 276,958 12,463.12
JUMLAH HARGA BAHAN 1,177,262.76
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,208,402.76
E Overhead & Profit 10% 10% 120,840.28
F Harga Satuan Pekerjaan (D+E) - 1,329,243.00

A.4.4.3.13. Pemasangan 1m2 lantai Granit ukuran 60cm x60cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.1400 78,000 10,920.00
Tukang Batu L.02.03 OH 0.1000 85,000 8,500.00
Kepala tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0100 95,000 950.00
JUMLAH TENAGA KERJA 21,270.00
B BAHAN
Granit 60cm x60cm Bh 4.0000 46,964 187,857.76
Semen portland kg 6.6000 1,296 8,554.84
Semen Warna Kg 1.5000 2,125 3,187.50
Pasir Pasang M3 0.0350 276,958 9,693.54
JUMLAH HARGA BAHAN 209,293.63
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 230,563.63
E Overhead & Profit 10% 10% 23,056.36
F Harga Satuan Pekerjaan (D+E) - 253,619.00

A.4.4.3.18. Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 10 cm x 60cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.0300 78,000 2,340.00
Tukang Batu L.02.03 OH 0.0300 85,000 2,550.00
Kepala tukang L.03.01 OH 0.0030 90,000 270.00
Mandor L.04.01 OH 0.0015 95,000 142.50
JUMLAH TENAGA KERJA 5,302.50
B BAHAN
Plint Keramik ukuran 10 cm x 60cm Bh 1.8000 31,277 56,298.47
Semen portland kg 1.2400 1,296 1,607.27
Pasir pasang M3 0.0030 276,958 830.87
JUMLAH HARGA BAHAN 58,736.61
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 64,039.11
E Overhead & Profit 15% 10% 6,403.91
F Harga Satuan Pekerjaan (D+E) - 70,443.00

A.4.4.3.54. Pemasangan 1 m2 dinding keramik 25 cm x 40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.9000 78,000 70,200.00
Tukang Batu L.02.03 OH 0.4500 85,000 38,250.00
Kepala tukang L.03.01 OH 0.0450 90,000 4,050.00
Mandor L.04.01 OH 0.0450 95,000 4,275.00
JUMLAH TENAGA KERJA 116,775.00
B BAHAN
Keramik Dinding 25 cm x 40 cm Bh 9.0000 10,899 98,094.33
Semen portland Kg 9.3000 1,296 12,054.54
Pasir Pasang M3 0.0180 276,958 4,985.25
Semen Warna Kg 1.9400 2,125 4,122.50
JUMLAH HARGA BAHAN 119,256.62
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 236,031.62
E Overhead & Profit 15% 10% 23,603.16
F Harga Satuan Pekerjaan (D+E) - 259,634.00

A.4.4.3.65. Pemasangan 1 m2 paving block natural tebal 8 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2500 -
Tukang Kayu L.02.04 OH 0.2500 -
Kepala tukang L.03.01 OH 0.0250 -
Mandor L.04.01 OH 0.0025 -
JUMLAH TENAGA KERJA -
B BAHAN
Paving block 8 cm natural M2 1.01 -
Pasir beton M3 0.07 -
JUMLAH HARGA BAHAN -
C PERALATAN -
Peralatan Kerja Paving Blok % 0.1000 - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.4.4.3.68. Pemasangan 1 M2 Aluminium Composite Panel


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.1500 -
Tukang Besi L.02.05 OH 0.0750 -
Kepala Tukang L.03.01 OH 0.0080 -
Mandor L.04.01 OH 0.0080 -
JUMLAH TENAGA KERJA -
B BAHAN
Aluminium Composite Panel Lbr 0.3650 -
Screw bh 20.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.1000 78,000 7,800.00
Tukang kayu L.02.04 OH 0.1500 85,000 12,750.00
Kepala tukang L.03.01 OH 0.0200 90,000 1,800.00
Mandor L.04.01 OH 0.0200 95,000 1,900.00
JUMLAH TENAGA KERJA 24,250.00
B BAHAN
Gypsum board 9 mm (1200 x 2400 mm) Lembar 0.5560 68,117.38 37,873.27
Cornice A Plus Kg 1.2000 3,500 4,200.00
Paku skrup kg 0.1100 20,000 2,200.00
JUMLAH HARGA BAHAN 44,273.27
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 68,523.27
E Overhead & Profit 15% 10% 6,852.33
F Harga Satuan Pekerjaan (D+E) - 75,375.00

A.4.5.1.9. Pemasangan 1 m’ list langit-langit Gypsum


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.0500 78,000 3,900.00
Tukang Kayu L.02.04 OH 0.0500 85,000 4,250.00
Kepala tukang L.03.01 OH 0.0050 90,000 450.00
Mandor L.04.01 OH 0.0030 95,000 285.00
JUMLAH TENAGA KERJA 8,885.00
B BAHAN
List Plafond Gypsum m 1.0500 8,625 9,056.25
Paku Biasa kg 0.0100 17,250 172.50
JUMLAH HARGA BAHAN 9,228.75
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 18,113.75
E Overhead & Profit 15% 10% 1,811.38
F Harga Satuan Pekerjaan (D+E) - 19,925.00
A.4.5.1.10 Pemasangan 1 m2 Rangka langit-langit besi hollow 40.40
Lihat pada kelompok Pekerjaan Besi dan Alumunium ( A.9.21)

A.4.5.1.10. Pemasangan 1 m2 Plafond PVC


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1500 -
Tukang Kayu L.02.04 OH 0.2500 -
Kepala tukang L.03.01 OH 0.0250 -
Mandor L.04.01 OH 0.0750 -
JUMLAH TENAGA KERJA -
B BAHAN
Plafond PVC (setara Shunda Plafon, Flat Gloss Half Si m2 1.0500 -
Screw bh 18.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.33. Pemasangan 1 m2 genteng Multiroof
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 78,000 15,600.00
Tukang Kayu L.02.04 OH 0.1000 85,000 8,500.00
Kepala tukang L.03.01 OH 0.0100 90,000 900.00
Mandor L.04.01 OH 0.0010 95,000 95.00
JUMLAH TENAGA KERJA 25,095.00
B BAHAN
Genteng multiroof M2 1.0000 81,403 81,403.49
Sekrup Kg 0.2000 600 120.00
JUMLAH HARGA BAHAN 81,523.49
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 106,618.49
E Overhead & Profit 15% 10% 10,661.85
F Harga Satuan Pekerjaan (D+E) - 117,280.00

A.4.5.2.37. Pemasangan 1 m’ nok genteng metal


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2500 -
Tukang Kayu L.02.04 OH 0.1500 -
Kepala tukang L.03.01 OH 0.0150 -
Mandor L.04.01 OH 0.0130 -
JUMLAH TENAGA KERJA -
B BAHAN
Nok genteng metal Bh 1.1000 -
Paku Biasa Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.4.6.1 HARGA SATUAN PEKERJAAN KAYU


A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 7.0000 78,000 546,000.00
Tukang kayu L.02.04 OH 21.0000 85,000 1,785,000.00
Kepala tukang L.03.01 OH 2.1000 90,000 189,000.00
Mandor L.04.01 OH 0.3500 95,000 33,250.00
JUMLAH TENAGA KERJA 2,553,250.00
B BAHAN
Balok kayu m3 1.1000 6,621,192 7,283,311.59
Paku Biasa Kg 1.2500 17,000 21,250.00
Lem Kayu/Karet Kg 1.0000 57,500 57,500.00
JUMLAH HARGA BAHAN 7,362,061.59
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 9,915,311.59
E Overhead & Profit 15% 10% 991,531.16
F Harga Satuan Pekerjaan (D+E) - 10,906,842.00

A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 6.0000 78,000 468,000.00
Tukang kayu L.02.04 OH 18.0000 85,000 1,530,000.00
Kepala tukang L.03.01 OH 1.8000 90,000 162,000.00
Mandor L.04.01 OH 0.3000 95,000 28,500.00
JUMLAH TENAGA KERJA 2,188,500.00
B BAHAN
Balok kayu m3 1.2000 3,047,500 3,657,000.00
Paku Biasa Kg 1.2500 17,000 21,250.00
Lem Kayu/Karet Kg 1.0000 57,500 57,500.00
JUMLAH HARGA BAHAN 3,735,750.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 5,924,250.00
E Overhead & Profit 15% 10% 592,425.00
F Harga Satuan Pekerjaan (D+E) - 6,516,675.00

A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.0000 78,000 78,000.00
Tukang kayu L.02.04 OH 3.0000 85,000 255,000.00
Kepala tukang L.03.01 OH 0.3000 90,000 27,000.00
Mandor L.04.01 OH 0.0500 95,000 4,750.00
JUMLAH TENAGA KERJA 364,750.00
B BAHAN
Kayu Papan m3 0.0350 7,650,000 267,750.00
Lem Kayu/Karet Kg 0.5000 57,500 28,750.00
JUMLAH HARGA BAHAN 296,500.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 661,250.00
E Overhead & Profit 15% 10% 66,125.00
F Harga Satuan Pekerjaan (D+E) - 727,375.00

A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.8000 78,000 62,400.00
Tukang kayu L.02.04 OH 2.4000 85,000 204,000.00
Kepala tukang L.03.01 OH 0.2400 90,000 21,600.00
Mandor L.04.01 OH 0.0400 95,000 3,800.00
JUMLAH TENAGA KERJA 291,800.00
B BAHAN
kayu Papan m3 0.0340 4,550,000 154,700.00
Lem Kayu/Karet Kg 0.3000 57,500 17,250.00
JUMLAH HARGA BAHAN 171,950.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 463,750.00
E Overhead & Profit 15% 10% 46,375.00
F Harga Satuan Pekerjaan (D+E) - 510,125.00

A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.0000 78,000 78,000.00
Tukang kayu L.02.04 OH 3.0000 85,000 255,000.00
Kepala tukang L.03.01 OH 0.3000 90,000 27,000.00
Mandor L.04.01 OH 0.0500 95,000 4,750.00
JUMLAH TENAGA KERJA 364,750.00
B BAHAN
kayu Papan m3 0.0640 4,550,000 291,200.00
Lem Kayu/Karet Kg 0.5000 57,500 28,750.00
JUMLAH HARGA BAHAN 319,950.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 684,700.00
E Overhead & Profit 15% 10% 68,470.00
F Harga Satuan Pekerjaan (D+E) - 753,170.00

A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 4.000 78,000 312,000.00
Tukang kayu L.02.04 OH 12.000 85,000 1,020,000.00
Kepala tukang L.03.01 OH 1.200 90,000 108,000.00
Mandor L.04.01 OH 0.2 95,000 19,000.00
JUMLAH TENAGA KERJA 1,459,000.00
B BAHAN
Balok kayu m3 1.100 2,127,500 2,340,250.00
Besi strip kg 15.000 161,000 2,415,000.00
Paku Biasa kg 5.600 17,000 95,200.00
JUMLAH HARGA BAHAN 4,850,450.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 6,309,450.00
E Overhead & Profit 15% 10% 630,945.00
F Harga Satuan Pekerjaan (D+E) - 6,940,395.00

A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 6.700 78,000 522,600.00
Tukang kayu L.02.04 OH 20.100 85,000 1,708,500.00
Kepala tukang L.03.01 OH 2.010 90,000 180,900.00
Mandor L.04.01 OH 0,335 95,000 31,825.00
JUMLAH TENAGA KERJA 2,443,825.00
B BAHAN
Balok kayu m3 1.100 3,047,500 3,352,250.00
Besi strip kg 15.000 161,000 2,415,000.00
Paku Biasa kg 3.000 17,000 51,000.00
JUMLAH HARGA BAHAN 5,818,250.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 8,262,075.00
E Overhead & Profit 15% 10% 826,207.50
F Harga Satuan Pekerjaan (D+E) - 9,088,282.00

A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.2 78,000 15,600.00
Tukang kayu L.02.04 OH 0.3 85,000 25,500.00
Kepala tukang L.03.01 OH 0.03 90,000 2,700.00
Mandor L.04.01 OH 0.01 95,000 950.00
JUMLAH TENAGA KERJA 44,750.00
B BAHAN
Kayu 5/7 m3 0.0163 3,250,000 52,975.00
Paku Biasa kg 0.25 15,000 3,750.00
JUMLAH HARGA BAHAN 56,725.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 101,475.00
E Overhead & Profit 15% 10% 10,147.50
F Harga Satuan Pekerjaan (D+E) - 111,622.00

A.4.6.1.21. Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.050 78,000 3,900.00
Tukang kayu L.02.04 OH 0.050 85,000 4,250.00
Kepala tukang L.03.01 OH 0.010 90,000 900.00
Mandor L.04.01 OH 0.005 95,000 475.00
JUMLAH TENAGA KERJA 9,525.00
B BAHAN
Kayu Papan m3 0.0108 4,550,000 49,140.00
Paku Biasa kg 0.1 15,000 1,500.00
JUMLAH HARGA BAHAN 50,640.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 60,165.00
E Overhead & Profit 15% 10% 6,016.50
F Harga Satuan Pekerjaan (D+E) - 66,181.00

A.4.6.1.22. Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.1 78,000 7,800.00
Tukang kayu L.02.04 OH 0.2 85,000 17,000.00
Kepala tukang L.03.01 OH 0.02 90,000 1,800.00
Mandor L.04.01 OH 0.005 95,000 475.00
JUMLAH TENAGA KERJA 27,075.00
B BAHAN
Kayu Papan m3 0.011 4,550,000 50,050.00
Paku Biasa kg 0.05 15,000 750.00
JUMLAH HARGA BAHAN 50,800.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 77,875.00
E Overhead & Profit 15% 10% 7,787.50
F Harga Satuan Pekerjaan (D+E) - 85,662.00

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA


A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.010 78,000 780.00
Tukang kayu L.02.04 OH 0.500 85,000 42,500.00
Kepala tukang L.03.01 OH 0.050 90,000 4,500.00
Mandor L.04.01 OH 0.005 95,000 475.00
JUMLAH TENAGA KERJA 48,255.00
B BAHAN
Kunci tanam biasa Bh 1.000 84,250 84,250.00
JUMLAH HARGA BAHAN 84,250.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 132,505.00
E Overhead & Profit 15% 10% 13,250.50
F Harga Satuan Pekerjaan (D+E) - 145,755.00
A.4.6.2.5. Pemasangan 1 buah engsel pintu
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.015 78,000 1,170.00
Tukang kayu L.02.04 OH 0.150 85,000 12,750.00
Kepala tukang L.03.01 OH 0.015 90,000 1,350.00
Mandor L.04.01 OH 0.001 95,000 76.00
JUMLAH TENAGA KERJA 15,346.00
B BAHAN
Engsel pintu Bh 1.000 39,675 39,675.00
JUMLAH HARGA BAHAN 39,675.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 55,021.00
E Overhead & Profit 15% 10% 5,502.10
F Harga Satuan Pekerjaan (D+E) - 60,523.00

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.010 78,000 780.00
Tukang kayu L.02.04 OH 0.100 85,000 8,500.00
Kepala tukang L.03.01 OH 0.010 90,000 900.00
Mandor L.04.01 OH 0.001 95,000 47.50
JUMLAH TENAGA KERJA 10,227.50
B BAHAN
Engsel kupu-kupu Bh 1.000 23,000 23,000.00
JUMLAH HARGA BAHAN 23,000.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 33,227.50
E Overhead & Profit 15% 10% 3,322.75
F Harga Satuan Pekerjaan (D+E) - 36,550.00

A.4.6.2.7. Pemasangan 1 buah engsel angin


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
A TENAGA - -
Pekerja L.01.01 OH 0.100 78,000 7,800.00
Tukang kayu L.02.04 OH 0.200 85,000 17,000.00
Kepala tukang L.03.01 OH 0.020 90,000 1,800.00
Mandor L.04.01 OH 0.001 95,000 47.50
JUMLAH TENAGA KERJA 26,647.50
B BAHAN
Engsel angin Bh 1.000 17,250 17,250.00
JUMLAH HARGA BAHAN 17,250.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 43,897.50
E Overhead & Profit 15% 10% 4,389.75
F Harga Satuan Pekerjaan (D+E) - 48,287.00

A.4.6.2.8. Pemasangan 1 buah spring knip


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
A TENAGA - -
Pekerja L.01.01 OH 0.015 78,000 1,170.00
Tukang kayu L.02.04 OH 0.150 85,000 12,750.00
Kepala tukang L.03.01 OH 0.015 90,000 1,350.00
Mandor L.04.01 OH 0.008 95,000 760.00
JUMLAH TENAGA KERJA 16,030.00
B BAHAN
Spring knip Bh 1.000 12,000 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 28,030.00
E Overhead & Profit 15% 10% 2,803.00
F Harga Satuan Pekerjaan (D+E) - 30,833.00

A.4.6.2.9. Pemasangan 1 buah kait angin


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.015 78,000 1,170.00
Tukang kayu L.02.04 OH 0.015 85,000 1,275.00
Kepala tukang L.03.01 OH 0.015 90,000 1,350.00
Mandor L.04.01 OH 0.008 95,000 760.00
JUMLAH TENAGA KERJA 4,555.00
B BAHAN
Kait angin Bh 1.000 12,000 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 16,555.00
E Overhead & Profit 10% 10% 1,655.50
F Harga Satuan Pekerjaan (D+E) - 18,210.00

A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.015 78,000 1,170.00
Tukang kayu L.02.04 OH 0.150 85,000 12,750.00
Kepala tukang L.03.01 OH 0.015 90,000 1,350.00
Mandor L.04.01 OH 0.001 95,000 76.00
JUMLAH TENAGA KERJA 15,346.00
B BAHAN
Kaca tebal 5 mm m2 1.100 201,250 221,375.00
SEalant Kg 0.050 20,000 1,000.00
JUMLAH HARGA BAHAN 222,375.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 237,721.00
E Overhead & Profit 15% 10% 23,772.10
F Harga Satuan Pekerjaan (D+E) - 261,493.00

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.070 78,000 5,460.00
Tukang cat L.02.08 OH 0.009 85,000 765.00
Kepala tukang L.03.01 OH 0.006 90,000 540.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 7,050.00
B BAHAN
Cat menie Kg 0.200 34,500 6,900.00
Plamuur Kg 0.150 11,500 1,725.00
Cat dasar Kayu Kg 0.170 50,500 8,585.00
Cat Penutup Kayu Kg 0.260 69,000 17,940.00
Kuas Bh 0.010 20,000 200.00
Pengencer Kg 0.030 31,625 948.75
Ampelas Lbr 0.200 5,000 1,000.00
JUMLAH HARGA BAHAN 37,298.75
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 44,348.75
E Overhead & Profit 15% 10% 4,434.88
F Harga Satuan Pekerjaan (D+E) - 48,783.00

A.4.7.1.6. Pelaburan 1 m2 bidang kayu dengan teak oil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.040 78,000 3,120.00
Tukang cat L.02.08 OH 0.063 85,000 5,355.00
Kepala tukang L.03.01 OH 0.063 90,000 5,670.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 14,430.00
B BAHAN
Teak oil L 0.360 30,000 10,800.00
JUMLAH HARGA BAHAN 10,800.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 25,230.00
E Overhead & Profit 15% 10% 2,523.00
F Harga Satuan Pekerjaan (D+E) - 27,753.00

A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien (Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.040 78,000 3,120.00
Tukang cat L.02.08 OH 0.060 85,000 5,100.00
Kepala tukang L.03.01 OH 0.016 90,000 1,440.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 9,945.00
B BAHAN
Politur L 0.150 50,500 7,575.00
Politur jadi L 0.372 30,000 11,160.00
Ampelas Lbr 2.000 5,000 10,000.00
JUMLAH HARGA BAHAN 28,735.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 38,680.00
E Overhead & Profit 15% 10% 3,868.00
F Harga Satuan Pekerjaan (D+E) - 42,548.00

A.4.7.1.9. Pelaburan 1 m2 bidang kayu dengan vernis


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.160 -
Tukang cat L.02.08 OH 0.160 -
Kepala tukang L.03.01 OH 0.016 -
Mandor L.04.01 OH 0.003 -
JUMLAH TENAGA KERJA -
B BAHAN
Vernis L 0.150 -
Dempul Kg 0.050 -
Ampelas Lbr 0.100 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.020 78,000 1,560.00
Tukang cat L.02.08 OH 0.063 85,000 5,355.00
Kepala tukang L.03.01 OH 0.006 90,000 567.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 7,767.00
B BAHAN
Plamuur Kg 0.100 11,500 1,150.00
Cat dasar Tembok Kg 0.100 50,500 5,050.00
Cat Penutup Tembok Kg 0.260 60,000 15,600.00
JUMLAH HARGA BAHAN 21,800.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 29,567.00
E Overhead & Profit 15% 10% 2,956.70
F Harga Satuan Pekerjaan (D+E) - 32,523.00

A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.020 78,000 1,560.00
Tukang cat L.02.08 OH 0.200 85,000 17,000.00
Kepala tukang L.03.01 OH 0.020 90,000 1,800.00
Mandor L.04.01 OH 0.003 95,000 237.50
JUMLAH TENAGA KERJA 20,597.50
B BAHAN
Menie besi Kg 0.100 34,500 3,450.00
Kuas Bh 0.010 20,000 200.00
JUMLAH HARGA BAHAN 3,650.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 24,247.50
E Overhead & Profit 15% 10% 2,424.75
F Harga Satuan Pekerjaan (D+E) - 26,672.00

A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1. (K3) Pemasangan 1 buah closet duduk/monoblock
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 3.300 78,000 257,400.00
Tukang batu L.02.03 OH 1.100 85,000 93,500.00
Kepala tukang L.03.01 OH 0.010 90,000 900.00
Mandor L.04.01 OH 0.160 95,000 15,200.00
JUMLAH TENAGA KERJA 367,000.00
B BAHAN
Closet duduk Unit 1.000 2,258,747 2,258,747.49
Perlengkapan % 0.060 22,587 1,355.25
JUMLAH HARGA BAHAN 2,281,335 2,260,102.74
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 2,627,102.74
E Overhead & Profit 15% 10% 262,710.27
F Harga Satuan Pekerjaan (D+E) - 2,889,813.00

A.5.1.1 5. (K3) Pemasangan 1 buah wastafel


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.200 78,000 93,600.00
Tukang batu L.02.03 OH 1.450 85,000 123,250.00
Kepala tukang L.03.01 OH 0.150 90,000 13,500.00
Mandor L.04.01 OH 0.060 95,000 5,700.00
JUMLAH TENAGA KERJA 236,050.00
B BAHAN
Wastafel Unit 1.000 550,000 550,000.00
Semen portland Kg 6.000 1,296 7,777.13
Pasir pasang M3 0.010 276,958 2,769.58
Perlengkapan % 12.000 5,605 67,265.60
JUMLAH HARGA BAHAN 627,812.31
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 863,862.31
E Overhead & Profit 15% 10% 86,386.23
F Harga Satuan Pekerjaan (D+E) - 950,248.00

A.5.1.1 8. (K3) Pemasangan 1 buah bak mandi batu bata vol 0,30 m3
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.600 78,000 46,800.00
Tukang batu L.02.03 OH 0.300 85,000 25,500.00
Kepala tukang L.03.01 OH 0.015 90,000 1,350.00
Mandor L.04.01 OH 0.015 95,000 1,425.00
JUMLAH TENAGA KERJA 75,075.00
B BAHAN
Bata merah Buah 5.600 2,883 16,145.24
Semen portland Kg 12.000 1,296 15,554.25
Pasir pasang M3 0.300 276,958 83,087.46
Porselen 11x11 bh 3.600 2,500 9,000.00
Semen warna Kg 0.600 2,125 1,275.00
JUMLAH HARGA BAHAN 125,061.95
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 200,136.95
E Overhead & Profit 15% 10% 20,013.70
F Harga Satuan Pekerjaan (D+E) - 220,150.00

A.5.1.1 11. Pemasangan 1 buah bak beton volume 1 m3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 3.500 -
Tukang batu L.02.03 OH 4.500 -
Kepala tukang L.03.01 OH 0.050 -
Mandor L.04.01 OH 0.018 -
JUMLAH TENAGA KERJA -
B BAHAN
Beton 1:2:3 M3 0.900 1,103,755 993,379.50
Baja tulangan Kg 180.000 -
Kayu bekisting M2 8.000 -
Ubin porselen Bh 500.000 -
Perlengkapan % 10.000 9,934 99,337.95
JUMLAH HARGA BAHAN 1,092,717.45
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,092,717.45
E Overhead & Profit 15% 10% 109,271.75
F Harga Satuan Pekerjaan (D+E) - 1,201,989.00

A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.030 78,000 2,340.00
Tukang batu L.02.03 OH 0.300 85,000 25,500.00
Kepala tukang L.03.01 OH 0.030 90,000 2,700.00
Mandor L.04.01 OH 0.015 95,000 1,425.00
JUMLAH TENAGA KERJA 31,965.00
B BAHAN
Bak cuci piring Unit 1.000 250,000 250,000.00
Waterdrain Bh 1.000 56,000 56,000.00
JUMLAH HARGA BAHAN 306,000.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 337,965.00
E Overhead & Profit 15% 10% 33,796.50
F Harga Satuan Pekerjaan (D+E) - 371,761.00

A.5.1.1 14. Pemasangan 1 buah floor drain


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.010 78,000 780.00
Tukang batu L.02.03 OH 0.100 85,000 8,500.00
Kepala tukang L.03.01 OH 0.010 90,000 900.00
Mandor L.04.01 OH 0.005 95,000 475.00
JUMLAH TENAGA KERJA 10,655.00
B BAHAN
Floor drain Unit 1.000 20,000 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 30,655.00
E Overhead & Profit 15% 10% 3,065.50
F Harga Satuan Pekerjaan (D+E) - 33,720.00

A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 3.200 -
Tukang batu L.02.03 OH 1.150 -
Kepala tukang L.03.01 OH 0.011 -
Mandor L.04.01 OH 0.016 -
JUMLAH TENAGA KERJA -
B BAHAN
Bata merah bh 70.000 -
Semen portland Kg 77.000 -
Pasir pasang M3 0.130 -
Pasir beton M3 0.090 -
Kerikil M3 0.020 -
Baja tulangan Kg 2.600 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 17. Pemasangan 1 buah bak kontrol pasangan bata 60cm x60cm tinggi 65 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 3.200 -
Tukang batu L.02.03 OH 1.150 -
Kepala tukang L.03.01 OH 0.011 -
Mandor L.04.01 OH 0.016 -
JUMLAH TENAGA KERJA -
B BAHAN
Bata merah bh 123.000 -
Semen portland Kg 114.000 -
Pasir pasang M3 0.184 -
Pasir beton M3 0.120 -
Kerikil M3 0.033 -
Baja tulangan Kg 4.850 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 18. Pemasangan 1 m’ pipa galvanis diameter ½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.054 -
Tukang batu L.02.03 OH 0.090 -
Kepala tukang L.03.01 OH 0.009 -
Mandor L.04.01 OH 0.027 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa galvanis ½” M 1.200 -
Perlengkapan % 35.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.010 -
Tukang batu L.02.03 OH 0.400 -
Kepala tukang L.03.01 OH 0.040 -
Mandor L.04.01 OH 0.005 -
JUMLAH TENAGA KERJA -
B BAHAN
Kran air M 1.000 -
Sealtape Buah 0.025 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 20. Pemasangan 1 m’ pipa galvanis diameter 3/4”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.054 -
Tukang batu L.02.03 OH 0.090 -
Kepala tukang L.03.01 OH 0.009 -
Mandor L.04.01 OH 0.027 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa galvanis 3/4” M 1.200 -
Perlengkapan % 35.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 21. Pemasangan 1 m’ pipa galvanis diameter 1”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.054 -
Tukang batu L.02.03 OH 0.090 -
Kepala tukang L.03.01 OH 0.009 -
Mandor L.04.01 OH 0.027 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa galvanis 1” M 1.200 -
Perlengkapan % 35.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 22. Pemasangan 1 m’ pipa galvanis diameter 1 ½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.108 -
Tukang batu L.02.03 OH 0.180 -
Kepala tukang L.03.01 OH 0.018 -
Mandor L.04.01 OH 0.005 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa galvanis 11/2” M 1.200 -
Perlengkapan % 35.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 23. Pemasangan 1 m’ pipa galvanis diameter 3”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.135 -
Tukang batu L.02.03 OH 0.225 -
Kepala tukang L.03.01 OH 0.023 -
Mandor L.04.01 OH 0.007 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa galvanis 3” M 1.200 -
Perlengkapan % 35.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 24. Pemasangan 1 m’ pipa galvanis diameter 4”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.135 -
Tukang batu L.02.03 OH 0.225 -
Kepala tukang L.03.01 OH 0.023 -
Mandor L.04.01 OH 0.007 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa galvanis 4” M 1.200 -
Perlengkapan % 35.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 10% -
F Harga Satuan Pekerjaan (D+E) - -

A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.036 78,000 2,808.00
Tukang Pipa L.02.03 OH 0.060 85,000 5,100.00
Kepala tukang L.03.01 OH 0.006 90,000 540.00
Mandor L.04.01 OH 0.002 95,000 190.00
JUMLAH TENAGA KERJA 8,638.00
B BAHAN
Pipa PVC 1/2” M 1.200 23,000 27,600.00
Perlengkapan % 35.000 276 9,660.00
JUMLAH HARGA BAHAN 37,260.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 45,898.00
E Overhead & Profit 15% 10% 4,589.80
F Harga Satuan Pekerjaan (D+E) - 50,487.00

A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.036 78,000 2,808.00
Tukang Pipa L.02.03 OH 0.060 85,000 5,100.00
Kepala tukang L.03.01 OH 0.006 90,000 540.00
Mandor L.04.01 OH 0.002 95,000 190.00
JUMLAH TENAGA KERJA 8,638.00
B BAHAN
Pipa PVC 3/4” M 1.200 22,000 26,400.00
Perlengkapan % 35.000 264 9,240.00
JUMLAH HARGA BAHAN 35,640.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 44,278.00
E Overhead & Profit 15% 10% 4,427.80
F Harga Satuan Pekerjaan (D+E) - 48,705.00

A.5.1.1 27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.036 78,000 2,808.00
Tukang Pipa L.02.03 OH 0.060 85,000 5,100.00
Kepala tukang L.03.01 OH 0.006 90,000 540.00
Mandor L.04.01 OH 0.002 95,000 190.00
JUMLAH TENAGA KERJA 8,638.00
B BAHAN
Pipa PVC 1” M 1.200 45,000 54,000.00
Perlengkapan % 35.000 540 18,900.00
JUMLAH HARGA BAHAN 72,900.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 81,538.00
E Overhead & Profit 15% 10% 8,153.80
F Harga Satuan Pekerjaan (D+E) - 89,691.00

A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 11/2”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.054 78,000 4,212.00
Tukang Pipa L.02.03 OH 0.090 85,000 7,650.00
Kepala tukang L.03.01 OH 0.009 90,000 810.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 12,957.00
B BAHAN
Pipa PVC 11/2” M 1.200 56,500 67,800.00
Perlengkapan % 35.000 678 23,730.00
JUMLAH HARGA BAHAN 91,530.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 104,487.00
E Overhead & Profit 15% 10% 10,448.70
F Harga Satuan Pekerjaan (D+E) - 114,935.00

A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.054 78,000 4,212.00
Tukang Pipa L.02.03 OH 0.090 85,000 7,650.00
Kepala tukang L.03.01 OH 0.009 90,000 810.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 12,957.00
B BAHAN
Pipa PVC 2” M 1.200 78,500 94,200.00
Perlengkapan % 35.000 942 32,970.00
JUMLAH HARGA BAHAN 127,170.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 140,127.00
E Overhead & Profit 15% 10% 14,012.70
F Harga Satuan Pekerjaan (D+E) - 154,139.00

A.5.1.1 30. Pemasangan 1 m’ pipa PVC tipe AW diameter 21/2”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.081 78,000 6,318.00
Tukang Pipa L.02.03 OH 0.135 85,000 11,475.00
Kepala tukang L.03.01 OH 0.014 90,000 1,215.00
Mandor L.04.01 OH 0.004 95,000 380.00
JUMLAH TENAGA KERJA 19,388.00
B BAHAN
Pipa PVC 21/2” M 1.200 80,000 96,000.00
Perlengkapan % 35.000 960 33,600.00
JUMLAH HARGA BAHAN 129,600.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 148,988.00
E Overhead & Profit 15% 10% 14,898.80
F Harga Satuan Pekerjaan (D+E) - 163,886.00

A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.081 78,000 6,318.00
Tukang Pipa L.02.03 OH 0.135 85,000 11,475.00
Kepala tukang L.03.01 OH 0.014 90,000 1,215.00
Mandor L.04.01 OH 0.004 95,000 380.00
JUMLAH TENAGA KERJA 19,388.00
B BAHAN
Pipa PVC 3” M 1.000 97,500 97,500.00
Perlengkapan % 35.000 0.00036 0.01
JUMLAH HARGA BAHAN 97,500.01
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 116,888.01
E Overhead & Profit 15% 10% 11,688.80
F Harga Satuan Pekerjaan (D+E) - 128,576.00

A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.081 78,000 6,318.00
Tukang Pipa L.02.03 OH 0.135 85,000 11,475.00
Kepala tukang L.03.01 OH 0.014 90,000 1,215.00
Mandor L.04.01 OH 0.004 95,000 380.00
JUMLAH TENAGA KERJA 19,388.00
B BAHAN
Pipa PVC 4” M 1.000 98,750 98,750.00
Perlengkapan % 35.000 0.00035 0.01
JUMLAH HARGA BAHAN 98,750.01
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 118,138.01
E Overhead & Profit 15% 10% 11,813.80
F Harga Satuan Pekerjaan (D+E) - 129,951.00

A.5.1.1 33. Pemasangan 1 m’ pipa air limbah jenis pipa tanah


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.080 78,000 6,240.00
Tukang batu L.02.03 OH 0.040 85,000 3,400.00
Kepala tukang L.03.01 OH 0.004 90,000 360.00
Mandor L.04.01 OH 0.004 95,000 380.00
JUMLAH TENAGA KERJA 10,380.00
B BAHAN
Pipa tanah Bh 1.600 -
Semen portland Kg 35.000 -
Pasir pasang M3 0.014 -
Pasir urug M3 0.014 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 10,380.00
E Overhead & Profit 15% 10% 1,038.00
F Harga Satuan Pekerjaan (D+E) - 11,418.00

A.5.1.1 34. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 15 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.060 78,000 4,680.00
Tukang batu L.02.03 OH 0.030 85,000 2,550.00
Kepala tukang L.03.01 OH 0.003 90,000 270.00
Mandor L.04.01 OH 0.003 95,000 285.00
JUMLAH TENAGA KERJA 7,785.00
B BAHAN
Pipa tanah Bh 1.600 -
Semen portland Kg 0.680 -
Pasir pasang M3 0.013 -
Pasir urug M3 0.011 -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 7,785.00
E Overhead & Profit 15% 10% 778.50
F Harga Satuan Pekerjaan (D+E) - 8,563.00

A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)

A TENAGA
Upah % 0.1000 78,000 7,800.00
JUMLAH TENAGA KERJA 7,800.00
B BAHAN
Pipa listrik 5/8” btg 0.3000 10,000 3,000.00
Kabel NYM 3x2,5 mm2 m 2.4000 13,500 32,400.00
Tee Doos bh 1.0000 13,500 13,500.00
L.Bow bh 0.1000 8,500 850.00
Las Dop bh 0.3000 8,500 2,550.00
Imbul Doos bh 1.0000 5,000 5,000.00
Klem Pipa Listrik bh 0.1000 5,000 500.00
Fitting Lampu bh 1.0000 12,500 12,500.00
JUMLAH HARGA BAHAN 70,300.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 78,100.00
E Overhead & Profit 15% 10% 7,810.00
F Harga Satuan Pekerjaan (D+E) - 85,910.00
ANALISA PEKERJAAN
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1m2 dinding batako tebal 1 batu campuran 1 SP : 4 PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.6000 78,000 46,800.00
Tukang Batu L.02.03 OH 0.2000 96,014 19,202.88
Kepala Tukang L.03.01 OH 0.0200 109,759 2,195.18
Mandor L.04.01 OH 0.0300 116,598 3,497.95
JUMLAH TENAGA KERJA 71,696.02
B BAHAN
Batako Buah 12.0000 2,883 34,596.94
Semen portland Kg 26.5500 1,296 34,413.78
Pasir Pasang m3 0.0930 276,958 25,757.11
JUMLAH HARGA BAHAN 94,767.83
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 166,463.84
E Overhead & Profit 15% 10% 16,646.38
F Harga Satuan Pekerjaan (D+E) - 183,110.00

A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.3500 -
Tukang Besi L.02.05 OH 0.3500 -
Kepala Tukang L.03.01 OH 0.0350 -
Mandor L.04.01 OH 0.0180 -
JUMLAH TENAGA KERJA -
B BAHAN
Rangka metal hollow 40.40.2 mm M1 4.0000 -
Assesoris (perkuatan, las dll) Ls 1.0000 - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - -
E Overhead & Profit 15% 15% -
F Harga Satuan Pekerjaan (D+E) - -
A.2.2.1.15. Pemasangan 1 m2 pagar BRC lengkap dengan tiang
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0420 61,500 2,583.00
Tukang L.02.01 OH 0.0040 65,000 260.00
Kepala Tukang L.03.01 OH 0.0020 70,000 140.00
Mandor L.04.01 OH 0.0420 75,000 3,150.00
JUMLAH TENAGA KERJA 6,133.00
B BAHAN - -
Pagar BRC dengan tiang Lbr 1.0000 482,000 482,000.00
JUMLAH HARGA BAHAN 482,000.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 488,133.00
E Overhead & Profit 15% 15% 73,219.95
F Harga Satuan Pekerjaan (D+E) - 561,352.00
UPAH TENAGA KERJA DAN HARGA SATUAN BAHAN

NAMA KEGIATAN : PEMBANGUNAN RUMAH SEDERHANA


PEKERJAAN : PEMBANGUNAN RUMAH 10 X 10 METER 1 UNIT
LOKASI : JALAN NISNONI KEC. KOTA LAMA KEL. KUANINO KOTA KUPANG
TAHUN ANGGARAN : 2021

Upah Tenaga
No. Tenaga Kerja Satuan
Kerja (Rp./Hr)
1 Pekerja Org/Hari 78,000.00
2 Mandor Org/Hari 95,000.00
3 Kepala Tukang Org/Hari 90,000.00
4 Tukang Kayu Org/Hari 85,000.00
5 Tukang Batu Org/Hari 85,000.00
6 Tukang Besi Org/Hari 85,000.00
7 Tukang Las Org/Hari 85,000.00
8 Tukang Pipa Org/Hari 85,000.00
9 Tukang Cat Org/Hari 85,000.00
10 Operator Org/Hari 90,000.00
11 Pembantu Operator Org/Hari 78,000.00
12 Driver Org/Hari 90,000.00
13 Pembantu Driver Org/Hari 95,000.00
14 Mekanik Org/Hari 95,000.00
15 Helper (Pembantu) Org/Hari 78,000.00
16 Welder (Tukang Las) Org/Hari 90,000.00

No. Material Satuan Harga ( Rp )


1 2 3 4
BAHAN LOKAL
1 SemenPortland Kg 1,296.19
2 SemenPortland Zak 48,000.00
3 Semen Putih Kg 2,125.00
4 Pasir Filter M3 291,958.21
5 Pasir Urug M3 276,958.21
6 Pasir Pasang M3 276,958.21
7 Pasir Beton M3 276,958.21
8 Pasir Beton Kg 197.83
9 Sirtu Kasar M3 121,721.74
10 Batu Kali/Gunung/Karang M3 524,996.76
11 Koral Beton M3 393,997.08
12 Batu Gravel 5-10 cm M3 326,958.21
13 Batu Gravel 5-10 cm Kg 242.19
14 Batu Gravel 3-5 cm M3 326,958.21
15 Batu Gravel 3-5 cm Kg 242.19
16 Kerikil Gravel 2-3 cm M3 331,958.21
17 Kerikil Gravel 2-3 cm Kg 245.89
18 Kerikil Gravel 1-2 cm M3 326,958.21
19 Kerikil Gravel 1-2 cm Kg 242.19
20 Kerikil Gravel 0.5-1 cm M3 326,958.21
21 Kerikil Gravel 0.5-1 cm Kg 242.19
22 Bata Merah Buah 977.50
23 Batu Batako Buah 2,883.08
24 Batu Roster Buah 25,000.00
25 Kayu Klass III M3 2,127,500.00
26 Papan Bekisting 3/30 M3 2,185,000.00
27 Kayu Klas II Balok M3 3,047,500.00
28 Kayu Kaso 5/7 M3 3,250,000.00
29 Kayu Kaso 5/7 M' 16,750.00
No. Material Satuan Harga ( Rp )
1 2 3 4
30 Kayu Jati Balok M3 6,621,192.36
31 Kayu Jati Papan M3 7,650,000.00
32 Kayu Klas II Papan M3 4,550,000.00
33 Kayu Dolken Panjang 4 Meter Btg 55,000.00
34 Kayu Bayam Panjang 4 Meter Btg 321,428.57
35 List Plafond Gypsum M¹ 8,625.00
36 Paku Biasa Kg 17,250.00
37 Sekrup Bh 500.00
38 Besi Beton Kg 19,350.18
39 Kawat Beton Kg 19,550.00
40 Kawat Lat Kg 30,000.00
41 Kawat Bronjong Kg 27,500.00
42 Kawat Bronjong Uk. 1 m3 Bh 375,000.00
43 Cat Manie Kg 34,500.00
44 Cat Tembok Kg 63,250.00
45 Plamir Tembok Kg 11,500.00
46 Kuwas Buah 20,000.00
47 Amplas Lembar 5,000.00
48 Cat Kayu/Besi Kg 69,000.00
49 Cat Dasar Kg 50,500.00
50 Cat Tembok Kg 60,000.00
51 Plamir Kayu Kg 51,750.00
52 Plitur Liter 28,000.00
53 Plitur Kayu Liter 30,000.00
54 Minyak Cat (Tinner) Kg 31,625.00
55 Minyak Bekesting Kg 20,125.00
56 Sealant Kg 17,250.00
57 Lem Kayu (Webber) Liter 57,500.00
58 Lem Kayu (Webber) Kg 57,500.00
59 Paku Seng Kg 23,000.00
60 Paku 2-3 Kg 10,000.00
61 Paku 5-7 Kg 15,000.00
62 Paku 10 Kg 17,000.00
63 Paku 12 Kg 20,000.00
64 Seng Gelombang BJLS 20 Lembar 63,250.00
65 Seng Nok BJLS 20 Lembar 46,000.00
66 Seng Licin 0.2mm Lembar 34,500.00
67 Genteng Multiroof 0,30 mm M2 81,403.49
68 Besi Siku 60.60.06 M' 46,920.00
69 Besi Siku50.50.05 M' 34,500.00
70 Besi Siku 30.30.03 M' 18,400.00
71 Plat Baja 1.9 mm Kg 69,662.92
72 Besi Profil Kg 32,666.67
73 Besi Beton Kg 23,000.00
74 Besi Strip Kg 20,125.00
75 Besi Tralis M¹ 14,375.00
76 Kawan Beton Kg 20,125.00
77 Kawat Las Btg 2,300.00
78 Kawat Bronjong Kg 23,000.00
79 Kawat Harmonika M² 28,750.00
80 Kawat Duri Rol 287,500.00
81 Kawat Duri M' 3,500.00
82 Triplek 4 mm Lembar 74,300.00
83 Multipek 8 mm Lembar 113,275.00
84 Plywood/Multipek 9 mm Lembar 143,750.00
85 Multipek 18 mm Lembar 281,750.00
86 Teakwood 4 mm Lembar 97,750.00
87 Gypsum board 9 mm (1200 x 2400 mm) Lembar 68,117.38
No. Material Satuan Harga ( Rp )
1 2 3 4
88 Beugel U Buah 25,000.00
89 Jendela Nako M² 138,000.00
90 Besi Strip M² 161,000.00
91 Kunci Tanam 2 Slaag Buah 84,250.00
92 Engsel Pintu Buah 39,675.00
93 Spring Knip Buah 12,000.00
94 Kait Angin Buah 17,250.00
95 Engsel Kupu-Kupu Buah 23,000.00
96 Grendel Buah 17,250.00
97 Kaca Tebal 3 mm M² 143,750.00
98 Kaca Tebal 5 mm M² 201,250.00
99 Plastik Kasa M¹ 23,000.00
100 Waterstop Lebar 20 cm M' 2,070.00
101 Kloset Jongkok Porselin Buah 172,500.00
102 Baut Moer 12 -50 mm Buah 5,750.00
103 Baja Honeycom WF.375.125.6.9, termasuk pabrikasi Kg 21,850.00
104 Baja WF.250.125.6.9 Kg 10,925.00
105 Baja Wide Flange (WF) 300.150.6,5.9 Kg 10,000.00
106 Baja Wide Flange (WF) 350.175.7.11 Kg 10,000.00
107 Baja Wide Flange (WF) 400.200.8.13 Kg 10,000.00
108 Baja Wide Flange (WF) 500.200.10.16 Kg 10,000.00
109 Baja Wide Flange (WF) 600.200.11.17 Kg 10,000.00
110 Baja Wide Flange (WF) 800.300.14.26 Kg 15,000.00
111 Baja Ringan Kanal C (C Galvalum/Truss/CNP 75x35x0,70 mm m' 20,852.01
112 Pipa Kotak Baja Ringan 2 x 4 m' 5,833.33
113 Pengaku dan Brancing L.50.50.05 Kg 10,752.50
114 Pengaku Kanal C.80.50.5 Kg 35,000.00
115 Plat-Plat 12.10.8.6 Kg 35,000.00
116 Plat RIB Buah 10,000.00
117 Besi Plat Pengaku Samping 300.232.08 Buah 300,000.00
118 Plat Tumpu Baja WF Tebal 12mm (30x40cm) Buah 450,000.00
119 Clamp Pipa Plat Strip 50.05 Buah 128,800.00
120 Baut Moer HTB Sambungan WF Ø 16 mm Buah 22,137.50
121 Baut Moer Pengaku dan Brancing Ø 16 mm Buah 18,112.50
122 Baut Moer Clamp Pipa Ø 16 mm Buah 14,950.00
123 Angker Moer Baut Ø 25 mm - 30 mm Buah 97,175.00
124 Pagar Landak Besi Beton dan Plat Strip Buah 560,625.00
125 Sambungan WF Set 563,500.00
126 Angker Moer Baut Ø 16 mm - 25 cm Buah 30,000.00
127 Pipa Gip Ø 150 mm Buah 566,720.00
128 Pipa PVC tipe AW diameter 1/2” M' 23,000.00
129 Pipa PVC tipe AW diameter 3/4” M' 22,000.00
130 Pipa PVC tipe AW diameter 1” M' 45,000.00
131 Pipa PVC tipe AW diameter 1.1/2” M' 56,500.00
132 Pipa PVC tipe AW diameter 2” M' 78,500.00
133 Pipa PVC tipe AW diameter 2.1/2” M' 80,000.00
134 Pipa PVC tipe AW diameter 3” M' 97,500.00
135 Pipa PVC tipe AW diameter 4” M' 98,750.00
136 Kran Air 1/2" Buah 135,000.00
137 Floor Drain Buah 20,000.00
138 Bak Cuci Piring Stainles Steel Buah 250,000.00
139 Closed Duduk Monoblock Lengkap Asesorisnya Buah 2,258,747.49
140 Wastafel Buah 550,000.00
141 Jet/ Sower Lengkap Asesorinya Buah 350,000.00
142 Tandon Air uk 5000 L (tebal 10-12mm) Buah 6,500,000.00
143 Tandon Air uk 2200 L (10-12mm) Buah 2,200,000.00
144 Pompa Air Sumersible Unit 1,500,000.00
145 Tower Besi Jadi Penempatan Tandon Air Unit 3,500,000.00
No. Material Satuan Harga ( Rp )
1 2 3 4
146 Baut Mur 19 mm + Ring M¹ 25,000.00
147 Balok Kayu Bayam 150.80.400 Buah 75,000.00
148 Clamp Support Pipa Ø 200 mm Buah 161,000.00
149 Clamp Support Pipa Ø 150 mm Buah 138,000.00
150 Clamp Support Pipa Ø 100 mm Buah 92,000.00
151 Clamp Support Pipa Ø 75mm Buah 74,750.00
152 Clamp Support Pipa Ø 50mm Buah 56,000.00
153 Tutup Bak Kontrol Buah 862,500.00
154 Pintu saluran dari plat baja 8mm Buah 1,100,000.00
155 Engsel Besi Buah 14,750.00
156 Gembok Buah 10,000.00
157 Pipa Udara Buah 287,500.00
158 Tangga Kontrol Buah 575,000.00
159 Pipa Selubung Buah 78,750.00
160 Pintu Pagar BRC Lebar 1M¹ Buah 1,200,000.00
161 Pintu Teralis Buah 1,000,000.00
162 Jelusi Buah 750,000.00
163 Kawat saringan Buah 30,000.00
164 Katup Saringan Buah 102,000.00
165 Paving Block M² 345,000.00
166 Keramik 25 x 25 Bertesktur Buah 69,776.93
167 Keramik 40 x 40 Buah 16,184.11
168 Granit 60 x 60 Buah 46,964.44
169 Dinding Keramik 25 x 40 cm Buah 10,899.37
170 Plint Keramik ukuran 10 cm x 60cm Buah 31,276.93
171 Meteran Listrik PLN 1300 KWA Unit 3,500,000.00
172 1 MCB Unit 70,000.00
173 Lampu LED Dwonlight Tutup 23 WATT Bh 105,000.00
174 Lampu LED Dwonlight Tutup 18 WATT Bh 95,000.00
175 Saklar Tunggal Bh 20,000.00
176 Saklar Ganda Bh 22,000.00
177 Saklar Tripel Bh 23,000.00
178 Stop Kontak Dinding Bh 17,500.00
179 Pipa listrik 5/8” Btg 10,000.00
180 Kabel NYM 3x2,5 mm2 M' 13,500.00
181 Tee Doos Bh 13,500.00
182 L.Bow Bh 8,500.00
183 Las Dop Bh 8,500.00
184 Klem Pipa Listrik Bh 5,000.00
185 Imbul Doos Bh 12,500.00
186 Saklar (standar) Bh 15,000.00
187 Fitting Lampu Bh 12,500.00
188 Air Bersih Ltr 25.00
189 Minyak Bensin Ltr 7,475.00
190 Minyak Solar Ltr 13,000.00
191 Minyak Pelumas Ltr 40,250.00
E PERALATAN
1 Sewa Dump Truck Hari 1,697,241.72
2 Mesin las HDPE Hari 1,321,950.10
3 Mesin Las Listrik Jam 192,152.47
4 Alat Bantu Hari 200,000.00
5 Pompa Tes Tekan Hari 1,227,105.66
6 Stamper Hari 1,451,908.55
7 Concrete Mixer Hari 450,000.00
8 Concrete Vibrator Hari 175,000.00
9 Jack Hammer Hari 225,000.00
10 Genset Hari 1,267,145.00
11 Tripod/ Tackle & Handle Crane 2T Hari 325,000.00
ANALISA MATERIAL ON SITE
1 HARGA SEMEN PER KG DI LOKASI PEKERJAAN

A 1 Kg Harga Semen dan Biaya Angkut sd lokasi yang dapat di akses kendaraan
- Jarak angkut PP = 1.20 Km
- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3,000.00 Kg
- Waktu per trip + fixed time = 1.03 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 6.77 Trip
- Berat per zak semen = 40.00 Kg
- Kapasitas angkut per trip per truck = 75.00 Zak
- Sewa truck per trip = 1,640,979.57 Rp.
- Produksi per hari = 507.60 Zak
- Ongkos angkut ke lokasi per zak = 3,232.84 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per zak = 614.66 Rp.
- Harga Semen per zak = 48,000.00 Rp.
- Ongkos Angkut ke Lokasi per zak = 3,232.84 Rp.
- Ongkos Bongkar Muat per zak = 614.66 Rp.
- Jumlah Harga Semen per zak di lokasi ( q + r + s ) = 51,847.50 Rp.

Jumlah Harga semen per kg = 1,296.19 Rp.

ANALISA MATERIAL ON SITE


2 HARGA BATU KALI PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 70.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 35.00 Km
- Kecepatan truck rata-rata per jam = 30.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.33 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.10 Trip
- Sewa truck per trip = 1,640,979.57 Rp.
- Produksi per hari = 6.30 M3
- Ongkos angkut ke lokasi per M3 = 260,472.95 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 49,523.81 Rp.

Harga Batu Kali per M3 = 215,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 260,472.95 Rp.
Ongkos Bongkar Muat per M3 = 49,523.81 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 524,996.76 Rp.


ANALISA MATERIAL ON SITE
3 HARGA BATU KARANG PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 70.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.00 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.33 Trip
- Sewa truck per trip = 1,640,979.57 Rp.
- Produksi per hari = 7.00 M3
- Ongkos angkut ke lokasi per M3 = 234,425.65 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 44,571.43 Rp.

Harga Batu Karang per M3 = 150,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 234,425.65 Rp.
Ongkos Bongkar Muat per M3 = 44,571.43 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 428,997.08 Rp.

ANALISA MATERIAL ON SITE


4 HARGA KORAL BETON PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 70.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.00 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.33 Trip
- Sewa truck per trip = 1,640,979.57 Rp.
- Produksi per hari = 7.00 M3
- Ongkos angkut ke lokasi per M3 = 234,425.65 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 44,571.43 Rp.

Harga Koral Beton per M3 = 115,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 234,425.65 Rp.
Ongkos Bongkar Muat per M3 = 44,571.43 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 393,997.08 Rp.


ANALISA MATERIAL ON SITE
5 HARGA PASIR URUG PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

Harga Pasir Urug per M3 = 150,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 276,958.21 Rp.

ANALISA MATERIAL ON SITE


6 HARGA PASIR PASANG PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

- Harga Pasir Pasang per M3 = 150,000.00 Rp.


- Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
- Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 276,958.21 Rp.


ANALISA MATERIAL DILOKASI SEMENTARA
7 HARGA PASIR BETON PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

- Harga Pasir Beton per M3 = 150,000.00 Rp.


- Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
- Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 276,958.21 Rp.

ANALISA MATERIAL DILOKASI SEMENTARA


8 HARGA PASIR FILTER PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

- Harga Pasir Filter per M3 = 165,000.00 Rp.


- Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
- Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 291,958.21 Rp.


ANALISA MATERIAL ON SITE
9 HARGA BATU GRAVEL Ø 5 - 10 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

Harga Batu Gravel per M3 = 200,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 326,958.21 Rp.

ANALISA MATERIAL ON SITE


10 HARGA BATU PECAH 2-3 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

Harga Batu Pecah per M3 = 205,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 331,958.21 Rp.


ANALISA MATERIAL ON SITE
11 HARGA BATU PECAH 0,5-1 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

Harga Kerikil Gravel cm per M3 = 200,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 326,958.21 Rp.

ANALISA MATERIAL ON SITE


12 HARGA BATU PECAH Ø 3 - 5 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.

Harga Batu Pecah per M3 = 200,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 326,958.21 Rp.


ANALISA MATERIAL ON SITE
13 HARGA BATU PECAH Ø 1 - 2 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 80.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 3.29 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.13 Trip
- Sewa truck per trip = 499,428.56 Rp.
- Produksi per hari = 6.39 M3
- Ongkos angkut ke lokasi per M3 = 78,141.88 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 48,816.33 Rp.
Harga Batu Gravel per M3 = 200,000.00 Rp.
Ongkos Angkut ke Lokasi per M3 = 78,141.88 Rp.
Ongkos Bongkar Muat per M3 = 48,816.33 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 326,958.21 Rp.

ANALISA MATERIAL ON SITE


14 HARGA BESI POLOS DIAMETER 8 PER KG SD LOKASI PEKERJAAN

- Jarak angkut PP = 8.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3,000.00 Kg
- Waktu per trip + fixed time = 1.23 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.70 Trip
- Berat per 1 Staaf = 0.39 Kg
- Kapasitas angkut per trip per truck = 7,692.31 Kg
- Sewa truck per trip = 1,381,475.82 Rp.
- Produksi per hari = 43,828.26 Staf
- Ongkos angkut ke lokasi per Staf = 31.52 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Staf = 7.12 Rp.
- Harga Besi Polos Diameter 8 Per Staf = 56,000.00 Rp.
- Ongkos Angkut ke Lokasi per Staf = 31.52 Rp.
- Ongkos Bongkar Muat per Staf = 7.12 Rp.
- Jumlah Harga Semen per Staf di lokasi ( q + r + s ) = 56,038.64 Rp.

Jumlah Harga per kg = 4,669.89 Rp.


ANALISA MATERIAL ON SITE
15 HARGA KAYU KELAS I PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 8.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 35.00 Km
- Kecepatan truck rata-rata per jam = 30.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.27 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.53 Trip
- Sewa truck per trip = 1,697,241.72 Rp.
- Produksi per hari = 16.58 M3
- Ongkos angkut ke lokasi per M3 = 102,373.31 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 18,819.05 Rp.
Harga Kayu Kelas I M3 = 6,500,000.00 Rp.
Ongkos Angkut ke Lokasi per M3 = 102,373.31 Rp.
Ongkos Bongkar Muat per M3 = 18,819.05 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 6,621,192.36 Rp.

ANALISA MATERIAL ON SITE


16 HARGA KAYU DOLKEN M3 DI LOKASI PEKERJAAN

- Jarak angkut PP = 8.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 30.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 37.50 Km
- Kapasitas angkut truk = 3.00 M3
- Waktu per trip + fixed time = 1.21 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.77 Trip
- Berat per meter = 94.00 Kg
- Kapasitas angkut per trip per truck = 0.03 M'
- Sewa truck per trip = 1,697,241.72 Rp.
- Produksi per hari = 17.31 Kg
- Ongkos angkut ke lokasi per M3 = 98,062.86 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per M3 = 3,319.15 Rp.
Harga Kayu Dolken M3 = 3,500,000.00 Rp.
Ongkos Angkut ke Lokasi per M3 = 98,062.86 Rp.
Ongkos Bongkar Muat per M3 = 3,319.15 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 3,601,382.00 Rp.


ANALISA MATERIAL ON SITE
17 HARGA TRIPLEKS LEMBAR DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Lembar = 30.00 Kg
- Kapasitas angkut per trip per truck = 100.00 Lembar
- Sewa truck Waktu trip = 1,697,241.72 Rp.
- Produksi per Lembar = 597.56 Lembar
- Ongkos angkut ke lokasi per Lembar = 2,840.28 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Lembar = 522.12 Rp.
- Harga Batako Per Lembar = 105,000.00 Rp.
- Ongkos Angkut ke Lokasi per Lembar = 2,840.28 Rp.
- Ongkos Bongkar Muat per Lembar = 522.12 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 108,362.40 Rp.
Jumlah Harga per Lembar di lokasi (p + q + r) = 108,362.40 Rp.

ANALISA MATERIAL ON SITE


18 HARGA BAJA RINGAN CANAL C 0,75 PER BATANG SD LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Batang = 1.00 Kg
- Kapasitas angkut per trip per truck = 3,000.00 Batang
- Sewa truck Waktu trip = 1,697,241.72 Rp.
- Produksi per Lembar = 17,926.83 Lembar
- Ongkos angkut ke lokasi per Batang = 94.68 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Batang = 17.40 Rp.
- Harga Per Batang = 125,000.00 Rp.
- Ongkos Angkut ke Lokasi per Batang = 94.68 Rp.
- Ongkos Bongkar Muat per Batang = 17.40 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 125,112.08 Rp.

Jumlah Harga per Batang di lokasi (p + q + r) = 125,112.08 Rp.


ANALISA MATERIAL ON SITE
19 HARGA MULTIROOF 0,30MM PER LEMBAR SD LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Lembar = 3.00 Kg
- Kapasitas angkut per trip per truck = 1,000.00 Lembar
- Sewa truck Waktu trip = 1,697,241.72 Rp.
- Produksi per Lembar = 5,975.61 Lembar
- Ongkos angkut ke lokasi per Lembar = 284.03 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Lembar = 52.21 Rp.
- Harga Per Lembar = 67,500.00 Rp.
- Ongkos Angkut ke Lokasi per Lembar = 284.03 Rp.
- Ongkos Bongkar Muat per Lembar = 52.21 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 67,836.24 Rp.

Jumlah Harga per Lembar di lokasi (p + q + r) = 67,836.24 Rp.

ANALISA MATERIAL ON SITE


20 HARGA GYPSUM PER KG SD LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Lembar = 3.00 Kg
- Kapasitas angkut per trip per truck = 1,000.00 Lembar
- Sewa truck Waktu trip = 1,697,241.72 Rp.
- Produksi per Lembar = 5,975.61 Lembar
- Ongkos angkut ke lokasi per Lembar = 284.03 Rp.
- Harga upah pekerja = 498,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Lembar = 333.36 Rp.
- Harga Per Lembar = 67,500.00 Rp.
- Ongkos Angkut ke Lokasi per Lembar = 284.03 Rp.
- Ongkos Bongkar Muat per Lembar = 333.36 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 68,117.38 Rp.

Jumlah Harga per Lembar di lokasi (p + q + r) = 68,117.38 Rp.


ANALISA MATERIAL ON SITE
21 HARGA KERAMIK 40 X 40 PLATINUM PERBUAH DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Dos = 18.00 Kg
- Kapasitas angkut per trip per truck = 166.67 Buah
- Sewa truck Waktu trip = 1,697,241.72 Rp.
- Produksi per Dos = 995.93 Buah
- Ongkos angkut ke lokasi per Buah = 1,704.17 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Dos = 313.27 Rp.
- Harga Per Buah = 14,166.67 Rp.
- Ongkos Angkut ke Lokasi per Dos = 1,704.17 Rp.
- Ongkos Bongkar Muat per Dos = 313.27 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 16,184.11 Rp.

Jumlah Harga per Buah di lokasi (p + q + r) = 16,184.11 Rp.

ANALISA MATERIAL ON SITE


22 HARGA GRANIT 60 X 60 PERBUAH DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Dos = 18.00 Kg
- Kapasitas angkut per trip per truck = 166.67 Buah
- Sewa truck Waktu trip = 848,620.86 Rp.
- Produksi per Dos = 995.93 Buah
- Ongkos angkut ke lokasi per Buah = 852.08 Rp.
- Harga upah pekerja = 276,958.21 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Dos = 1,112.35 Rp.
- Harga Per Buah = 45,000.00 Rp.
- Ongkos Angkut ke Lokasi per Dos = 852.08 Rp.
- Ongkos Bongkar Muat per Dos = 1,112.35 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 46,964.44 Rp.

Jumlah Harga per Buah di lokasi (p + q + r) = 46,964.44 Rp.


ANALISA MATERIAL ON SITE
23 HARGA KERAMIK 25 X 25 PERBUAH DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Dos = 13.00 Kg
- Kapasitas angkut per trip per truck = 230.77 Buah
- Sewa truck Waktu trip = 1,448,864.89 Rp.
- Produksi per Dos = 1,378.99 Buah
- Ongkos angkut ke lokasi per Buah = 1,050.67 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Dos = 226.25 Rp.
- Harga Per Buah = 68,500.00 Rp.
- Ongkos Angkut ke Lokasi per Dos = 1,050.67 Rp.
- Ongkos Bongkar Muat per Dos = 226.25 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 69,776.93 Rp.

Jumlah Harga per Dos = 69,776.93 Rp.

ANALISA MATERIAL ON SITE


24 HARGA KERAMIK 20 X 25 PERBUAH DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Dos = 13.00 Kg
- Kapasitas angkut per trip per truck = 230.77 Buah
- Sewa truck Waktu trip = 1,448,864.89 Rp.
- Produksi per Dos = 1,378.99 Buah
- Ongkos angkut ke lokasi per Buah = 1,050.67 Rp.
- Harga upah pekerja = 68,500.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Dos = 198.70 Rp.
- Harga Per Buah = 9,650.00 Rp.
- Ongkos Angkut ke Lokasi per Dos = 1,050.67 Rp.
- Ongkos Bongkar Muat per Dos = 198.70 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 10,899.37 Rp.

Jumlah Harga per Dos = 10,899.37 Rp.


ANALISA MATERIAL ON SITE
25 HARGA PLINT KERAMIK PERBUAH DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3.00 m3
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Dos = 13.00 Kg
- Kapasitas angkut per trip per truck = 230.77 Buah
- Sewa truck Waktu trip = 1,448,864.89 Rp.
- Produksi per Dos = 1,378.99 Buah
- Ongkos angkut ke lokasi per Buah = 1,050.67 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Dos = 226.25 Rp.
- Harga Per Buah = 30,000.00 Rp.
- Ongkos Angkut ke Lokasi per Dos = 1,050.67 Rp.
- Ongkos Bongkar Muat per Dos = 226.25 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 31,276.93 Rp.

Jumlah Harga per Buah di lokasi (p + q + r) = 31,276.93 Rp.

ANALISA MATERIAL ON SITE


26 HARGA CLOSET DUDUK LENGKAP ASESORIS PERBUAH DI LOKASI PEKERJAAN

- Jarak angkut PP = 6.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 30.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 37.50 Kg
- Kapasitas angkut truk = 3,000.00 M3
- Waktu per trip + fixed time = 1.16 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 6.03 Trip
- Berat per Buah = 9.00 Kg
- Kapasitas angkut per trip per truck = 333.33 M'
- Sewa truck per trip = 1,463,139.42 Rp.
- Produksi per hari = 18,103.45 Buah
- Ongkos angkut ke lokasi per Buah = 80.82 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 1.00 Orang
- Biaya bongkar muat per Buah = 8,666.67 Rp.
Harga Perbuah = 2,250,000.00 Rp.
Ongkos Angkut ke Lokasi per Buah = 80.82 Rp.
Ongkos Bongkar Muat per Buah = 8,666.67 Rp.

Jumlah Harga per Buah di lokasi (p + q + r) = 2,258,747.49 Rp.


ANALISA MATERIAL ON SITE

27 HARGA BATAKO Per/BUAH SD LOKASI PEKERJAAN

1 Buah Harga Batako dan Biaya Angkut sd lokasi yang dapat di akses kendaraan
- Jarak angkut PP = 6.00 Km
- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 400.00 Buah
- Waktu per trip + fixed time = 1.17 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.98 Trip
- Berat per Buah = 0.52 Kg
- Kapasitas angkut per trip per truck = 769.23 Buah
- Sewa truck Waktu trip = 1,448,864.89 Rp.
- Produksi per Buah = 4,596.62 Zak
- Ongkos angkut ke lokasi per Buah = 315.20 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Buah = 67.88 Rp.
- Harga Batako Per Buah = 2,500.00 Rp.
- Ongkos Angkut ke Lokasi per Buah = 315.20 Rp.
- Ongkos Bongkar Muat per Buah = 67.88 Rp.
- Jumlah Harga di lokasi ( q + r + s ) = 2,883.08 Rp.

Jumlah Harga per Buah = 2,883.08 Rp.

ANALISA MATERIAL ON SITE


28 HARGA SIRTU M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 62.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 2.77 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 2.53 Trip
- Sewa truck Waktu trip = 1,697,241.72 Rp.
- Produksi per hari = 7.58 M3
- Ongkos angkut ke lokasi per M3 = 223,989.72 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 41,175.51 Rp.

Harga per M3 = 100,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 223,989.72 Rp.
Ongkos Bongkar Muat per M3 = 41,175.51 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 365,165.23 Rp.


ANALISA MATERIAL ON SITE
28 HARGA BESI POLOS DIAMETER 10 PER KG SD LOKASI PEKERJAAN

- Jarak angkut PP = 8.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut truk = 3,000.00 Kg
- Waktu per trip + fixed time = 1.23 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 5.70 Trip
- Berat per 1 Staaf = 0.86 Kg
- Kapasitas angkut per trip per truck = 3,488.37 Kg
- Sewa truck per trip = 1,697,241.72 Rp.
- Produksi per hari = 19,875.61 Staf
- Ongkos angkut ke lokasi per Staf = 85.39 Rp.
- Harga upah pekerja = 78,000.00 Rp.
- Jumlah pekerja bongkar muatan = 4.00 Orang
- Biaya bongkar muat per Staf = 15.70 Rp.
- Harga Besi Polos Diameter 10 Per Staf = 116,000.00 Rp.
- Ongkos Angkut ke Lokasi per Staf = 85.39 Rp.
- Ongkos Bongkar Muat per Staf = 15.70 Rp.
- Jumlah Harga Besi per Kg di lokasi ( q + r + s ) = 116,101.09 Rp.

Jumlah Harga Besi per kg = 19,350.18 Rp.


URAIAN ANALISA ALAT

NO. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK
2 Tenaga Pw 2.00 HP
3 Kapasitas Cp 5.00 Ton
4 Alat Bekas a. Umur Ekonomi A 4.00 Tahun
b. Jam Kerja dalam 1 tahun W 2,000.00 Jam
c. Harga Alat B 350,000,000.00 Rupiah
5 Alat Yang Dipakai a. Umur Ekonomi A' Tahun
b. Jam Kerja dalam 1 tahun W' Jam
c. Harga Alat (*) B' Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nial Sisa alat = 10 % x B C 35,000,000.00 Rupiah

2 Faktor Angsuran Modal = i x (1 + i )ˆA' D 0.26


(1 x i ) A'-1̂

3 Biaya Padsti perjam


a. Biaya Pengembalian Modal =(B-C)xD E 41,548.10 Rupiah
W

B. Asuransi dll = 0,002 x B F 350.00 Rupiah


W

Biaya Pasti Per Jam =(E+F) G 41,898.10 Rupiah

C. BIAYA OPERASIONAL PER JAM KERJA


1 Bahan Bakar = ( 0,15 Ltr/HP/Jam ) x Pw x Mb H 3,900.00 Rupiah

2 Pelumas = ( 0,015 Ltr/HP/Jam ) x Pw x Mp I 2,415.00 Rupiah

3 Perawatan dan Perbaikan = ( 15 % ) x B K 26,250.0 Rupiah


W'
4 Operator = ( 1 Orang / Jam ) x U1 L 90,000.00 Rupiah
5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 78,000.00 Rupiah

Biaya Operasi Per Jam =(H+I+K+L+M) P 200,565.00 Rupiah

D TOTAL BIAYA SEWA ALAT PER HARI = ( G + P ) X 7 S 1,697,241.72 Rupiah

E LAIN - LAIN
1 Tingkat Suku Bunga I 10.00 % / Tahun
2 Upah Operator / Sopir U1 90,000.00 Rp./Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 78,000.00 Rp./Jam
4 Bahan Bakar Bensin Mb 7,475.00 Liter
5 Bahan Bakar Solar Ms 13,000.00 Liter
6 Minyak Pelumas Mp 40,250.00 Liter
DAFTAR HARGA SATUAN ALAT

No. Jenis Peralatan Kode Satuan Harga Satuan (Rp.)

1 EXCAVATOR A01 Jam 684,802.94

2 DUMP TRUCK A02 Jam 272,637.69

3 BOLDOZER A03 Jam 732,349.51

4 VIBRATO ROLLER A04 Jam 327,594.99

5 WATER TANK TRUCK A05 Jam 279,994.31

6 Crawler Crane A06 Jam 750,000.00

7 Mesin Bor Untuk Pondasi A07 Jam 500,000.00

8 ALAT DAN BAHAN LAS A14 Ls 85,000.00


9 ALAT BANTU A15 Ls 1,000.00
ANALISIS BIAYA OPERASI ALAT BERAT

JENIS ALAT : Excavator, Dump Truck, Buldozer, Roller Vibro dan Water Tanker
SATUAN PEMBAYARAN : Rupiah/Jam

No. URAIAN KODE SATUAN PERHITUNGAN BIAYA OPERASI PERALATAN KETERANGAN

A. URAIAN PERALATAN Excavator


Dump Truck Bulldozer Roller Vibro Water Tank Truck
1. Peralatan (Standar)
2. Merk/Tipe 80 - 140 HP 3 - 4 M3 100 - 150 HP 5 - 8 Ton 3000 - 4500 L
3. Tenaga Pw HP 133.0 100.0 150.0 82.0 100.0
4. Kapasitas Cp - 0.4 3.5 - 7.1 4,000
5. Umur Ekonomis A Tahun 5.0 5.0 5.0 5.0 5.0
6. Jam Operasi dalam 1 tahun W Jam 2,000 2,000 2,000 2,000 2,000
7. Harga Alat B Rp 1,750,000,000 300,000,000 1,825,000,000 650,000,000 330,000,000

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat C Rp 175,000,000 30,000,000 182,500,000 65,000,000 33,000,000
i x (1 + i)A
2. Faktor Angsuran Modal = D - 0.33438 0.33438 0.33438 0.33438 0.33438
(1 + i)A - 1
3. Biaya Pasti Per Jam :
(B - C) x D
a. Biaya Pengembalian Modal = E Rp/Jam 263,324.02 45,141.26 274,609.33 97,806.06 49,655.39
W
B
b. Asuransi, dll = px F Rp/Jam 1,750.00 300.00 1,825.00 650.00 330.00
W
Biaya Pasti Per Jam G=(E+F) 265,074.02 45,441.26 276,434.33 98,456.06 49,985.39

C. BIAYA OPERASI PER JAM KERJA Koef. Biaya OP Alat


1. Bahan Bakar = (12% - 15%) x Pw x Ms H Rp/Jam 111,720.00 84,000.00 126,000.00 68,880.00 84,000.00 12.00%
2. Pelumas = (2,5% - 3%) x Pw x Mp I Rp/Jam 116,375.00 87,500.00 131,250.00 71,750.00 87,500.00 2.50%
B
3. Biaya Bengkel = (6,25 - 8,75%) x J Rp/Jam 54,687.50 9,375.00 57,031.25 20,312.50 10,312.50 6.25%
W
Perawatan dan B
4. = (12,5 - 17,5%) x K Rp/Jam 109,375.00 18,750.00 114,062.50 40,625.00 20,625.00 12.50%
Perbaikan W

5. Operator = (m orang/jam) x U1 / 7 Jam M Rp/Jam 16,428.57 16,428.57 16,428.57 16,428.57 16,428.57


6. Pembantu Operator = (n orang/jam) x U1 / 7 Jam L Rp/Jam 11,142.86 11,142.86 11,142.86 11,142.86 11,142.86
Biaya Operasi (per Jam) = P Rp/Jam 419,728.93 227,196.43 455,915.18 229,138.93 230,008.93

D. BIAYA OPERASI ALAT/JAM = ( G + P ) 684,802.94 272,637.69 732,349.51 327,594.99 279,994.31


E. BIAYA OPERASI ALAT/HARI = ( P X 7 ) 4,793,620.61 1,908,463.82 5,126,446.57 2,293,164.94 1,959,960.20
F. LAIN-LAIN
1. Bahan Bakar Premium (Non Subsidi) Mb Liter - - - - -
2. Bahan Bakar Solar (Non Subsidi) Ms Liter 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00
3. Minyak Pelumas Mp Liter 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00
4. Suku Bunga i % 0.2000 0.2000 0.2000 0.2000 0.2000
5. Asuransi p % 0.002 0.002 0.002 0.002 0.002
6. Upah Operator/Sopir U1 Rp 115,000.00 115,000.00 115,000.00 115,000.00 115,000.00
7. Upah Operator/Sopir U2 Rp 78,000.00 78,000.00 78,000.00 78,000.00 78,000.00

Das könnte Ihnen auch gefallen