Sie sind auf Seite 1von 40

/ Perfect Charging / Perfect Welding / Solar Energy

Installationsanleitung
OPT/i WF Gasdüsen- DE

Positionssuchen Systemerweiterung

Installations instructions
OPT/i WF gas nozzle touch sensing
EN

System extension

Instructions d'installation
Fonction de recherche de position
FR

buses de gaz OPT/i WF Extension système

42,0410,1943 004-13122016
2
Inhaltsverzeichnis

DE
Allgemeines ............................................................................................................................................... 5
Lieferumfang ......................................................................................................................................... 5
Einbaulage ............................................................................................................................................ 5
Benötigtes Werkzeug............................................................................................................................ 6
OPT/i WF Gasdüsen-Positionssuchen in WF 15i/25i/30i R / SB 500i R einbauen .................................... 7
Sicherheit .............................................................................................................................................. 7
Vorbereitung ......................................................................................................................................... 8
OPT/i WF Gasdüsen-Positionssuchen einbauen.................................................................................. 8
Abschließende Tätigkeiten.................................................................................................................... 11
OPT/i WF Gasdüsen-Positionssuchen in SB 60i R einbauen.................................................................... 12
Sicherheit .............................................................................................................................................. 12
Vorbereitung ......................................................................................................................................... 12
OPT/i WF Gasdüsen-Positionssuchen einbauen.................................................................................. 13
Abschließende Tätigkeiten.................................................................................................................... 14

3
4
Allgemeines

DE
Lieferumfang
(1) Sensor

(2) 2 Schrauben TX 20
4 x 10 mm

(3) 2 Schrauben TX 20
(1) 5 x 25 mm

Ohne Abbildung:
diese Installationsanleitung

(2)

(3)

Einbaulage
OPT/i WF Gasdüsen-Positionssuchen kann bei folgenden Geräten eingebaut werden
- alle Varianten der Geräte WF 15i/25i/30i R und R PAP
- alle Varianten der Geräte SB 500i R und R PAP
- alle Varianten der Geräte SB 60i R

Der Einbau der Option wird wie folgt dargestellt:


- anhand des Roboter-Drahtvorschubes WF 30i R (gilt auch für SB 500i)
- anhand der SplitBox SB 60i R

Ist OPT/i WF Ausblasen 7 bar bereits im Gerät eingebaut, muss OPT/i WF Gasdüsen-
Positionssuchen auf der gegenüberliegen Seite von OPT/i WF Ausblasen 7 bar im Gerät
eingebaut werden. Unabhängig von der Montageseite im Gerät ist der Einbau wie be-
schrieben durchzuführen.

(1) (1)

(3) (2) (2) (3)

Ansicht der Geräte-Rückseite mit demontierter Ge- Ansicht der Geräte-Rückseite mit demontierter Ge-
häuseabdeckung häuseabdeckung

(1) Drahtvorschub / SplitBox


(2) OPT/i WF Ausblasen 7 bar
(3) OPT/i WF Gasdüsen-Positionssuchen

5
Benötigtes Werk- - Torx-Schraubendreher TX 20
zeug

6
OPT/i WF Gasdüsen-Positionssuchen in WF 15i/25i/
30i R / SB 500i R einbauen

DE
Sicherheit
WARNUNG! Fehlbedienung und fehlerhaft durchgeführte Arbeiten können
schwerwiegende Personen- und Sachschäden verursachen.
Alle in diesem Dokument beschriebenen Arbeiten und Funktionen dürfen nur von
geschultem Fachpersonal ausgeführt werden, wenn folgende Dokumente voll-
ständig gelesen und verstanden wurden:
- dieses Dokument
- sämtliche Bedienungsanleitungen der Systemkomponenten, insbesondere
Sicherheitsvorschriften

WARNUNG! Ein elektrischer Schlag kann tödlich sein. Vor Beginn der Arbeiten:
- Netzschalter der Stromquelle in Stellung - O - schalten
- Stromquelle vom Netz trennen
- sicherstellen, dass die Stromquelle bis zum Abschluss aller Arbeiten vom
Netz getrennt bleibt

Nach dem Öffnen des Gerätes mit Hilfe eines geeigneten Messgerätes sicher-
stellen, dass elektrisch geladene Bauteile (z.B. Kondensatoren) entladen sind.

VORSICHT! Verletzungsgefahr durch austretende Drahtelektrode. Ist ein Abs-


pul-Drahtvorschub im Schweißsystem vorhanden, vor Beginn der Arbeiten:
- Netzschalter des Abspul-Drahtvorschubes in Stellung - O - schalten
- Abspul-Drahtvorschub vom Netz trennen
- sicherstellen, dass der Abspul-Drahtvorschub bis zum Abschluss aller Arbei-
ten vom Netz getrennt bleibt

VORSICHT! Verletzungsgefahr durch heiße Systemkomponenten. Vor Beginn


der Arbeiten alle heißen Systemkomponenten auf Zimmertemperatur (+25 °C,
+77 °F) abkühlen lassen, beispielsweise:
- Kühlmittel
- wassergekühlte Systemkomponenten
- Antriebsmotor des Drahtvorschubes

7
Vorbereitung
1 Sämtliche Verbindungen des Gerätes von allen anderen Systemkomponenten tren-
nen
2 Gerät auf einer geeigneten Unterlage ablegen
3 4 Schrauben TX 20 (1) lösen
4 Abdeckung (2) öffnen
5 Gehäuseabdeckung (3) wie abgebildet vom Gerät abziehen

(1) (1)

(2)

(3)

(1) (1)

OPT/i WF Gasdü-
1 Sensor (1) wie abgebildet in das Gerät einsetzen und mittels Schraube TX 20 (2) an
sen-Positionssu-
der Position (3) festschrauben
chen einbauen

(3)
(2)

(1)

8
2 Sensor (1) mittels Schraube TX 20 (4) an der Position (5) festschrauben

DE
(1)

(4)
(5)

3 Den Flachstecker des Kabels (6) vom


(7) (6) Sensor (1) wie abgebildet an der
Strombuchse (7) des Gerätes anste-
cken

4 Stecker (8) und (9) von einander ab-


(8) (9) stecken

9
5 Vorkonfektioniertes Kabel (10) vom
(10) (8) Sensor (1) wie abgebildet in Anschluss
6 des Steckers (8) einstecken

5 6 7 8

6 Stecker (8) und (9) zusammenstecken


7 Sicherstellen, dass alle Kabel und
Schläuche im Geräteinnenraum ord-
(8) (9) nungsgemäß angeschlossen und ver-
legt sind

10
Abschließende

DE
HINWEIS! Beim Montieren der Gehäuseabdeckung sicherstellen, dass Kabel
Tätigkeiten
und Schläuche nicht geknickt, eingeklemmt, abgescheuert oder auf andere
Weise beschädigt werden.

1 Gehäuseabdeckung (3) wie abgebildet bis auf Anschlag auf das Gerät aufschieben
2 4 Schrauben TX 20 (1) festschrauben
3 Abdeckung (2) schließen
4 Gerät in seine Ausgangsposition bringen
5 Verbindungen mit anderen Systemkomponenten herstellen

(1) (1)

(2)

(3)

(1) (1)

11
OPT/i WF Gasdüsen-Positionssuchen in SB 60i R
einbauen

Sicherheit
WARNUNG! Fehlbedienung und fehlerhaft durchgeführte Arbeiten können
schwerwiegende Personen- und Sachschäden verursachen.
Alle in diesem Dokument beschriebenen Arbeiten und Funktionen dürfen nur von
geschultem Fachpersonal ausgeführt werden, wenn folgende Dokumente voll-
ständig gelesen und verstanden wurden:
- dieses Dokument
- sämtliche Bedienungsanleitungen der Systemkomponenten, insbesondere
Sicherheitsvorschriften

WARNUNG! Ein elektrischer Schlag kann tödlich sein. Vor Beginn der Arbeiten:
- Netzschalter der Stromquelle in Stellung - O - schalten
- Stromquelle vom Netz trennen
- sicherstellen, dass die Stromquelle bis zum Abschluss aller Arbeiten vom
Netz getrennt bleibt

Nach dem Öffnen des Gerätes mit Hilfe eines geeigneten Messgerätes sicher-
stellen, dass elektrisch geladene Bauteile (z.B. Kondensatoren) entladen sind.

VORSICHT! Verletzungsgefahr durch austretende Drahtelektrode. Ist ein Abs-


pul-Drahtvorschub im Schweißsystem vorhanden, vor Beginn der Arbeiten:
- Netzschalter des Abspul-Drahtvorschubes in Stellung - O - schalten
- Abspul-Drahtvorschub vom Netz trennen
- sicherstellen, dass der Abspul-Drahtvorschub bis zum Abschluss aller Arbei-
ten vom Netz getrennt bleibt

VORSICHT! Verletzungsgefahr durch heiße Systemkomponenten. Vor Beginn


der Arbeiten alle heißen Systemkomponenten auf Zimmertemperatur (+25 °C,
+77 °F) abkühlen lassen, beispielsweise:
- Kühlmittel
- wassergekühlte Systemkomponenten
- Antriebsmotor des Drahtvorschubes

Vorbereitung Der Einbau wird anhand einer rechten SB 60i R Geräteausführung beschrieben. Der Ein-
bau in eine linke SB 60i R Geräteausführung erfolgt analog dazu.

1 Sämtliche Verbindungen des Gerätes von allen anderen Systemkomponenten tren-


nen
2 Gerät vom Roboter abmontieren (4 x Innensechskant-Schraube M6 x 60 mm)
3 Gerät auf einer geeigneten Unterlage mit der durchsichtigen Abdeckung nach unten
ablegen

12
4 6 Schrauben TX25 (1) lösen
(1) 5 Abdeckung (2) abnehmen

DE
(1)

(1)
(1)

(2)

(1)

OPT/i WF Gasdü- Vorkonfektioniertes Kabel (4) vom


1
sen-Positionssu- Sensor wie abgebildet in Anschluss 6
chen einbauen des Steckers (5) einstecken

5 6 7 8

(3)
(4)

2 Gasschlauch (3) vom Magnetventil ab-


schließen
(5)

3 Sensor (7) wie abgebildet einsetzen


4 Sensor (7) mit 2 Schrauben TX20
5 x 25 mm fixieren
Anzugsmoment = 3 Nm
5 Flachstecker (8) wie abgebildet anste-
(6) cken
(7)

(6)

(8)

13
Abschließende Gasschlauch wieder am Magnetventil
1
Tätigkeiten anschließen
(1)
2 Abdeckung (2) einsetzen
3 Abdeckung mit 6 Schrauben TX25 (1)
(1) fixieren
Anzugsmoment = 3 Nm
(1)
(1)

(2)

(1)

4 Gerät am Roboter montieren (4 x Innensechskant-Schraube M6 x 60 mm)


5 Verbindungen mit den anderen Systemkomponenten herstellen

14
Contents
General ...................................................................................................................................................... 17
Scope of supply .................................................................................................................................... 17
Installation position ............................................................................................................................... 17
Tools required ....................................................................................................................................... 18

EN
Installing the OPT/i WF gas nozzle touch sensing in the WF 15i/25i/30i R / SB 500i R ............................ 19
Safety.................................................................................................................................................... 19
Preparations.......................................................................................................................................... 20
Installing the OPT/i WF gas nozzle touch sensing................................................................................ 20
And finally... .......................................................................................................................................... 23
Installing the OPT/i WF gas nozzle touch sensing in the SB 500i R.......................................................... 24
Safety.................................................................................................................................................... 24
Preparatory work................................................................................................................................... 24
Installing the OPT/i WF gas nozzle touch sensing................................................................................ 25
And finally... .......................................................................................................................................... 26

15
16
General

Scope of supply
(1) Sensor

EN
(2) 2 x TX20 screws
4 x 10 mm

(3) 2 x TX20 screws


(1) 5 x 25 mm

Not shown:
these Installation Instructions

(2)

(3)

Installation posi-
OPT/i WF gas nozzle touch sensing can be installed on the following devices
tion
- all variants of the WF 15i/25i/30i R and R PAP
- all variants of the SB 500i R and R PAP
- all variants of the SB 60i R

Installation of the option is outlined below:


- based on the WF 30i R robot wirefeeder (also valid for the SB 500i)
- based on the SplitBox SB 60i R

If OPT/i WF 7 bar gas purging is already installed in the device, OPT/i WF gas nozzle
touch sensing must be installed on the opposite side from the OPT/i WF 7 bar gas purging
option. The installation must be carried out as described, irrespective of the installation
side.

(1) (1)

(3) (2) (2) (3)

View of the rear of the device with housing cover re- View of the rear of the device with housing cover re-
moved moved

(1) Wirefeeder / SplitBox


(2) OPT/i WF 7 bar gas purging
(3) OPT/i WF gas nozzle touch sensing

17
Tools required - TX20 Torx screwdriver

18
Installing the OPT/i WF gas nozzle touch sensing in
the WF 15i/25i/30i R / SB 500i R

Safety

EN
WARNING! Incorrect operation or shoddy workmanship can cause serious injury
or damage.
All functions described in this document may only be carried out by trained and
qualified personnel after they have fully read and understood the following docu-
ments:
- this document
- all the operating instructions for the system components, especially the safe-
ty rules

WARNING! An electric shock can be fatal. Before starting work:


- turn the power source mains switch to the "O" position
- disconnect the power source from the mains
- ensure that the power source remains disconnected from the mains until all
work has been completed

After opening the device, use a suitable measuring instrument to check that elec-
trically charged components (e.g. capacitors) have been discharged.

CAUTION! Risk of injury from wire electrode emerging at speed. If the welding
system contains an unreeling wirefeeder, also carry out the following actions be-
fore starting work:
- turn the mains switch of the unreeling wirefeeder to the "O" position
- disconnect the unreeling wirefeeder from the mains
- ensure that the unreeling wirefeeder remains disconnected from the mains
until all work has been completed

CAUTION! Risk of scalding from hot system components. Before starting work,
allow all hot system components to cool down to room temperature (+25°C,
+77°F). For example:
- coolant
- water-cooled system components
- wirefeeder drive motor

19
Preparations
1 Disconnect all connections on the device from all other system components
2 Place the device on a suitable base
3 Undo four TX 20 screws (1)
4 Open cover (2)
5 Pull the housing cover (3) off the device as shown

(1) (1)

(2)

(3)

(1) (1)

Installing the
1 Insert the sensor (1) into the device as shown and secure in position (3) using a TX
OPT/i WF gas
20 screw (2)
nozzle touch
sensing

(3)
(2)

(1)

20
2 Screw the sensor (1) to position (5) using a TX 20 screw (4)

EN
(1)

(4)
(5)

3 Insert the blade terminal on the cable


(7) (6) (6) from the sensor (1) into the current
socket (7) of the device as shown

4 Disconnect the two plugs (8) and (9)


(8) (9)

21
5 Insert the pre-assembled cable (10)
(10) (8) from the sensor (1) into connection 6 of
the plug (8) as shown

5 6 7 8

6 Connect plugs (8) and (9)


7 Ensure that all cables and hoses inside
the device are connected and routed
(8) (9) correctly

22
And finally...
NOTE! When fitting the housing cover, ensure that the cables and hoses are not
kinked, trapped, sheared or damaged in any way.

1 Push housing cover (3) as far as it will go onto the device as shown

EN
2 Tighten the four TX 20 screws (1)
3 Close the cover (2)
4 Return the device to its original position
5 Establish connections to other system components

(1) (1)

(2)

(3)

(1) (1)

23
Installing the OPT/i WF gas nozzle touch sensing in
the SB 500i R

Safety
WARNING! Incorrect operation or shoddy workmanship can cause serious injury
or damage.
All functions described in this document may only be carried out by trained and
qualified personnel after they have fully read and understood the following docu-
ments:
- this document
- all the operating instructions for the system components, especially the safe-
ty rules

WARNING! An electric shock can be fatal. Before starting work:


- turn the power source mains switch to the "O" position
- disconnect the power source from the mains
- ensure that the power source remains disconnected from the mains until all
work has been completed

After opening the device, use a suitable measuring instrument to check that elec-
trically charged components (e.g. capacitors) have been discharged.

CAUTION! Risk of injury from wire electrode emerging at speed. If the welding
system contains an unreeling wirefeeder, also carry out the following actions be-
fore starting work:
- turn the mains switch of the unreeling wirefeeder to the "O" position
- disconnect the unreeling wirefeeder from the mains
- ensure that the unreeling wirefeeder remains disconnected from the mains
until all work has been completed

CAUTION! Risk of scalding from hot system components. Before starting work,
allow all hot system components to cool down to room temperature (+25°C,
+77°F). For example:
- coolant
- water-cooled system components
- wirefeeder drive motor

Preparatory work Installation is described based on the right-hand version of the SB 60i R. Installation of the
left-hand version of the SB 60i R is carried out in the same way.

1 Disconnect all connections on the device from all other system components
2 Detach the device from the robot (4 x Allen screws M6 x 60 mm)
3 Place the device on a suitable base with the transparent cover facing down

24
4 Undo the six TX25 screws (1)
(1) 5 Remove cover (2)

(1)

EN
(1)
(1)

(2)

(1)

Installing the Insert the pre-assembled cable (4)


1
OPT/i WF gas from the sensor into connection 6 of
nozzle touch the plug (5) as shown
sensing

5 6 7 8

(3)
(4)

2 Disconnect the gas hose (3) from the


solenoid valve
(5)

3 Fit the sensor (7) as shown


4 Secure the sensor (7) using two
5 x 25 mm TX20 screws
Tightening torque = 3 Nm
5 Connect the tab connector (8) as
(6) shown
(7)

(6)

(8)

25
And finally... Reconnect the gas hose to the sole-
1
(1) noid valve
2 Fit the cover (2)
3 Secure the cover with six TX25 screws
(1) (1)
Tightening torque = 3 Nm
(1)
(1)

(2)

(1)

4 Fit the device to the robot (4 x Allen screws M6 x 60 mm)


5 Establish connections to the other system components

26
Sommaire
Généralités................................................................................................................................................. 29
Contenu de la livraison ......................................................................................................................... 29
Emplacement de montage .................................................................................................................... 29
Outillage nécessaire ............................................................................................................................. 30
Installer l'option de recherche de position buses de gaz OPT/i WF en WF 15i/25i/30i R / SB 500i R....... 31
Sécurité................................................................................................................................................. 31
Préparation ........................................................................................................................................... 32
Installer l'option de recherche de position buses de gaz OPT/i WF...................................................... 32
Opérations finales ................................................................................................................................. 35

FR
Installer l'option de recherche de position buses de gaz OPT/i WF en SB 500i R .................................... 36
Sécurité................................................................................................................................................. 36
Préparation ........................................................................................................................................... 36
Installer l'option de recherche de position buses de gaz OPT/i WF...................................................... 37
Étapes finales ....................................................................................................................................... 38

27
28
Généralités

Contenu de la li-
vraison (1) Capteur

(2) 2 vis TX 20
4 x 10 mm

(3) 2 vis TX 20
(1) 5 x 25 mm

FR
Sans illustration :
les présentes Instructions d'installation

(2)

(3)

Emplacement de
L'option de recherche de position des buses de gaz OPT/i WF peut être installée sur les
montage
appareils suivants
- toutes les variantes des appareils WF 15i/25i/30i R et R PAP
- toutes les variantes des appareils SB 500i R et R PAP
- toutes les variantes des appareils SB 60i R

L'installation de l'option est représentée comme suit :


- à l'aide du dévidoir pour robot WF 30i R (valable également pour SB 500i)
- à l'aide de la SplitBox SB 60i R

Si le soufflage OPT/i WF 7 bar est déjà monté dans l'appareil, l'option de recherche des
buses de gaz OPT/i WF doit être montée sur le côté opposé dans l'appareil. Indépendam-
ment du côté de montage dans l'appareil, l'installation doit être effectuée comme décrit
ci-après.

(1) (1)

(3) (2) (2) (3)

Vue de la face arrière de l'appareil avec capot du Vue de la face arrière de l'appareil avec capot du
boîtier démonté boîtier démonté

(1) Dévidoir/SplitBox
(2) Soufflage OPT/i WF 7 bar
(3) Option de recherche de position buses de gaz OPT/i WF

29
Outillage néces- - tournevis Torx TX 20
saire

30
Installer l'option de recherche de position buses de
gaz OPT/i WF en WF 15i/25i/30i R / SB 500i R

Sécurité
AVERTISSEMENT ! Les erreurs de commande et les erreurs en cours d'opéra-
tion peuvent entraîner des dommages corporels et matériels graves.
L'ensemble des opérations et travaux décrits dans le présent document ne
doivent être effectués que par du personnel qualifié ayant lu et compris l'intégra-
lité des documents suivants :

FR
- le présent document
- toutes les Instructions de service des composants périphériques, en particu-
lier les consignes de sécurité

AVERTISSEMENT ! Une décharge électrique peut être mortelle. Avant d'enta-


mer les travaux :
- placer l'interrupteur secteur de la source de courant en position - O -,
- débrancher la source de courant du secteur,
- s'assurer que la source de courant reste déconnectée du secteur pendant
toute la durée des travaux.

Après ouverture de l'appareil, s'assurer, à l'aide d'un appareil de mesure appro-


prié, que les composants à charge électrique (condensateurs, par ex.) sont dé-
chargés.

ATTENTION ! Risque de blessure si le fil-électrode sort. Si un dévidoir de débo-


binage est disponible dans l'installation de soudage, avant d'entamer les travaux :
- commuter l’interrupteur du dévidoir de débobinage en position - O -,
- débrancher le dévidoir de débobinage du secteur,
- s'assurer également que le dévidoir de débobinage restera déconnecté du
secteur pendant toute la durée des travaux.

ATTENTION ! Risque de blessure dû aux composants périphériques chauds.


Avant de débuter les travaux, laisser les composants périphériques refroidir à
température ambiante (+25 °C, +77 °F) notamment :
- le réfrigérant,
- les composants périphériques refroidis à l'eau,
- le moteur entraînant le dévidoir.

31
Préparation
1 Débrancher toutes les connexions de l'appareil avec les autres composants périphé-
riques
2 Placer l'appareil sur un support adapté
3 Desserrer les 4 vis TX 20 (1)
4 Ouvrir le capot (2)
5 Retirer le capot du boîtier (3) comme illustré

(1) (1)

(2)

(3)

(1) (1)

Installer l'option
1 Placer le capteur (1) dans l'appareil comme indiqué sur l'illustration et le visser en
de recherche de
position (3) à l'aide d'une vis TX 20 (2)
position buses de
gaz OPT/i WF

(3)
(2)

(1)

32
2 Visser le capteur (1) en position (5) à l'aide d'une vis TX 20 (4)

(1)

(4)
(5)

FR
3 Raccorder le connecteur plat du câble
(7) (6) (6) du capteur (1) au connecteur (7) de
l'appareil comme indiqué sur l'illustrati-
on

4 Débrancher les connecteurs (8) et (9)


(8) (9) l'un de l'autre

33
5 Raccorder le câble préconfectionné
(10) (8) (10) du capteur (1) au raccord 6 du
connecteur (8) comme indiqué sur l'il-
lustration

5 6 7 8

6 Raccorder les connecteurs (8) et (9)


ensemble
7 S'assurer que tous les câbles et tuyaux
(8) (9) à l'intérieur de l'appareil sont correcte-
ment positionnés et raccordés

34
Opérations fi-
REMARQUE! Lors du montage du capot du boîtier, veiller à ce que le câble et
nales
le tuyau ne soient pas coincés, coudés, usés ou endommagés de toute autre
manière.

1 Pousser le capot du boîtier (3) sur l'appareil comme indiqué sur l'illustration jusqu'à
la butée
2 Visser les 4 vis TX 20 (1)
3 Fermer le capot (2)

FR
4 Replacer l'appareil dans sa position initiale
5 Rétablir la connexion avec les autres composants périphériques

(1) (1)

(2)

(3)

(1) (1)

35
Installer l'option de recherche de position buses de
gaz OPT/i WF en SB 500i R

Sécurité
AVERTISSEMENT ! Les erreurs de commande et les erreurs en cours d'opéra-
tion peuvent entraîner des dommages corporels et matériels graves.
L'ensemble des opérations et travaux décrits dans le présent document ne
doivent être effectués que par du personnel qualifié ayant lu et compris l'intégra-
lité des documents suivants :
- le présent document
- toutes les Instructions de service des composants périphériques, en particu-
lier les consignes de sécurité

AVERTISSEMENT ! Une décharge électrique peut être mortelle. Avant d'enta-


mer les travaux :
- placer l'interrupteur secteur de la source de courant en position - O -,
- débrancher la source de courant du secteur,
- s'assurer que la source de courant reste déconnectée du secteur pendant
toute la durée des travaux.

Après ouverture de l'appareil, s'assurer, à l'aide d'un appareil de mesure appro-


prié, que les composants à charge électrique (condensateurs, par ex.) sont dé-
chargés.

ATTENTION ! Risque de blessure si le fil-électrode sort. Si un dévidoir de débo-


binage est disponible dans l'installation de soudage, avant d'entamer les travaux :
- commuter l’interrupteur du dévidoir de débobinage en position - O -,
- débrancher le dévidoir de débobinage du secteur,
- s'assurer également que le dévidoir de débobinage restera déconnecté du
secteur pendant toute la durée des travaux.

ATTENTION ! Risque de blessure dû aux composants périphériques chauds.


Avant de débuter les travaux, laisser les composants périphériques refroidir à
température ambiante (+25 °C, +77 °F) notamment :
- le réfrigérant,
- les composants périphériques refroidis à l'eau,
- le moteur entraînant le dévidoir.

Préparation L'installation est décrite selon le modèle d'appareil SB 60i R droit. L'installation dans un
modèle d'appareil SB 60i R gauche s'effectue de façon similaire.

1 Débrancher toutes les connexions de l'appareil avec tous les autres composants pé-
riphériques
2 Démonter l'appareil du robot (4 x vis à tête à six pans creux M6 x 60 mm)
3 Poser l'appareil sur un support adapté avec le cache transparent vers le bas

36
4 Desserrer les 6 vis TX25 (1)
(1) 5 Retirer le cache (2)

(1)

(1)
(1)

(2)

FR
(1)

Installer l'option Raccorder le câble préconfectionné (4)


1
de recherche de du capteur au raccord 6 du connecteur
position buses de (5) comme indiqué sur l'illustration
gaz OPT/i WF

5 6 7 8

(3)
(4)

2 Déconnecter le tuyau de gaz (3) de


l'électrovanne
(5)

3 Mettre le capteur (7) en place comme


indiqué sur l'illustration
4 Fixer le capteur (7) avec les 2 vis TX20
5 x 25 mm
Couple de serrage = 3 Nm
(6) Raccorder le connecteur plat (8) com-
5
(7) me indiqué sur l'illustration

(6)

(8)

37
Étapes finales Raccorder à nouveau le tuyau de gaz
1
(1) à l'électrovanne
2 Remettre le cache (2) en place
3 Fixer le cache avec 6 vis TX25 (1)
(1) Couple de serrage = 3 Nm

(1)
(1)

(2)

(1)

4 Monter l'appareil sur le robot (4 x vis à tête à six pans creux M6 x 60 mm)
5 Rétablir la connexion avec les autres composants périphériques

38
FR

39
FRONIUS INTERNATIONAL GMBH
Froniusplatz 1, A-4600 Wels, Austria
Tel: +43 (0)7242 241-0, Fax: +43 (0)7242 241-3940
E-Mail: sales@fronius.com
www.fronius.com

www.fronius.com/addresses
Under http://www.fronius.com/addresses you will find all addresses
of our Sales & service partners and Locations

Das könnte Ihnen auch gefallen