No.CONTRACK 4710006213
MUTIARA FIELD Planning 22 Juni 2023
2 Yard PTM 1 Suprianto SPV - Mesin Las 1 Unit - Fabrikasi Walk Way & Handrail Phenol
- Fabrikasi Handrail Phenol 2 Abdul Haris Pipe Fitter - Grinder
3 Asroni Welder - Bus
4 Mahrus Grinder
5 Ahmat Rachmat Oprt. TMC
6 Andreansyah Rigger
7 Wahyu Saputra Helper
8 Abdul Hamim Driver Bus
Modifikasi WHC Trailer Mutiara Unit - Install Solar Cell 97% - - Install solar cell dan Install E/I
Fabrikasi Fuel Gas Scrubber di M8 Meter - 96% - - Koneksi Kabel ke Control Room