Beruflich Dokumente
Kultur Dokumente
: JMDC-2107
Project Title: Myla FernandeZ Gate
Project Location: Brgy. Pagdaraoan, City of San
Fernando La Union
Owner: Ms. Myla Fernandez Legend:
Project Start: 22/08/22 Planned Duration
Project Finish: 15/09/2022 Actual Duration
Schedule Duration
Project Finish
Actual Finish
Actual Start
Item Scope of Work
Layout
Layout for gate 1 22-Aug-22 22-Aug-22
Actual
Adjustment of temporary gate 1 22-Aug-22 22-Aug-22
Actual
FOOTING WORKS-WALL FOOTING
Excavation Works
4 22-Aug-22 25-Aug-22
Excavation for footing
Actual
Reinforcement Works
Percent Weight
Actual
Actual
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
SK L M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
22 26-Sep-22 6-Oct-22 13-Sep-21 20-Sep-21 27-Sep-21 4-Oct-21 11
24 25 26 27 28 29 30 1 6 7 8 9 10 11 13 14 15 16 17 18 20 21 22 23 24 25 27 28 29 30 1 2 4 5 6 7 8 9 11 12
S S M T W T F S T T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T
11-Oct-21 18-Oct-21 25-Oct-21 2-Nov-21 8-Nov-21 15-Nov-21 22-Nov-21
13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27 29
W T F S M T W T F S M T W T F S T W T F S M T W T F S M T W T F S M T W T F S M
29-Nov-21 6-Dec-21 13-Dec-21 20-Dec-21 27-Dec-21 3-Jan-22 10-Jan-22 17-Jan-
30 1 2 3 4 6 7 8 9 10 11 13 14 15 16 17 18 20 21 22 23 27 28 29 30 3 4 5 6 7 8 10 11 12 13 14 15 17 18 19
T W T F S M T W T F S M T W T F S M T W T M T W T M T W T F S M T W T F S M T W
17-Jan-22 24-Jan-22 31-Jan-22
20 21 22 24 25 26 27 28 29 31 1 2 3 4 5
T F S M T W T F S M T W T F S
Project I.D.: JMDC-2107
Schedule Duration
Project Finish
Actual Start
Item Scope of Work
CLEARING
Removal of existing roof frame 1 13-Sep-22 13-Sep-22
Actual
PARAPET WALL
Masonry Works
Layout for chb laying 1 13-Sep-22 13-Sep-22
Actual
Chb laying on parapet walls 2 13-Sep-22 14-Sep-22
Actual
ROOF FRAME SUPPORT
Masonry Works
Chb laying for roof support 3 15-Sep-22 17-Sep-22
Actual
ROOF FRAME WORKS
Layout
Layout for roof frame 1 15-Sep-22 15-Sep-22
Actual
Fabrication & Installation of Roof frames 8 15-Sep-22 23-Sep-22
Actual
Primer
Application of paint primer 2 24-Sep-22 26-Sep-22
Actual
ROOF COVER WORKS
Roof Cover
Installation of roof sheets 3 26-Sep-22 28-Sep-22
Actual
Installation of gutter 1 29-Sep-22 29-Sep-22
Actual
Fabrication & Installation of downspout 1 29-Sep-22 29-Sep-22
Actual
Installation of wall flashing 1 30-Sep-22 30-Sep-22
Actual
PAINTING WORKS-WALLS
Skimcoat
Application of skimcoat on walls 2 29-Sep-22 30-Sep-22
Actual
Paint primer
Application of primer -parapet wall 1 30-Sep-22 30-Sep-22
Actual
Paint topcoat
Application of topcoat -parapet wall 1 30-Sep-22 30-Sep-22
Actual
Inspection 1 01-Oct-22 01-Oct-22
Cleaning 1 01-Oct-22 01-Oct-22
Demobilization 1 03-Oct-22 03-Oct-22
Turn Over
25 days TOTAL PERCENT WEIGHT
Scheduled Costing
Item Scope of Work Project Cost Planned % Weight
Actual % Weight
I. REMOVAL OF EXISTING ROOF FRAMES ₱ 2,240.00 7 0.76 0.76
II. PARAPET WORKS ₱ 19,000.00 7 6.45
III. ROOF FRAME SUPPORT ₱ 5,000.00 7 1.70
IV. ROOF FRAME WORKS ₱ 121,460.00 7 41.22
V. ROOF COVER ₱ 135,182.50 7 45.88
VI. PAINTING WORKS-PARAPET WALL ₱ 11,765.00 7 3.99
TOTAL ₱ 294,647.50 7 100.00
Actual Schedule
Item Scope of Work Project Cost
I. REMOVAL OF EXISTING ROOF FRAMES ₱ 2,240.00
II. PARAPET WORKS ₱ 19,000.00
III. ROOF FRAME SUPPORT ₱ 5,000.00
IV. ROOF FRAME WORKS ₱ 121,460.00
V. ROOF COVER ₱ 135,182.50
VI. PAINTING WORKS-PARAPET WALL ₱ 11,765.00
TOTAL ₱ 294,647.50
10-Sep-22 16-Sep-22 21-Sep-22
Schedule % Finish
Percent Weight
Percent Weight
Actual Finish
Actual
Actual
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SK L S S M T W T F S S M T W T F S S M T
0.76% 0.76%
1 2
6.45%
1 1
1 2
1.70%
2 2
41.22%
2
45.88%
3.99%
100.00%
27-Sep-22 3-Oct-22
Remarks
Status
28 29 30 1 2 3 4 5 6 7 8
W T F S S M T W T F S
100% On-time
100% On-time
75%
Project I.D.: JMDC-2107
Project Location: Brgy.
Title: Myla Pagdaraoan,
Fernandez City
-Bungalow
of San Fernando La Union
Owner: Ms. Myla Fernandez
Project Start:
Project Finish:
MYLA BUNGALOW WORK CHECKLIST-REMAINING WORKS
Item Scope of Works Material & Labor Cost Priority Works Remarks