Sie sind auf Seite 1von 1

GENERAL FACILITIES CONSTRRUCTION AND MODIFICATION SERVICES

No.CONTRACK 4710006213
MUTIARA FIELD Planning 22 Juni 2023

NO LOCATION POB NAME POSISI PERALATAN DESCRIPTION


1 Yard PTM 1 Mat Sopingi SPV - Cutting torch - Pengelasan cheker plate
- Modifikasi WHC 2 Purnomo SPV - Grinding mechine - Painting top coat cheker plate
3 Abdul Kadir Welder - Hand tools
4 Hobirudin Adm.Logistik - Mesin Las 2 Unit
5 Darwis Helper - Cutting wheel
6 Arya Saputra Helper - Hilux
7 Suleman Rante Teknisi E/I - Bus
8 Muliadi Helper E/I
9 Mansur Driver Hilux

2 Yard PTM 1 Suprianto SPV - Mesin Las 1 Unit - Fabrikasi Walk Way & Handrail Phenol
- Fabrikasi Handrail Phenol 2 Abdul Haris Pipe Fitter - Grinder
3 Asroni Welder - Bus
4 Mahrus Grinder
5 Ahmat Rachmat Oprt. TMC
6 Andreansyah Rigger
7 Wahyu Saputra Helper
8 Abdul Hamim Driver Bus

3 Pamaguan Station 1 Suriansyah SPV - Mesin Las 1 Unit - Pemasangan chainlink


- Pembuatan Pagar Baru 2 Gusti Ahmad Prakoso Safetyman - Hand tools
3 Rico Asnaidi Welder - Cutting torch
4 Heriansyah Insp.Scaffolder - Grinder
5 Bahrullah Scaffolder - Pajero
6 Rudi Harianto Carpenter
7 Aditya Mahnur Helper
8 Angga Riadi Elektrik
9 Syaifullah Driver Pajero

Detail Progress 21 Juni 2023


Description Unit Progress Hari ini Total Progress Kendala Remaining
Install Handrail Phenol Kg - Install Handrail Phenol 60% - -

Modifikasi WHC Trailer Mutiara Unit - Install Solar Cell 97% - - Install solar cell dan Install E/I

- Pemasangan chainlink pagar


Penambahan Pagar Baru di Pamaguan Station Meter 92% - - 18 meter (Lokasi baru 35 meter)
baru

Fabrikasi Fuel Gas Scrubber di M8 Meter - 96% - - Koneksi Kabel ke Control Room

- Boom truck, Trailer, unit transport sewaktu waktu bisa berubah.


Note:
- Kepala kerja harap infokan keperluan material,consumable sehari sebelumnya di jam 15:00 sampai dengan Jam 16:00

TETAP SEHAT, semangat, dan selalu berhati hati.. SAFETY FIRST